Black Spactacles - Session 001 Flashcards
(52 cards)
Addenda
Issued during bidding by the architect to clarify or modify the bidding documents. They are written
documents sent to all bidders that become part of the contract documents.
RFI
Request for information: a standard form for contractors to ask for more information from an architect.
RFIs are used to resolve gaps, conflicts, and ambiguities in the drawings and specifications. They are a
fundamental part of a smooth project delivery.
Bidding documents
Documents that include the bidding requirements, any supplements to bid forms, contract forms and
conditions, specification, drawings, and any addenda issued by the architect during the bid period.
A201
An AIA document dealing with general conditions for the construction contract. The document sets forth
the rights, responsibilities, and relationships between owner, architect, and contractor.
Supplemental conditions
Special provisions in a contract that modify or qualify the general conditions. These can include additions, subtractions, local requirements, etc., to A201.
What are the owner’s responsibilities during the design and construction process?
The owner’s primary responsibility is to make payments to those that are contracted directly to the owner. The owner is also responsible for providing necessary site documentation (soils report, survey, etc.).
Pre-bid conference
A conference that is held to help clarify any concerns bidders may have about the construction documents, scope of work, and other details of the project.
GC
General contractor: the entity that enters into a contract with the owner for the work and coordinates subcontractors to complete the work.
Prime contractor
Contractor responsible for completion of the work. There can be more than one prime contractor on a project, depending on the scope and timing.
Joint venture
Two or more contractors may create a new entity for the sole purpose of bidding on a job together. This new entity, the joint venture , will be the prime contractor. This can occur when GCs want to bid on a project but don’t have the capacity in-house for the project or when there are MBE/WBE requirements for the prime contractor, among other situations.
Name the series/types of AIA contract documents
A-series: contracts between owner and contractor.
B-series; Contracts between owner and architect.
C series: contracts between architect and consultants.
D-series: architect industry documents.
E-series: exhibits.
G-series: administration documents.
Project manual
A document containing information required for bidders to review, including bid requirements, drawing list, contract conditions, contract forms, and specifications.
Bid requirements
Documents listing the requirements for the contractor to bid, including the invitation to bid, list of information available to bidders, instructions to bidders, bid forms, and bid supplements.
A701
Instructions to bidders. Used to provide instructions to bidders on procedures including bonding requirements and instructions for bidders to follow in preparing and submitting their bids.
Bid date
Date by which all bids need to be received. In general, bidders are given 2–6 weeks to prepare bids and ask for clarifications and substitutions.
Bid form
A document that assists the bidding process by providing a standardized form for all bidders to submit their bids. It includes a breakdown of all the material and labor costs associated with the job.
Schedule of values
Breaks down, line by line, each portion/trade involved in the work, assigning it a monetary value.
Qualifications
Modifications by the contractor to drawings and specifications. These can modify the products used, remove scope from the contractor’s portion of the work, and modify specifications. They are reviewed by the architect and owner before becoming an exhibit in the contract.
Alternate
A proposal by the bidder to add or deduct from the base bid. This could include alternates for additional scope as required by the owner/architect over the base bid, deducts for removal of scope or substitution of materials, etc. They are provided as separate line items so that the base bid provides the price of the work for equal scope from all bidders.
Allowance
Line item provided in the contractor’s schedule of values for scope of work that is not provided in detail
How is the low bidder determined?
The low bid is determined by adding the sum of the base bid and the cost of additive alternates, and subtracting the cost of deductive alternates. Unit cost estimating cannot be used to determine the low bidder.
Bid bond
A guarantee by the contractor to the project owner that the winning bidder will take on the project under the terms at which they bid.
Performance bond
A surety bond issued to guarantee satisfactory completion of a project by the contractor.
Payment bond
A surety bond posted by the general contractor to guarantee that subcontractors and material suppliers on the project will be paid.