Bidding and Contracts Flashcards
(84 cards)
DIVISION 1
General Requirements
What are the disadvantages to the design-bid-build process
- accurate cost unknown until design is done
- bids that exceed the owners budget cannot be readily accommodated without jeopardizing the project
- The various parties tend to be adversarial
- Errors or omissions in design may lead to costly change orders
- A negotiated contract eliminates many of these concerns (and some of the advantages as well)
What is the purpose of a short list in the bid process
To ensure the contractors bidding have the qualifications needed to complete the work
Value Engineering
essentially relates to reviewing the contract documents with the owners best interest in mind
What phases can Value Engineering be applied
design and construction phases
Constructability Review
an assessment of the contract documents prior to the bidding phase, to identify problem areas and suggest improvements
Instructions to Bidders
rules by which the project will be bid
Addenda
clarification and changes to the bid documents after the start of the bid notice
Alternates
alterations to the base bid, in general, bed to avoid
Bid form
included in the bid documents, allows for easy comparison of bids
Give an example of an irregular or nonconforming bid
- Missing signature
- Missing a bond or a bond from an approved surety
- Late submission
Under what conditions might the low bidder be able to withdraw the bid, even though the bids have already been opened?
Request has been made to the owner, in writing, before the time set for opening the bids
In public projects how is the winning bidder chosen
lowest responsible bidder submitting a regular bid
What unique risks are taken by a contractor who is not licensed?
Cannot use the court system as a means of redress for any construction-related disputes
Why might a mistake in a bid be seen as grounds for nullifying the bid?
There is no meeting of the minds
What is reverse auction and what are the issues potentially
all the contractors can see other bids submitted online but can be seen as unethical/bid shopping
Who owns the design in public projects verse public projects
In public projects, the owner, and in private project, its established in the contract
General drawing categories on building projects (6)
general information and site work, structural, architectural, plumbing, heating/AC/Ventilation, and Electrical
The project manual consists of which sections
bidding documents, general conditions, supplementary provisions, and the technical specifications
What is the underlying purpose of the general conditions, or boilerplate, of a construction contract
Outline the rules under which the project will be built
Establish the rights, authority and obligations of the contracting parties
What is the general purpose of supplementary provisions or special conditions in a construction contract
Specific to the job being constructed
What is the significance or value of using CSI format in preparing the technical specifications for a building project
- Widely used, helps the user become quickly oriented with the project
- Divisions listed on page 161 of Hinze
In the case of a conflict between plans and specifications which will govern
the specifications
If an item is not present in either the specs or the drawings but is in the other, how does the contractor bid the project
The contractor will still include that in their bidding process. They can use a request for information (RFI) submitted to the architect to clarify.