api-570_20150909133250 Flashcards

(412 cards)

1
Q

Code to follow when performing an internal inspection on pipe

A

API 510 570: 5.5.1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Positive Material Identification (PMI)

A

API 578 570: 5.9

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Fitness for Service (FFS)

A

API 579 570: 7.4

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Risked Based Inspection (RBI)

A

API 580 570: 5.2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Valve Inspection and Testing

A

API 598 570: 5.10

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Cathodic Protection

A

API 651 570: 9.3.5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Welding on In-Service Equipment containing Flammables

A

API 2205 570: 8.2.1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

NDE Procedure Guidelines

A

ASME Sect V B31.3: 343

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Design code for fabrication of piping relief devices

A

ASME Sect 8 B31.3: 322.6.3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Welder & Weld Procedure Qualification

A

ASME Sect 9 B31.3: 328.2.1.a

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

NDE Personnel Qualification

A

ASNT SNT-TC-1A B31.3: 342.1 Note

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

When fitting up a socket weld joint the male end is welded in the female socket with

A

An approx 1/16” gap at the base of the joint

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

The zone for preheat shall extend

A

At least 1 inch beyond each edge of the weld

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Where a hardness limit is specified in table 33 1.1.1 at least ________% of welds, hot bends, and hot formed components in each furnace heat treated batch and 100% of those locally heat-treated shall be tested

A

10

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is acceptable as an alternate heat treatment

A

Normalizing, normalizing and tempering, or annealing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

When an entire piping assemble is to be heat treated cannot fit into the furnace, it is permissible to heat treat in more than one heat treat, provided there is at least _______ overlap between successive heats, and that the parts of the assembly outside the furnace are protected from harmful temp gradients

A

1 foot

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Flattening of a bend, the difference between maximum and minimum diameter’s at any cross-section, shall not exceed _______% on nominal outside diameter for internal pressure

A

8

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Flattening of a Bend, the difference between maximum and minimum diameter’s at any cross-section, shall not exceed ________% on nominal outside diameter for external pressure

A

3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Flanged joints: Before bolting, mating gaskets contact surfaces should be within ________ in/ft, measured across any Dia.

A

16-Jan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Flange Bolt holes should be aligned within ______ max offset

A

1/8 in.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Bolts should extend completely through their nuts. Any which failed to do so or considered acceptably engaged if the lack of complete engagement is not more then

A

One thread

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

How many gaskets shall be used between Contacts faces in the Assembling a flanged joint

A

No more than one gasket

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

What is the minimum time that a leak tests must be maintained

A

10 minutes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

ASME code is not intended to apply to piping:

A

That has been placed in service

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Compatibility of materials with the service and hazards from instability of contained fluids:
Are not within the scope of ASME B31.3
26
A fluid service that is nonflammable non-toxic and not damaging to human tissue and it's gage pressure does not exceed 150 psi in the design temperature from -20° through 366°F is known as category
D
27
A fluid service in which the potential personal exposure is judged to be significant any which a single exposure to a very small quantity of toxic fluid caused by leakage can produce serious in reversible harm persons on breathing or bodily contact even when prompt restorative measures are taken is known as category
M
28
The heating of metal to and holding at a suitable temperature and then cooling at a suitable rate for such purposes as reducing hardness improving machinability facilitating cold working producing a Desired microstructure or obtaining desired mechanical physical or other properties is known as
Annealing
29
What might happen to a piping system that has a gas or vapor in it " like steam" and it is allowed to cool significantly
The pressure in the piping system may reduce sufficiently to create an internal vacuum
30
What happens to a piping system that has fluids in it and the fluids are heated with the system blocked
The internal pressure will increase
31
Loads on a piping system that include the weight of the medium transported or the medium used for test and snow loads or ice loads or examples of -______ loads
Live
32
When the service is erosive if there is crevice corrosion present or if cyclic loadings occur slip on flanges shall
Be double welded
33
The use of slip on flanges should be ________ where many large temperature cycles or expected particularly if the flanges or not insulated
Avoided
34
Unless save guarded, flanges is severe cyclic service conditions or limited to
Welding neck flanges
35
Bolting having not more than __________ ksi specified minimum yield Strength shall not be used for flange joints rated ASME B16.5 class 400 and higher
30
36
Tapped holes for pressure retaining bolting in metallic piping components shall be of sufficient depth that the thread engagement will be at least __________ Times the nominal thread diameter
8-Jul
37
What type of backing rings shall not be used under severe cyclic conditions
Split backing rings
38
Socket weld joints should be avoided in any service where ________ or _________ occur
Crevice corrosion , severe erosion
39
Socket weld's larger than NPS _______ shall not be used under severe cyclic conditions
2
40
Where flanges of different ratings are bolted together
The rating of the joint shall not exceed that of the lower rated flange
41
Where a metallic flange is bolted to a nonmetallic flange
Both should be flat-faced
42
Where a metallic flange is bolted to a nonmetallic flange
A fullface gasket is preferred
43
What type of joint should not be used under severe cyclic conditions
Expanded joints
44
Threaded joints should be avoided in any service where
Crevice corrosion, severe erosion, or cyclic loadings may occur
45
What is an example of a straight threaded joint
An union comprising male and female ends joined with a threaded union nut
46
Poisons ratio may be taken as _______ at all temperatures for all metals
0.3
47
For a liquid thermal expansion relief device which protects only a blocked in portion of piping system the set pressure shall not exceed the lesser of the system test pressure or ______% of design
120
48
Physical change of the piping component that has design applications affecting the pressure containing capabilities of flexibility of the piping system is an
Alteration
49
And imperfection of a type of magnitude exceeding the acceptable criteria
Defect
50
An __________ could be flaws or other types of discontinuities that were discovered during inspection that might be subject to some code acceptance criteria during further analysis
Imperfections
51
MDMT is the __________. __________ at which a significant pressure load can be applied to piping system as defined in applicable construction code
Lowest temperature
52
Injection points subject to accelerated or localized corrosion may be treated as
Separate inspection circuits
53
Pressure relieving devices should be tested and inspected at
Frequent enough intervals to make sure the PRDs perform reliably in service
54
Barlow formula for t
t= PD/2SE
55
Remaining life formula
t actual - t required / corrosion rate
56
Long term corrosion rate formula
t initial - t actual / years between
57
Short term corrosion rate
t previous - t actual / years in between
58
Any welding conducted on piping components in operation must be done in accordance with
API publication 2201
59
All repair and alteration welding to piping systems shall be done in accordance with the
Principles of ASME B31.3 or the code to which it was built
60
How often should cathodically protective buried piping be monitored to assure adequate levels of protection
Regularly
61
How often should above grade visual surveillance of a buried pipeline right-of-way be made
Approximately six month intervals
62
How often should poorly coated pipes with inconsistent cathodic protection potentials have a pipe to soil potential survey made
Every five years
63
The leak test for buried piping should be for a period of
Eight hours
64
Barlow formula for MAWP
MAWP= 2SET / D. T is projected thickness
65
Services with the highest potential of resulting in an immediate emergency if it leak were to occur are in class
1
66
Services not included in other classes or in class? This classification includes the majority of unit process piping and selected offsite piping
2
67
Services that are flammable but do not significantly vaporize when they leak and are not located in high activity areas or in class? Services that are potentially harmful to human tissue but are located in remote areas may be included in this class
3
68
Services that are essentially nonflammable and non-toxic or in class? As are most utility services. Inspections of this class of piping is optional and usually based on reliability needs and business impacts as opposed to safety or environmental impact
4
69
API 574 is
Inspection practices for piping systems components
70
Piping normally made by rolling plates to size and welding the seams is a larger then
16 NPS
71
Steel and alloy piping or manufactured to standard dimensions and normal pipe sizes up to
48 inches
72
Steel and alloy piping or also manufactured to standard thickness is designated as schedules in normal pipe sizes up to
36 inches
73
Gas piping has thickness tolerance of +_______ inch and - ________ inch
1/16, 0
74
For all nominal pipe sizes of _________ inches and smaller, the size refers to the nominal inside diameter
12
75
Under tolerance of welded pipe often used in refinery service is
0.010 inch
76
Tubing is generally seamlessly drawn, but it may be welded. It's stated size is it's actual
Outside diameter
77
The basic types of valves
Gate, globe, plug, ball, diaphragm, butterfly, check, and slide valves
78
Minimum thickness without corrosion allowance, based on structural and other loadings. The thickness is either determined from the standard chart or engineering calculations. It does not include thickness for corrosion allowance or mill tolerance
Structural minimum thickness
79
API RP 571 is
Damage mechanisms affecting fixed equipment in the refining industry
80
Article 2
Radiographic examination
81
Article 4
Ultrasonic examination
82
Article 6
Liquid penetrant
83
Article 7
Magnetic particle
84
Article 9
Visual examination
85
Article 10
Leak testing
86
Are class 200 flanges included in the standard
No
87
Are temperature markings required on all flanges
No
88
Bolting material having no more than 30 KS I specified Minimum yield strength or considered
Low strength
89
Class 400, 600, 900, 1500 and 2500 pipe flanges and companion flanges of fittings are regularly finished with _________ raised face
0.25
90
Class 150 and 300 pipe flanges and companion flanges of fittings or regularly finished with ______ raised face
0.06 in.
91
Flange Bolt holes are in multiples of
4
92
A flanged joint is composed of three interrelated components
The flanges, gasket, and bolting
93
At temperatures above 400° for class 150 and above 750° for other class designations flanged joints may
Develop leakage problems
94
When class 300 steel flanges are bolted to class 250 cast iron flanges what gasket should be used
Group No. Ia
95
ASME B16.5 covers flanges through NPS
24
96
ASME B16.47 covers the total range of larger flanges in size range NPS
26 through 60
97
API 570 Scope (Alteration, Inspection, Repair, Rerate)
AIRR 570: 1.1.1
98
API 570 Repair Organization (authorized by Jurisdiction, Owner, Contractor)
JOC 570: 3.1.79
99
API 570 AI’s Employer (Jurisdiction, User, Insurance company, Contractor)
JUIC 570: 3.1.6
100
Determine Corrosion Rate for New Service or Change in Service (Same or Similar Service, Owner’s Experience, Published Data, or Inspect in 3 months)
SOPI 570: 7.1.2
101
Primary responsibilities of API 570 AI (Testing, Inspection, Examination)
TIE 570: 4.3.4
102
Define Alteration
Physical Change 570: 3.1.2
103
Define Repair
Restore - Suitable 570: 3.1.78
104
Define Imperfection that exceeds the acceptance criteria
Defect 570: 3.1.17
105
Define Discontinuity that may or may not exceed the acceptance criteria
Imperfection 570: 3.1.30
106
Define RBI's two Primary Factors
Probability-Consequence 570: 5.2
107
NDE - Number of CMLs to obtain thickness readings during inspection
Represent- active 570: 6.5
108
NDE - CML that must be measured during a Thickness Inspection
CML w/ earliest renewal date 570: 6.5
109
How relief device intervals are determined
Performance 570: 6.7.3.1
110
Insp - Basis of API 570's Piping Classification
Consequence of failure 570: 6.3.1
111
Corrosion - Method by which process leaks can lead to brittle failure
Auto-refigeration 570: 6.3.4.2.a
112
Corrosion - Cause for fatigue crack
Cyclic Stress 574: 7.4.10.1
113
Corrosion - Factors that affect the creep rate
Time, Temp, & Stress 574: 7.4.11.1
114
Corrosion - Type of soil that is most corrosive
Low Resistivity 570: 9.2.4
115
Repairs - # of new flange assemblies to be inspected during repairs and alteration
Represent- active 570: 5.12
116
SCC can develop at hot spots, including where the heat tracing attaches to pipe
Caustic 574: 7.4.6.2.n
117
Where dew point corrosion often occurs
Overhead fractionation 574: 7.4.6.2.b
118
Potential for none or very few CMLs on circuit
Olefin cold side, Anhydrous ammonia 570: 5.6.2
119
Relatively uniform corrosion
Sulfidation, Sour water 570: 5.6.3
120
Valves that should be inspected for thermal fatigue
Cat Reformer 570: 5.10
121
Design - Mill tolerance for rolled and welded pipe
-0.010” 574: 4.1.1.3
122
NDE - Maximum length of Crack, or Incomplete Fusion allowed on a new weld
0” B31.3: Tbl 341.3.2
123
Flanges - Typical flange face finish
125-250 micro-inch B16.5: 6.4.5.3
124
Flanges - When mating flanges, the maximum amount of unparallel allowed (per diameter of flange in feet)
1/16” per foot B31.3: 335.1.c.1
125
Flanges - Max offset for bolt-holes for mating flanges
1/8” B31.3: 335.1.c.3
126
Welding - Maximum allowed size of open discontinuity in a Bend Test
1/8” ASME IX: QW-163
127
Preheat Zone - Distance from toe of weld
1” B31.3: 330.1.4
128
PWHT Zone - Distance from toe of weld
1” B31.3: 331.2.6
129
NDE - Minimum distance beyond the area to be examined to clean a part when performing a MT examination
1” ASME V: T-741.1.b
130
NDE - Minimum distance beyond the area to be examined to clean a part when performing a PT examination
1” ASME V: T-642.b
131
Repairs - Minimum radius of insert patch
1” 570: 8.1.4.2.c
132
Repairs - Minimum radius of insert patch
1” 570: Fig C.2
133
NDE - Max diameter of CML exam point for lines
2” 570: 3.1.20
134
NDE - Max diameter of CML exam point for lines > 10 NPS
3” 570: 3.1.20
135
NDE - Minimum length of Spot RT
6” B31.3: 344.5.2.c
136
Welding - Min length to RT/UT when qualifying a welder with test coupon or 1st production weld
6” ASME IX: QW-302.2/ 304.1
137
Welding - Minimum length of RT when qualifying a welding operator with a test coupon
6” ASME IX: QW-302.2
138
Corrosion - Soil-to-Air area – distance in air from interface
6” 570: 3.1.87
139
Corrosion - Distance to dig when inspecting for Soil-to-Air corrosion
6-12” 574: 7.4.5
140
NDE - Distance of eye-to-part to count as a Visual Exam
6-24” 577: 9.3.1.e
141
Corrosion - Soil-to-Air area – distance in soil from interface
12” 570: 3.1.87
142
NDE - Minimum upstream limit of intensive examination of injection point circuit
12” 570: 5.5.9
143
PWHT - Min overlap for PWHT when using multiple heats
12” B31.3: 331.2.5
144
Welding - Minimum length of RT/UT when qualifying a welding operator on first production weld
3’ ASME IX: QW-305.1
145
Underground - Minimum length of buried pipe to expose when excavating for inspection
6-8’ 570: 9.3.6
146
Repairs - Maximum size of fillet weld patch on pipe
½ Diameter 570: Fig C.2
147
Circuits - Minimum upstream limit of injection point circuit
Greater of: 12” or 3 Dia. 570: 5.5.9
148
NDE - Minimum downstream limit of intensive examination of injection point circuit
10 Diameters 570: 5.5.9
149
Circuits - Min downstream limit of injection point circuit
Lesser of:1st direction change + 25’or2nd direction change 570: 5.5.9
150
Corrosion - CUI affects Carbon Steel & low alloy (temperature range)
10 - 350 F 574: 7.4.4.1.e
151
UT Calibration - Calibration Block must be within what temperature of the part to be examined
25 F 577: 9.9.1
152
NDE - Standard temperature range for a PT exam
40 - 125 F V: T-652/653
153
Testing - Min flash point of hydrocarbons used for leak testing
120 F 570: 5.8.1
154
Corrosion - CUI affects Austenitic Stainless Steel (temperature range)
120 - 400 F 574: 7.4.4.1.h
155
Corrosion - Typical dew point of hydrochloric acid
130 F 571: 4.3.7.3.d
156
Corrosion - Temperature where chloride stress corrosion cracking becomes a concern
> 140 F 571: 4.5.1.3.g
157
NDE - Special procedures needed for UT thickness readings
> 150 F 570: 5.7.1
158
Corrosion - Temperature swings that can cause thermal fatigue
+/- 200 F 571: 4.2.9.3.c
159
Corrosion - Most aggressive CUI temperature range
212–350 F 571: 4.3.3.3.b
160
Corrosion - Typical dew point of sulfuric acid
280 F 571: 4.3.7.3.c
161
Welding - Minimum pre-heat temperature, when pre-heat is substituted for PWHT
300 F 570: 8.2.3.2
162
Welding - Minimum pre-heat temperature, when a local PWHT is substituted for a full encirclement PWHT
300 F 570: 8.2.3.3.c
163
Corrosion - Starting temp for Sulfidation on Carbon Steel per API 574
450 F 574: 7.4.6.2.j
164
Corrosion - Starting temp for Sulfidation on Iron-based Alloys per API 571
500 F 571: 4.4.2.3.c
165
Corrosion - Temperature range causing temper embrittlement in low chromes
650–1100 F 574: 3.1.39
166
Inspection - Operating Temp when a Corrosion Specialist must input on an Inspection Plan
> 750 F 570: 5.1.1.1
167
Corrosion - Graphitization occurs in Carbon Steel materials
> 800 F 574: 10.3.5.2.4
168
Corrosion - Creep occurs in 1-1/4% Chrome materials
> 900 F 574: 7.4.11.1
169
NDE - Maximum temperature for UT readings per ASME Sect V
1000 F ASME V: SE-797 8.5
170
NDE - Maximum temperature for UT readings per API 574
1100 F 574: 10.2.1.5.1
171
Materials - Carbon Steel PWHT temperature
1100-1200 F B31.3: Tbl 331.1.1
172
Testing - Minimum base metal temp during pressure testing when wall thickness is
MDMT + 10 F 570: 5.8.3
173
Testing - Minimum base metal temp during pressure testing when wall thickness is > 2” thick
MDMT + 30 F 570: 5.8.3
174
NDE - Maximum temperature for magnetic particles
Manufacturer Recommendation ASME V: 731.c
175
Common material with an endurance limit (fatigue cracking cannot occur below this stress level)
CS 571: 4.2.16.3.b.i
176
Subject to temper-embrittlement
Low Chromes 574: 7.4.12.1
177
Common material without an endurance limit
SS 571: 4.2.16.3.b.ii
178
Subject to chloride stress-corrosion cracking
300 SS 574: 7.4.8.1.a
179
Subject to polytheonic acid stress-corrosion cracking
Sensitized 300 SS 574: 7.4.8.1.b
180
P-numbers allowed to use pre-heat in lieu of PWHT
P1 & P3 570: 8.2.3.2
181
Flanges - Thread engagementellaneous acceptance criteria
-1 570: 5.12 / B31.3: 335.2.3
182
Ratio of Endurance Limit Stress to Ultimate Tensile Stress for Carbon Steel
0.4 – 0.5 571: 4.2.16.3.b.ii
183
Testing - Minimum range of pressure gauge used during a pressure test (multiplied by test pressure)
1.5 ASME V: T-1031.a
184
Testing - Preferred range of pressure gauge used during a pressure test (multiplied by test pressure)
2 ASME V: T-1031.a
185
NDE - # of additional welds or joints to examine when a weld defect is found during a Random examination
2 B31.3: 341.3.4.a
186
PWHT - Minimum # of thermocouples required when performing a local PWHT instead of a 360 degree band
2 570: 8.2.3.3.d
187
Weld Qualification - Number of tension tests to qualify a WPS
2 ASME IX: QW451.1
188
Weld Qualification - Number of bend tests to qualify a welder or welding operator in welding positions 1G-4G
2 ASME IX: QW452.1.a
189
NDE - Minimum # of exposures to RT 360o of a weld using a double-wall technique, double-wall view (elliptical shot)
2 ASME V: T-271.2.b.1
190
NDE - RT film Density Range - allowed for the weld & IQI when using a gamma ray source
2.0 – 4.0 ASME V: T-282.1
191
NDE - Minimum # of exposures to RT 360o of a weld using a double-wall technique, single-wall view
3 ASME V: T-271.2.a
192
Impact Test - Number of test bars required in each set
3 B31.3: 323.3.3
193
NDE - When using a shim under a hole-type IQI, the number of sides of the IQI that must be seen in the RT image
3 ASME V: T-277.3
194
Testing - Maximum range of pressure gauge used during a pressure test (multiplied by test pressure)
4 ASME V: T-1031.a
195
Weld Qualification - Number of bend tests to qualify a WPS
4 ASME IX: QW451.1
196
Weld Qualification - Number of bend tests to qualify a welder or welding operator in welding positions 5G & 6G
4 ASME IX: QW452.1.a Note 1
197
Design - # of Stress Cycles needed to become rated as Severe Cyclic Service
7000 B31.3: 300.2
198
NDE - Minimum time an examiner should be in a darkened area prior to using a black light for MT & PT exams
5 minutes ASME V: T-676.4.b & T-777.2.b
199
Testing - Minimum duration for a pressure test
10 minutes B31.3: 345.2.2.a
200
NDE - Final interpretation of a PT exam after application of developer (time range)
10-60 minutes ASME V: T-676.1
201
Testing - Minimum duration of hydro to evaluate integrity of buried pipe
8 hours 570: 9.3.7
202
NDE - Max Calibrating Interval – MT Permanent Magnet Yoke
Daily ASME V: T-762.a
203
NDE - Max Calibrating Interval - RT densitometer
90 days ASME V: T-262.1
204
Maximum time for obtaining thickness readings when corrosion rate on new pipe is not known (no other data available)
3 months 570: 7.1.2.c
205
Welding - Max Time a Welder or Welding Operator maintains qualifications for a process without using that process
6 months ASME IX: QW-322.1.a
206
Interval - Suggested interval for Above-grade Visual Surveillance of buried pipe
6 months 570: 9.3.1
207
NDE - Max Calibrating Interval - Electromagnetic MT Yoke
1 year ASME V: T-762.a
208
NDE - Maximum Interval for a visual examiner’s eye exam
1 year ASME V: T-923
209
NDE - Max interval to calibrate pressure gauge used in testing
1 year ASME V: T-1061.a
210
AI - Length of time before an API 570 AI must recertify
3 years 570: A.3.1
211
Insp - Max Thickness Inspection interval for an Injection Point
Lesser 3 yr or ½ Life 570: Table 2
212
Insp - Max External Inspection interval for Class 1 & 2 Piping
5 year 570: Table 2
213
Insp - Maximum Interval for Relief devices in fouling or corrosive service
5 year 570: 6.7.3.2
214
Insp - Suggested interval for Close-interval Potential Survey of buried pipe with poor CP
5 year 570: 9.3.2
215
Insp - Suggested interval for evaluation of Soil Corrosivity for buried pipe with no CP
5 year 570: 9.3.4
216
Insp - Max Thickness Inspection interval for Class 1 Piping
Lesser 5 yr or ½ Life 570: Table 2
217
Insp - Maximum Interval for Relief devices in non-fouling or non-corrosive service
10 years 570: 6.7.3.2
218
Insp - Minimum years of experience for Owner’s inspector during new fabrication
10 years B31.3: 340.4.b
219
Insp - Maximum External Inspection interval for Class 3 Piping
10 years 570: Table 2
220
Insp - Maximum Thickness Inspection interval for Class 2 & 3 Piping
Lesser 10 yr or ½ Life 570: Table 2
221
RBI - Maximum Interval for the RBI Reassessment
Per Table 2 570: 5.2.4
222
Repairs - When should temporary welded pipe repairs be replaced
Next opportunity 570: 8.1.4.1
223
Repairs - When shall non-welded repairs & temporary leak sealing devices and be removed and pipe repaired
Next turnaround 570: 8.1.5
224
NDE - Max Calibrating Interval - Check the light intensity of a black light used in a MT or PT exam
Before & after use ASME V: T-676.4.e & T-777.2.e
225
NDE - Pipe size where RT is preferred for thickness readings
Equal or
226
NDE - Pipe size where UT thickness readings may require specialized UT equipment
Equal or
227
Terms - Small bore piping
Equal or
228
Maximum pipe size normally allowed for threaded pipe
Equal or
229
Maximum pipe size normally allowed for socket-welded pipe
Equal or
230
NDE - Maximum pipe size for performing an elliptical shot (double-wall technique, double-wall view)
3 NPS ASME V: T-271.2.b
231
Pipe size where pipe OD is equal to pipe size (NPS)
Equal or > 14 NPS 574: 4.1.1.2
232
Pipe size where pipe is almost always made using rolled & welded plate
> 16 NPS 574: 4.1.1.1
233
NDE - Weight used to check magnetic strength of an AC yoke
10 lb. ASME V: T-762.b
234
NDE - Weight used to check magnetic strength of a DC yoke
40 lb. ASME V: T-762.c
235
NDE - Weight used to check magnetic strength of a permanent magnet yoke
40 lb. ASME V: T-762.c
236
NDE – Min angle of eye-to-part to count as a Visual Exam
30 degrees ASME V: T-952
237
NDE - Two primary gamma-ray RT sources
Ir 192, Co 60 577: 9.8.4
238
NDE - Lead letter used during RT to check for backscatter radiation
B ASME V: T-223
239
NDE - Lead letter used during RT to indicate a film-side IQI
F ASME V: T-277.1.b
240
NDE - Hole size that must be visible in RT when using a hole-type IQI
2T ASME V: Tbl T-276
241
NDE - Minimum light intensity when performing non-fluorescent MT or PT or VT exams
100 ft-candles ASME V: T-676.3, T-777.1 & T-952
242
NDE - Minimum black light intensity when performing MT or PT fluorescent exams
1000 mW/cm2 ASME V: T-676.4.c & T-777.2.c
243
NDE - Maximum UT scanning speed
6”/sec 574: 10.2.1.4.3
244
Weld Qualification - Maximum allowed thickness on a WPS based on the plate thickness (T) of a PQR test coupon
2T ASME IX: QW451.1
245
Weld Qualification – The “all-position” test coupon
6G ASME IX: QW461.9
246
Weld Qualification – Rejectable in RT when qualifying a welder
Crack, LoF, IP ASME IX: QW191.1. 2.2.a.1
247
Weld Qualification – Which welding process can a welder NOT be qualified by RT/UT
GMAW - SC ASME IX: QW-304
248
Welding - Variables needed on WPS
Essential & Non-Essent. ASME IX: QW200.1.b
249
Welding - Variables needed on PQR
Essential ASME IX: QW200.2.a
250
Welding - Minimum taper required for welds with mismatch
30 degrees B31.3: Fig 328.4.3
251
Design - Two most common CS pipe materials
A53 & A106 574: 4.1.1.1
252
Repair - Maximum allowed SMYS for pipe if fillet-welded patch is installed
40,000 psi 570: 8.1.4.1
253
Test - Maximum stress allowed during a pressure test
90% of SMYS 570: 5.8 Note
254
Test - pH of water needed to reduce likelihood of MIC (bugs)
>10 pH 570: 5.8.1
255
Corrosion - Typical external corrosion rate for dry rural environments
256
Corrosion - Typical external corrosion rate for inland locations with moderate rain & humidity
1-3 mpy 571: 4.3.2.3.c
257
Corrosion - Possible external corrosion rate for industrial environments with acid or sulfur compounds
5-10 mpy 571: 4.3.2.3.b
258
Corrosion - Possible external corrosion rate for marine environments
20 mpy 571: 4.3.2.3.b
259
NDE - Limits of RT Film Density of weld as compared to IQI
-15 to +30% ASME V: T-282.2.a.1
260
Design - Mill Tolerance of Seamless Pipe
-12.5% 574: 4.1.1.3
261
Pipe Class - % of H2S in process to classify as Class 1 Pipe
Equal to or > 3% 570: 6.3.4.2.c
262
NDE - % of welds to RT when fabricating Normal Service Pipe
5% B31.3: 341.4.1.b.1
263
NDE - % of welds to VT when fabricating Normal Service Pipe
5% B31.3: 341.4.1.a.2
264
NDE - % of welds to Brinnell after PWHT in furnace (if BHN are required)
10% B31.3: 331.1.7.a
265
NDE - Overlap with a UT scan, % of transducer diameter
10% 574: 10.2.1.4.3
266
AI - Amount of time inspector must be involved in inspection activities - required to maintain API 570 certification
20% 570: A.3.2
267
Mtls - Amount of nickel required for a material to be considered a nickel alloy
> 30% 571: 3.1.15
268
NDE - % of welds to Brinnell after local PWHT (if BHN is reqd)
100% B31.3: 331.1.7.a
269
NDE - % of Visual & RT required when fabricating Severe Cyclic Pipe
100% B31.3: 341.4.3.a.1/b
270
Testing - Pneumatic test pressure, % of design pressure
110% B31.3: 345.5.4
271
Testing - Leak test pressure of underground pipe, % of operating pressure
110% 570: 9.3.7
272
PRV - Maximum set pressure for thermal relief valves, % of design pressure
120% B31.3: 322.6.3.b.2
273
Document Owner/User must have that is following API 570
QA/Repair Manual 570: 4.3.1.1
274
Document required for each piping system
Inspection Plan 570: 5.1.1.1
275
Document required when changes are made to hardware or process
MOC 570: 4.3.1.2
276
Document required when Owner audits inspection program
Tracking System 570: 5.13
277
Document required of Examiner’s Employer
Certification Records 570: 4.3.5.3
278
Document required for each PRD Repair Organization
QA Manual 570: 6.7.2
279
Document required concerning personnel at PRD Repair Organization
Training Program 570: 6.7.2
280
Records maintain by Repair Organization and available to the inspector
WPS(s) & WPQ(s) 570: 8.2.2
281
Another Record that the Owner/User must maintain # 1
Insp Iso’s 570: 7.6.6
282
Another Record that the Owner/User must maintain # 2
Track Repairs Recommendations 570: 7.7
283
Another Record that the Owner/User must maintain # 3
External Inspections 570: 7.8
284
Another Record that the Owner/User must maintain # 4
Track Temporary Repairs 570: 7.9
285
Another Record that the Owner/User must maintain # 5
Deferrals 570: 7.10
286
API 578 provides guidelines for a material assurance system to verify:
All alloy materials. 1.0
287
The material verification program specified by API 578 covers:
Only pressure-containing components. 1.0
288
An alloy material is any metallic material that contains alloying elements thatare added:
To improve either mechanical properties or corrosion resistance. 3.1
289
An inspection lot includes:
all materials from a common source, of the same material type and same heat. 3.4
290
For construction and repair activities a written material verification program should be established by the:
Owner/User. 4.1
291
The material verification program should cover PMI testing of materials:
In existing piping systems and during construction, repairs andalterations of piping systems. 4.1
292
During repairs, random PMI sampling of new components is most appropriatefor:
low-risk piping systems. 4.1
293
Who has the responsibility to determine the extent of PMI performed?
Owner/User 4.1
294
During construction the Owner should consider 100% PMI of new components on:
high-risk piping systems. 4.1
295
Usually substituting an alloy for carbon steel does not cause a problem. But hardenable alloys may cause failure in some carbon steel systems. Which of the following process services would substituting an alloy for carbon steelnot result in a potential problem.
Benzene 4.1.1
296
Who is responsible to assure that the material verification program meets the guidelines of API 578?
Owner/User 4.2.1
297
Who is responsibility to verify the adequacy of the material verification program that is performed by material suppliers?
Owner/User 4.2.2
298
Who has the responsibility to review and approve the adequacy of the PMI program used by fabricators?
Owner/User 4.2.2
299
A mill test report:
Is an important part of the material qualify assurance program. 4.2.4
300
During construction, which of the following alloy components does not need to be covered by a material verification program?
Bolts, expansion joints, gaskets, and pressure containing welds need to be checked. 4.2.5
301
During alloy welding:
One electrode from each lot or package should be identified. 4.2.6
302
If alloy element(s) are contained in the flux of a welding electrode, PMI testing:
Could be conducted on a “weld button” prior to production welds. 4.2.6
303
New longitudinal welded alloyed pipe should:
Receive random PMI testing of weld and base metal if there is a reason to suspect problems. 4.2.6.1
304
PMI of autogenous welds is:
Not required if the base metal was PMI tested. 4.2.6.2
305
Who has the responsibility to determine the extent of PMI testing required on existing piping systems?
Owner/User 4.3.2
306
When prioritizing the need for PMI on existing piping systems, which of the following is not a factor to consider?
Age of the facility. 4.3.3
307
Incorrect substitution of carbon steel is most likely to be found in:
Chrome systems. 4.3.3.1
308
Which residual element in a carbon steel system has not caused increased corrosion rates in HF acid piping system?
Fe 4.3.3.2
309
Low silicon carbon steel can corrode rapidly when exposed to:
Hydrogen-free sulfidation. 4.3.3.4
310
Carbon steel can corrode rapidly in hydrogen-free sulfidation when the silicon content in carbon steel is:
311
The owner decides to conduct PMI testing on some existing piping systems. Which of the following is a major factor in prioritizing the pipe?
The effectiveness of the construction & maintenance practices. 4.3.3.5
312
Which of the following piping components is most likely to have a substitution with the wrong material?
Bolting. 4.3.4
313
Which of the following piping components is most likely to have a substitution with the wrong material?
6 NPS Gate valve. 4.3.4
314
Who has the responsibility to determine the extent of PMI testing required during repairs and alterations of piping systems?
Owner/User. 4.4.1
315
Who has the responsibility to evaluate the effectiveness of a PMI program during repairs and alterations?
Owner/User. 4.4.1
316
During repairs and alterations the Owner should:
Have a written procedure describing their PMI program. 4.4.1
317
PMI testing at the warehouse is:
Not a substitute for PMI testing required during fabrication. 4.4.2
318
In the petrochemical industry, one common material mix-up problem occurs:
When temporarily removing spool pieces. 4.4.3
319
Identification of materials by visual stamps or markings:
Is not a substitute for PMI testing. 5.1
320
How do portable X-Ray Fluorescence PMI tools work?
Radiation waves excite the materials and the material emits adifferent spectrum of radiation that can be analyzed. 5.2.2
321
PMI tools that use X-Ray fluorescence can not detect:
carbon. 5.2.2
322
How does Portable Optical Emission Spectrometry determine the elements in a material?
An electric arc causes a spectrum of light to be emitted from the tested material. The light is analyzed. 5.2.3
323
Chemical spot testing:
Removes a small amount of surface metal that is placed in a filter paper. Small droplets of reagents are used on the sample and different colors indicated different materials. 5.2.5.1
324
PMI tools that use Resistivity Testing are not always able to sort:
Low chromes and 300 series stainless steels. 5.2.5.2
325
PMI testing equipment should be:
Calibrated as specified by the manufacturer. 5.3
326
All personnel performing PMI tests should be:
Knowledgeable about the operation of the PMI test equipment. 5.5
327
Qualifications for personnel performing PMI testing should be submitted and reviewed by:
The Owner/User. 5,5
328
When PMI testing indicates that an alloy is outside the range allowed on the material spec, the component can:
Be used if accepted by the Owner/User following an assessment. 6.1c
329
An alloy weld overlay is applied to carbon steel base metal. What will occur?
Dilution. 6.2
330
An alloy weld overlay is applied to carbon steel base metal. Who has the responsibility to establish the minimum alloy requirements of the asdeposited weld metal?
Owner/User. 6.2
331
What is the appropriate action to take when an incorrect material is located during a PMI sampling of an inspection lot?
A more extensive inspection of the lot should be considered. 6.3
332
A color code system for pipe is specified by:
PFI ES22. 7.1.1
333
Identification of materials by color coding:
Is not a substitute for PMI testing. 7.1.1
334
Which of the following is not required when the owner’s PMI system requires physical marking of components?
The name of individual doing the marking. 7.1.1 / 7.1.2
335
Marking pens should not contain chlorides or:
Sulfur. 7.1.2b
336
When PMI testing is conducted on a new piping system, the documentation of the PMI results should be kept:
Until piping system is removed/scrapped. 7.4
337
Overall responsibility for complying with API 570 4.1
O
338
Responsible for developing &implementing a QA insp/repair mgmt system 4.3.1.1
O
339
Responsible for implementing an effective MOC process 4.3.1.2
O
340
Responsible for QC during repairs or alterations 4.3.3
Repair Organization
341
Assure owner - testing, inspection & examination activities meet Code 4.3.4
I
342
Evaluate and accept NDE examination results 4.3.4
I
343
Maintain certification records of NDE examiners 4.3.5.3
Exam Employer
344
Develop an inspection plan for a piping system 5.1.1.1
And / Or I E
345
Also involved in making inspection plans for pipe that operates >750 oF 5.1.1.1
CS
346
Choose to conduct RBI assessments 5.2
0
347
Get familiar with prior inspection data & repairs prior to inspections 5.3.5
I
348
Get familiar w/ operating conditions & potential damage mech of pipe system 5.4.1.2
I
349
Perform On-stream inspections 5.5.2
Or I Tech
350
Perform Thickness Inspection 5.5.3
Or I Tech
351
Assure individuals taking thickness measurements are trained and qualified 5.5.3
O
352
Determine cause if short-term corrosion rate varies significantly 5.5.3
And I CS
353
Perform External Inspection 5.5.4
Or I Qualified Other
354
Involved if the # of CML’s will be significantly reduced or eliminated 5.6.2
CS
355
Select or adjust the # of CMLs 5.6.3
I
356
Select CMLs for pipe systems subject to localized corrosion or cracking 5.6.3
CS
357
Determine need for non-thickness NDE techniques. Inspector consults w/: 5.7.2
Or E CS
358
Determine surface prep for NDE exam. Inspector made need to consult with: 5.7.3
GURU
359
Perform UT flaw detection for finding linear flaws 5.7.4
QUTE
360
Determine pressure for leak tests (non-code tests) 5.8
O
361
Prior to hydrotest determine if structure will support weight 5.8
E
362
Determine risk of brittle fracture prior to performing a pressure test 5.8.3
E
363
Approve substituting NDE for a pressure test 5.8.5
And I E
364
Perform UT as a substitute for a pressure test 5.8.5
QUTE
365
Verify that new alloy material during repairs & alteration meet specifications 5.9
I
366
When verifying new materials, determine the sampling percentage 5.9
O
367
PMI new materials during repairs & alterations 5.9
Or I Tech
368
If incorrect mat’l found in existing pipe, determine amount of further verification 5.9
I
369
Determine if PMI program is needed for existing facilities 5.9
O
370
Determine date to replace incorrect mat’ls found during PMI survey 5.9
And I O CS
371
Periodically inspect components found during PMI survey that are wrong mat’ls 5.9
I
372
Determine if crack-like weld flaws are the result of original weld fabrication 5.11
I
373
Assess crack-like flaws and environmental cracking 5.11
Or E CS
374
Assess preferential weld corrosion 5.11
I
375
Perform audit of owner/users to assure compliance with 570 5.13
Competent
376
Make corrections based on the audit of owner/users piping program 5.13
Owner’s AIA
377
Review and approve RBI assessments 6.3.2
And I E
378
Determine the inspection intervals 6.3.3
Or I O
379
Maintain a record of process fluid classification 6.3.4.1
O
380
PRD’s tested and repaired 6.7.1
Exp. Repair Org
381
Determine the inspection intervals for PRDs 6.7.3.1
Or I E Qualified Other
382
Select corrosion rate that best reflects conditions 7.1.1
And I CS
383
Maintain piping records 7.6.1
O
384
Review and approval an interval deferral 7.10
I
385
Revise an existing interval and document basis for change 7.10
I
386
Revise an existing interval that has unusual degradation issues. Inspector and: 7.10
Or E CS
387
Perform piping repairs 8.1.2
Repair Org
388
Authorize all repairs 8.1.2
I
389
Authorize all alterations 8.1.2
And I E
390
Designate hold points for repairs and alterations 8.1.2
I
391
Provide general authorization for limited or routine repairs 8.1.2
I
392
Approve all proposed methods of design, materials, WPSs, NDE & testing 8.1.3
Or I E
393
Approve use of on-stream welding 8.1.3
O
394
Approve repair welding of cracks 8.1.3
E
395
Approve all repair and alteration work at hold points 8.1.3
I
396
Approve all repair and alteration work at completion of work 8.1.3
I
397
Design temporary repairs 8.1.4.1
E
398
Determine longitudinal cracks won’t grow beyond a FW patch 8.1.4.1
E
399
Approve using lap patches with a material different than the pipe 8.1.4.1
E
400
Determine that wall thickness is adequate for on-stream welding 8.1.4.1
I
401
Allow temporary welded repairs to remain in place past “next opportunity” 8.1.4.1
E
402
Allow temp leak sealing devices to remain in place past “next opportunity” 8.1.5
E
403
Review leak sealing procedures 8.1.5
Or I E
404
Maintain record of qualified WPS’s and WPQ’s 8.2.2
Repair Org
405
Allow exceptions to required preheat temperature for temporary repairs 8.2.3.2
E
406
Check preheat temperature when using Preheat in lieu of PWHT 8.2.3.2
I
407
Review the use of Preheat in lieu of PWHT 8.2.3.2
E
408
Exceptions to PWHT on temporary repairs 8.2.3.3
E
409
Review the use of a local PWHT in lieu of a full encirclement PWHT 8.2.3.3
E
410
Determine whether a pressure test is needed after repairs 8.2.7
I
411
Approve substituting NDE in lieu of a pressure test 8.2.7
And I E
412
Perform rerating calcs 8.3
Or I E