Ballast Review Flashcards

(106 cards)

0
Q

Look @ occupancy chart

A

Will do

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
1
Q

Min clr floor space for 1 wheelchair

A

30x48

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Occupancy load factors are based on

A

Net or gross floor area, depending on occupancy group

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Max distance object may protrude into path of travel

A

4”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Duck size designations use ___ 1st and ____ second

A

Width by depth

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

The standard for exit width requirement is

A

.2 inches per person

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

An exit door must have a clear width of at least

A

32 inches

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Height of the handrail for barrier free design

A

34 to 38 inches , measured from the nosing of the stair

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

1:12 ramp max rise is

A

30 in

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

1:8 ramp maximum rise

A

3 inches

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Normal sequence of drawings

A

Site plan, civil, architectural, structural, mechanical, plumbing, electrical

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

The design strength of the final mix of concrete is determined after

A

28 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Requires a material or product to be compliant with an independent testing

A

Reference specification

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Defines the standard scope of services

A

B141

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Bricklaying. One course has short sides next course has long sides

A

English bond

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Bricklaying: each rack alternates longside short side and each course centers on the next

A

Flemish bond

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Addenda are issued

A

Prior to bid

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Quest for substitution must be received ___ days before the bid date

A

10

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q
  • change order
  • construction change directive
  • written order for minor change
  • written amendment to the contract signed by both parties
A

Modification

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q
  • Acts on behalf of the principal to perform certain duties to third-party
  • can legally bind principal
A

Agent

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Contractor is an example of a

A
  • Vendor

- supplies a specific product at a fixed price

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Fast track

One part needs to start before the other ones are designed

A

Many prime contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Advantages of using a CM

A

Early advice on constructibility
Early cost estimating/value analysis
Project scheduling
Professional management of multiple contracts
* in some cases guaranteed maximum price/completion date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Disadvantages of CM

A

Extra costs

More complicated management structure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
A.k.a. stipulated sum/lump sum Owner not responsible for cost overruns Owner sees no savings if it comes in under budget
Fixed price
25
Price guaranteed by contractor | Owner see savings if project comes in under budget
GMP
26
Cost-plus fee
Actual cost | Plus fees set before contract signing
27
Design build
O + 1 entity design and construction * May hire architects as subcontractors * maybe a joint venture between A/C * May subcontract both A/C
28
Advantages of design build
Single source of responsibility Owner has fixed-price early Total time usually reduced
29
Disadvantages of design build
- Owner has less control over design Can be disagreements about what is included - Design build firm has control over material quality & construction methods - To get what's needed, client must develop specific performance requirements
30
In design build owner can hire architect as advisor to:
- Set up performance requirements - Evaluate design build firm's - Administer contract - Evaluate progress of work
31
Initial information
- project objectives - owner's program - physical, legal, financial and time parameters - Key personnel * to encourage communication at beginning of project
32
Owner and contractor are supposed to communicate through
The architect
33
Owners responsibilities
Provide program Land surveys Geotechnical services
34
Privity
One party is protected from claims from another party where there's no contractual relationship
35
Date of commencement can be either:
1) A fixed date in the contract | 2) when receive "notice-to-proceed" letter
36
Substantial completion
When owner can use or occupy project
37
Retainage is typically
10%
38
Competitive bidding always uses
Stipulated sum
39
Advantages of cost-plus fee
More flexibility | Allow construction to proceed prior to final design
40
Unit prices are used for
Portions of projects but not usually whole projects
41
Who pays for the copy of the drawings and project manual
Owner
42
O has right to carry out Work if C fails to do so according to the CD's. Procedure is
7 days written notice for C to begin +3 days written notice that O will fix work if C fails to begin *A must approve O's actions to carry out the work, as well as amount charged
43
If C knowingly observes error or omission in contract documents or discrepancy with known regulation
They assume full responsibility for such work
44
Contractor wants to make a substitution
Must have consent of the owner, after evaluation by the architect, and in accordance with change order
45
Warranty clause is separate and distinct from
The one year correction period
46
Who pays for the building permit, weather permits, governmental fees, licenses, and inspections necessary after the execution of the contract?
Contractor
47
Are allowances included or excluded in the contractors contract sum?
Included
48
Contractor must maintain up-to-date, on site
Record documents
49
Indemnify
Secure against loss or damage, To hold harmless
50
The architects decisions concerning matters related to aesthetic effect are final if
They're consistent with the intent shown on the contract documents
51
Construction change directive
Contractor must proceed with required changes Final cost / time changes submitted by contractor Agreed to by architect and owner, then change order is issued
52
Frequency of application for payment is typically
Monthly
53
Mechanics lien
The claim against the property of another for the satisfaction of a debt
54
If a property carries a mechanics lien it cannot
Be sold Except by foreclosure
55
If hazardous materials are found the contractor must
Stop work and report the conditions to the owner and architect in writing
56
Architects professional liability insurance policies exclude
Giving advice on insurance and bonds
57
Bonds are a protection for
The owner against default by the contractor
58
The only person that can except nonconforming work, as long as it meets code, is
The Owner * advantage is contract sun may be reduced
59
Contractor may terminate the contract if work has stopped for more than
30 days, through no fault of the contractor. 7 days written notice on top of the 30 days is required.
60
Additional items that may be included in the Supplementary Conditions are
- Permission for the architect to furnish the contractor with instruments of service in electronic form - Additional information and services provided by the owner - Cost for the architect to review the contractors request for submissions - Provisions for the owner, instead of the contractor, to pay for utilities - Requirement that the contractor employ a superintendent to coordinate mechanical and electrical work - Provisions for fast-track scheduling - Reimbursement by the contractor for extra site visits by the architect, made necessary by the fault of the contractor - Additional protection for the owner against claims for additional time or for consequential damages - Requirements for more detailed information on costs and overhead - Additional requirements for payment procedures - Requirements for liquidated damages and bonuses - Additional requirements for bonding and insurance
61
Supplementary conditions of the contract
Modify the general conditions to accommodate different clients, governmental regulations, and local laws
62
Special conditions
Are a separate section to describe conditions that are unique to a particular project or site.
63
For most public agencies what type of bidding is mandatory
Open bidding * advertising for bids is usually required
64
Two ways to notify perspective bidders
1, newspapers and trade journals 2, invitation to bid
65
Addenda
Written or graphic document issued by the architect prior to the execution of the contract
66
When addenda is issued it is sent to
All registered bidders not later than 4 days before receipt of bids
67
Pre-bid conference
Meeting with A/O and bidders * answers to significant questions should be formalized in an addendum
68
Bids received after the opening time should not be excepted unless
None of the bids have been opened and there are no objections from those bidders present
69
Architect reviews bids and a decision is awarded within usually
10 days
70
If a bidder discovers a mathematical error has been made
They can usually withdraw the bid
71
If all bids exceed project budget and the owner architect agreement fixes a limit on construction the owner has four choices:
1. to rebid 2. To authorize an increase in the construction cost and proceed 3. to work with the architect in revising the scope of the project to reduce cost 4. to abandon the project
72
Bidding documents and construction documents are
Not the same thing
73
Bidding documents usually include
The advertisement or invitation to bid Instructions to bidders Supplementary instructions to bidders Bid forms Bid security information Performance bond, if required Labor and material payment bond, if required
74
Bidding documents are not part of
Contract documents
75
Instructions to Bidders:
- Bidders representations - bidding documents - interpretation or correction bidding documents - substitutions - addenda - bidding procedures - modification or withdrawal of bid - consideration of bids - post bid information - performance bond and payment bond
76
If bidders require more information they must contact the architect in writing this many days prior to the bid date
Seven days
77
Bidders representation:
Materials have been understood Bid is based on bid documents without exception
78
Bidding documents:
Where documents may be obtained How many sets Amount deposit
79
Deposit for bid documents is returned if documents are returned within
10 days after bids
80
Interpretation or correction of bidding documents:
report any errors, inconsistencies, or ambiguities discovered. if clarification is needed, written request seven days prior to bid date
81
Substitutions:
Must submit request for approval at least 10 days prior to bid date Proof of merit of substitution by contractor
82
Addenda must be issued no later then
4 days prior to bid date
83
Bidding procedures:
How bid forms are to be filled in What bid security is needed Procedure for submitting the bid
84
Modification or with drawl of bid
As long as before designated big time
85
Owner has the right to reject bids
For any reason
86
Post bid information
Contractors qualification statement Names of manufacturers Names of subs
87
If the successful bidder requests owner must show
Reasonable evidence that financial arrangements have been made
88
A standard bid form is used to
Make it easier to compare and evaluate bids
89
Bids are written in both
Numbers and words * words trump numbers
90
Bid security may be in the form of And amount
Bid bond Certified check Cashiers check *5% bid amount
91
Purpose of bid security is
Cover the cost between difference of low bid and the next lowest bid, if the bidder fails to enter into an agreement
92
Performance bond
Surety will complete construction should contractor default * usually mandatory on public work
93
Labor and material payment bond
Protects owner from liens by guaranteeing payment
94
Architect reviews submittals for
Conformance with information given and design intent not responsible for accuracy of measurements , completeness of details , quantity, or fabrication or installation procedure
95
Minor change
No change in sum or time consistent with contract documents
96
If the architect volunteers suggestions or directions concerning construction means and techniques in regard to safety issues
The architect may also assume legal responsibility
97
Unlike a trial, arbitration decisions can not be
Appealed
98
The arbitrator is knowledgeable in
The construction industry
99
Contractor must submit to the architect and notarized application for payment ___ days before the date established for each payment in the owner contractor agreement
10 days
100
The amount due to the contractor at each periodic payment is based on
The schedule of values of the contractor submits to the architect after the award of the contract, allocating the total sum to specific portions of the work.
101
Before the final certificate for payment can be issued, the contractor must submit to the architect The following
- and affidavit that all debts have been paid - certificate of insurance remaining will not be canceled or expire without at least 30 days written notice to the owner - written statement that no reason insurance not renewable - consent of surety to final payment - releases and waivers of liens
102
Who issues the certificate of substantial completion
The architect
103
At completion contractor must submit to the owner following items
- all warranties, instructions, certificates of inspection, and bonds - A set of record drawings if required by the owner contractor agreement - certificate of occupancy as issued by the building department - extra materials per specification
104
Who issues certificate of occupancy
Building department
105
Architect services may terminate when
Final certificate for payment is issued