All Words Flashcards
(143 cards)
What is “Acceptance Criteria”?
A set of conditions that are met before deliverables are accepted by the customers or sponsors.
What is “Activity”?
A distinct, scheduled portion of work performed during the project. Usually stored on the activity list.
What is “Actual Cost (AC)”?
The actual cost incurred for the work performed on an activity during a specific time period.
What is “Analogous Estimating”?
A technique for estimating the duration or cost of an activity or a project using historical data from a similar activity or project. Also known as top-down estimating.
What is “assumption”?
A factor in the planning processes considered to be true or real without proof or demonstration.
What is a “backward pass”?
A critical path method technique for computing the late start and late finish dates by working backward through the schedule model from the project end date.
What is “baseline”?
The accepted version of a work product which can be changed using formal change control processes and is used as the basis for comparison to actual results.
What is “bottom-up estimating”?
A method of estimating project duration or cost by aggregating the estimates for the lower-level components of the “work breakdown structure (WBS)”?
What is “change control”?
A process whereby changes to documents, deliverables, or baselines related to the project are identified, documented, approved, or rejected.
What is a “change control board”?
A formally commissioned group responsible for reviewing, assessing, approving, deferring, or rejecting changes to the project, and for recording and communicating such decisions.
What is a “change control system”?
A set of procedures that defines how modifications to the project deliverables and documentation are managed and controlled.
What is a “change report”?
A formal proposal to change any document, deliverable, or baseline in the project management plan.
What is a “communication management plan”?
A component of the project management plan that describes how, when, and by whom information will be administered and distributed.
What is a “configuration management system”?
A collection of procedures used to track project artifacts and monitor and control changes to these artifacts.
What is a “constraint”?
A restrictive feature that affects the execution of a project.
What is a “contingency reserve”?
Time or money assigned in the schedule or cost baseline for known risks with response strategies.
What is a “corrective action”?
A planned activity that restores the performance of the project work with the project management plan.
What is a “cost baseline”?
The approved version of work packages cost estimates and contingency reserve that can be changed using formal change control procedures.
What is a “cost management plan”?
A component of a project management plan that defines how costs will be planned and controlled.
What is the “cost performance index (CPI)”?
A measure of the cost efficiency of budgeted resources is expressed as the ratio of earned value and the actual cost.
What is “cost variance (CV)”?
The amount of budget shortfall or surplus at a given point in time, which is expressed as a difference between the earned value and the actual cost.
What is “crashing”?
A schedule compression technique used to shorten the schedule duration by adding resources. This will generally increase the cost of the project.
What is the “critical chain method”?
A schedule method that allows the project team to place buffers on any project schedule path to account for limited resources.
What is the “critical path”?
The sequence of activities that represents the longest path through a project, which determines the shortest and longest possible duration. Activities on the critical path have no float.