BOD Flashcards

(23 cards)

1
Q

Field water depths ?

A

40m to 85m

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Components of “Honeybee” field development plan (3) ?

A
  1. Jackup MODPU
  2. flexible retrievable export flowline system,
  3. CALM moored FSO
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is CALM moored ?

A

Catenary Anchor Leg Mooring System -

Floating buoy anchored to the seabed by catenary chain legs which are secured to anchors or piles.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

PLEM

A

Pipeline End Manifold

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

MODPU definition ?

A
  • Mobile
  • Offshore
  • Drilling
  • Prodution
  • Unit
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What will CALM moored FSO storage be replaced by ?

A
  1. Relocatable subsea crude oil storage tank
  2. CALM for mooring of export tankers (during crude oil liftings)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

MODPU key drivers (6) ?

A
  1. low CAPEX (new build or conversion)
  2. high residual value (easily separable / one single lift Production Module) - back to MODU
  3. able to process a range of fluid types/rates/ pressures, gas-oil ratios and water-cuts.
  4. handle varied metocean, geotechnical and water depth conditions.
  5. relocated quickly
  6. operated with minimal crewing.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Export Flow line and PLEM key drivers (2) ?

A
  1. quick install/retrieve
  2. w/o sat diving
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

CALM Mooring key drivers (4) ?

A
  1. quick install/retrieve
  2. w/o sat diving.
  3. light-weight,
  4. low cost
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are the key principles of “Honeybee” field development plan ?

A
  1. discovered stranded oilfields (1-8mmbbl)
  2. sub-economic to reduce uncertainty by drilling further appraisal wells
  3. produce until commercial threshold reached then move on to another field
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are the unique Innovations of Honeybee model (6) ?

A
  1. No WHP - Tensioned Well conductors tied back to the MODPU
  2. Wells drilled/completed with light weight hydraulic automated DM located on the PM (lower footprint/cost)
  3. ESPs- lower $ dry trees base case.
  4. MODPU (DM) able to supt wireline ops / ESP workovers / well abandonment
  5. On-board storage (MODPU); 20 - 30,000 bbl in hull (maybe in tanks on seabed) for;
    • ongoing production during short-term FSO disconnect (Cyclone, FSO swap out).
    • continuous ops for ESPs (without need to shut-in wells.
  6. Proven tech only - min 2 years
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Corowa Field

A
  1. Best Field, but only 50km from Ningaloo Reef
  2. Bought from Santos
  3. 85m
  4. P10/50/90 = 4/7/12 (potenital 13m upside)
  5. Non waxy
  6. to be developed with a single horizontal well
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Sage Field

A
  1. 67m
  2. P50 of 1.4m (potential 4m upside)
  3. Non waxy to be developed using a single well, possibly with multi-laterals
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

MetOcean Data - status ?

A
  1. Metocean complete for the Corowa, Sage and Tusk/Okapi.
  2. MODPU to be designed for 1/100yr storm
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Geotech Data (4) ?

A
  1. Not performed.
  2. Surveys reqd for MODPU and mooring anchor locations once locations confirmed
  3. Currently using pre-spud survey data
  4. basically all strongly cemented carbonate sediments
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is the Design Life (4) ?

A
  1. 5 years
    • static subsea flexible flowline
    • floating marine hoses for CALM and crude oil export
  2. 10 years
    • PM
    • DM
    • FLET
    • CALM Bouy
  3. 40 years
    • JU Hull
  4. Production Uptime
    • 98%
17
Q

What is RAM Analysis ?

A
  • Reliability,
  • Availability
  • Maintainability

Predicts asset performance - feeds back to NPV

18
Q

JU Hull Selection

new or refurb’d ?

Refurb types ?

A
  • Pref new build
  • Friede & Goldman JU-2000E
  • Zentech R-550D
19
Q

Producution Module (PM)

Key attributes?

A
  • Located on JU Unit Deck -
  • PM+DM assembly to be retracted during MODPU relocation
  • PM layout will be revised to have two (2) decks only
20
Q

Jack Up Unit Hull

What systems does it support (11) ?

A
  1. Storage for: Fuel / water / Mud
  2. Jack up Systems
  3. Mooring Systems
  4. Marine Loading Hoses
  5. Cranes and Hoisting systems
  6. Helicopter
  7. Comms / Power / Utility
  8. Mud Mixing
  9. Accom
  10. Safety Equip
  11. Pollution Fighting Equip
21
Q

Taunton (4) ?

A
  1. Operated by Apache
  2. Hydra own 15%
  3. P10/50/90 = 2/5/8
  4. Apache spent $65m drilling an appraisal well - much data not much data return
22
Q

Cornea (3) ?

A
  1. Was owned by Shell who walked away
  2. Now owned by Albas
  3. Hydra currently negotiating for 75% P10/50/90 = 2.5/5.5/9
23
Q

Outtrim

A
  1. Next to Corowa
  2. Who currently owns ?
  3. P10/50/90 = ?/3/?