all chapters Flashcards
(43 cards)
The problem which deals with the distribution of goods from several sources to several destinations is the
transportation problem
the parts of a network that represent the origins are
the nodes
the number of units shipped from origin i to destination j is respresented by
Xij
IN a transshipment formulation in which you have two plants shipping centers three in turn can ship to any one of six customer zones, the number of constraints is
11
IF you have a transportation problem in which the total supply is greater than the total demand,you will need to
make no additional changes
The difference between the transportation and assignment problems is that
each supply and demand value is 1 in the assignment problem
which of the following is not true regarding an LP model of the assignment problem
all constraints are of the > or equal too form
if a transportation problem has four origin and five destinations, the LP formulation of the problem will have
9 constraints
the assignment problem constraint x31+x32 +x33+x34
agent 3 can be assigned to 1 task
consider a shortest route problem in whcih a bank courier must travel between branches and the main operations center. When represented with a network,
the branches and the operations center are all nodes and the streetsare the arcs.
THe shortest route problme finds the shortest-route
from the source to any other note
rounding the solution of an lp relaxation to the nearest integer values provide s
an integer solution that might be neither feasible nor optimal
Let x1, x2, and x3 be 0-1 variables whose values indidcate whether the projects are not done(0) or are done(1). Which answer below indicatest hat at least two of the projects must be done?
X1+X2+x3 >2
In an all-integer linear program,
all variables must be integer
most practical applications of integer linear programming involve
only 0-1 integer variables and not ordinary integer variables
project management differs from management of more traditional day-to-day activities because:
it has limited time frame
Arcs in a project network indicate
prrecedence relationships
The critical path is the _____ path through the network
longest
IF an activity cannot be delayed without affecting the entire project, then it is a _____ activity
critical
A PERT/CPM activity has an optimistic time estimate of 4 days, a most likely time estimate of 6 days, and a pessimistic time estimate of 10 days. the expected time is
6.33
When activity times are uncertain
calculate the expected time, using (a+4m+b)/6
To determine how to crash activity times
all of the alternatives are true
In deciding which activities to crash, one must
crash activities on the critical paths only
_____ demand items are final products demanded by an external customer.
independent