Authority Approvals and Planning Controls Flashcards

(17 cards)

1
Q

Architect’s role in approvals is…

A

To understand the DA process and correctly interpret planning controls
Advise the client on the process and appoint the right consultants for the job (planner etc)
Involve the client in all Council meetings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

State approvals

A

DPIE, IPC ($100M), SPP ($30-100M)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Local approvals

A

Local planning panel (+value, +objections, +departure from controls, +sensitive)
Delegated planning officers
Committees

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Appeals

A

Local Environmental Court - a division of the Supreme Court

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Concurrence (parallel approvals)

A

Integrated development (Transport, Airport etc)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Statute Law

A

Planning principles set by court cases.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Varying planning controls

A

SEPP 1 - LEP clause 4.6
<10% Council
>10% LPP
Significant - planning proposal

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Relevant planning controls

A

SEPPs esp 65(+ADG) and Basix for residential, Infrastructure
LEPs (note draft LEPs need only be considered when on exhibition)
DCPs not legally binding but problematic if too many objectives or characters statements breached

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Options if development is refused

A

Appeal to court

Submit a review application to Council

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

DA process in Council

A

2 weeks to assign to officer
~14 days notification (28 for integrated)
Assessing officer review (months)
Sign off by manager
Determination letter and conditions of consent to applicant

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Deemed refusal

A

Assumed by the applicant when they don’t hear from the Council within a certain timeframe ie 40 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

DA conditions - to check

A

Check if they require any redesign prior to construction certificate
Check they can be achieved within the client’s scope/budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Deferred commencement

A

Requires compliance to be achieved with a specific condition (not the general CoC) prior to the development consent being issued. Example - site remediation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Timeframes for consents

A

2-5 years from the date of the Determination letter for the original consent (mods do not restart the clock)
Physical commencement must be achieved within the timeframes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Modification applications

A

Must be substantially the same as the originally approved DA.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Construction Certificate

A

Required for all works to commence construction (except for complete demolition)

17
Q

Occupation certificate

A

Required from Council or PC in order to occupy a new building of change the use of an existing building