Appropriate Contract Selection flashcards

(50 cards)

1
Q

What is the main purpose of the RICS ‘Appropriate Contract Selection’ guidance?

A

To assist clients and professional advisers in selecting the most suitable construction contract for a project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the three levels of guidance provided in the document?

A

Level 1 – Knowing; Level 2 – Doing; Level 3 – Advising.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the key factor in determining which construction contract should be chosen?

A

The procurement route.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Name the main procurement routes discussed in the document.

A

Traditional, Design and Build, Construction Management, Management Contracting, Partnering, Public Private Partnerships (PPP), and others.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

In traditional procurement, who is responsible for design?

A

The employer, via their appointed professional team.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What distinguishes a ‘Design and Build’ contract from a traditional one?

A

The contractor is responsible for both design and construction.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is a Contractor’s Designed Portion (CDP)?

A

An element of a traditionally procured project where the contractor takes on specific design responsibilities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the key characteristic of a construction management (CM) contract?

A

The employer holds all trade contracts and appoints a construction manager to oversee them.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the difference between construction management and management contracting?

A

In CM, the employer holds the trade contracts; in MC, the management contractor holds the contracts.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is a ‘cost reimbursable’ or ‘prime cost’ contract?

A

The contractor is paid for actual costs incurred plus a fixed fee or percentage for profit.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is a ‘target cost’ contract?

A

A contract where the cost risk is shared between employer and contractor through a painshare/gainshare mechanism.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are the key standard form contract publishers mentioned?

A

JCT and NEC.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is the philosophy behind NEC contracts?

A

They promote good project management, mutual trust, and cooperation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are the core characteristics of NEC contracts?

A

Simple language, modular structure, focus on project management, and early warning mechanisms.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is the purpose of JCT’s Design and Build Contract (DB)?

A

Used where the contractor is responsible for both design and construction.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What contract should be used under JCT for major projects using design and build?

A

Major Project Construction Contract (MP).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What is the JCT Minor Works Building Contract (MW) used for?

A

Smaller, simple projects using traditional procurement.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What distinguishes the JCT Intermediate Building Contract (IC)?

A

A middle ground between the detailed SBC and simple MW, suitable for moderately complex projects.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What is the role of standard form contracts in construction?

A

To save time, reduce legal costs, and provide a familiar risk allocation framework.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Why might a standard form contract be amended?

A

To tailor it to project-specific requirements or shift risk allocation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Front

22
Q

Which JCT contract is best for large, complex traditional projects?

A

Standard Building Contract (SBC)

23
Q

What are the three versions of the JCT Standard Building Contract?

A

SBC/Q (with quantities), SBC/XQ (without quantities), SBC/AQ (with approximate quantities)

24
Q

Which JCT contract fills the gap between SBC and MW for medium complexity projects?

A

Intermediate Building Contract (IC)

25
Which JCT contract should be used for small, simple traditional projects?
Minor Works Building Contract (MW)
26
Which JCT contract is suitable when the contractor is responsible for both design and construction?
Design and Build Contract (DB)
27
Which JCT contract is designed for major projects with experienced parties using D&B?
Major Project Construction Contract (MP)
28
Which JCT contract is used for the management contracting procurement route?
Management Building Contract (MC)
29
What JCT contract allows the employer to directly appoint trade contractors while a construction manager oversees them?
Construction Management Contract (CM)
30
Which JCT contract promotes partnering and collaborative working?
Constructing Excellence Contract (CE)
31
What JCT contract is used for ongoing maintenance over a period?
Measured Term Contract (MTC)
32
Which JCT contract is suitable for urgent works where scope isn't fully defined at the start?
Prime Cost Building Contract (PCC)
33
Which JCT document is used for multiple call-off contracts over time?
Framework Agreement (FA)
34
Which JCT contract is used for defined one-off repair/maintenance jobs?
Repair and Maintenance Contract (RM)
35
Which JCT contracts are designed for domestic homeowner use?
Home Owner Contracts (HO/C, HO/B, HO/CA, HO/RM)
36
What is the flagship contract in the NEC suite for engineering and construction work?
NEC Engineering and Construction Contract (ECC)
37
Name the six main pricing options in the NEC ECC.
Option A – Activity schedule, Option B – Bills of quantities, Option C – Target with activity schedule, Option D – Target with bills of quantities, Option E – Cost reimbursable, Option F – Management contract
38
Which NEC ECC option involves a lump sum with an activity schedule?
Option A
39
Which NEC ECC option uses cost reimbursable pricing?
Option E
40
Which NEC ECC options include a painshare/gainshare mechanism?
Options C and D
41
What NEC contract is used for shorter, simpler works projects?
Engineering and Construction Short Contract (ECSC)
42
Which NEC contract is used to appoint a consultant for services like design or project management?
Professional Services Contract (PSC)
43
What NEC contract is used to procure ongoing services over a term?
Term Service Contract (TSC)
44
Which NEC contract is suitable for appointing subcontractors under the ECC?
Engineering and Construction Subcontract (ECS)
45
What NEC documents provide simplified terms for subcontracting under ECC?
Engineering and Construction Short Subcontract (ECSS)
46
What Procurement route is this?
Traditional (‘design-bid-build’) This procurement route is typically characterised by a separation of responsibility for the design and the production/construction of the project. The employer appoints the contractor via the construction contract and also separately appoints the team of professional consultants (e.g. the architect, structural engineer, building services engineer and quantity surveyor). The contractor assumes the responsibility and financial risk for constructing the project in accordance with the design produced by the employer’s team of professional consultants, for the agreed contract sum and within the agreed contract period.
47
Design and build While a traditionally procured construction contract is characterised by the separation of responsibility for the design and the production/construction of a project, a construction contract that is procured on a design and build (D&B) basis is characterised by the contractor taking responsibility for both the design and the production/construction of a project. One of the main reasons employers often choose this form of procurement route is the desire to have one party (the contractor) as the single point of responsibility for the design and production/construction of a project. However, the extent of the creation of a true single point of responsibility will depend on the terms and conditions of the construction contract with the contractor.
48
Construction management Under a construction management (CM) route, the employer does not allocate risk and responsibility to a single main contractor. Instead, the employer employs the design team (e.g. the architect, structural engineer and building services engineer) and a separate construction manager is engaged as a fee-earning professional to manage, programme and co-ordinate the design and construction activities and to facilitate collaboration.
49
Management contracting Under a management contract, the employer engages a management contractor to participate in the project at an early stage, contribute construction expertise to the design, and manage the construction of the project. The management contractor does not carry out any construction work, but manages the project for a fee, which is paid on top of the construction costs incurred by the management contractor. The management contractor then employs and pays works contractors to carry out the actual construction works. In effect, management contracting consists of 100% subcontracting. Every item of the construction works is subcontracted to the works contractors. It is this subcontracting feature that distinguishes management contracting from construction management (discussed in Section 2.2.4), under which the separate trade contracts are all entered into directly between the employer and trade contractors.
50
Public Private Partnerships (PPP) The term Public Private Partnership (PPP) is an umbrella term that covers a diverse range of business structures and partnerships involving the public and private sectors. Typically, private sector companies will form a consortium, sometimes referred to as a ‘special purpose vehicle’ (SPV), and enter into some kind of partnership with the public sector for supporting or providing a public service, sometimes described as Build-Own-Operate-Transfer (BOOT). One key aspect of PPP schemes is that the public sector seeks to transfer much of the development and financing risk to the private sector. For example, the private sector agrees to finance, design, build and operate a particular asset (e.g. a hospital, school, road or prison) that the public sector is able to use. The private sector is also obliged to provide long term lifecycle investment and routine maintenance; sometimes together with ‘soft services’ (e.g. catering, cleaning, rent collection).