Breach And Performance and Remedies Flashcards
What is the basic rule of performance - Performance and breach answers found on Moodle
The basic rule is that the performance must be exact and full, according to the requirements of the contract.
Case that shows full performance - same as card 1
Cutter v Powell (1795)
Cutter was contracted to sail from Jamaica to Liverpool, the pay was 30 guineas provided he did his duty all the way to Liverpool. (this was higher than the usual rate) The ship set sail on 2nd August, Cutter died on 20th September and the ship got to Liverpool on 9th October.
His widow was unable to claim a proportion of his wages as he had not completed the voyage from Jamaica as he was contracted to do, the contract specified complete performance.
Case that shows exact performance same as card 1 and law e-resources
Re Moore and Landauer (1921): Here tins of fruit were to be delivered in cases of 30. In fact they were delivered in cases of 24.
Held: The purchaser was entitled to reject the goods as they were not as described although the agreed overall number of tins was supplied.
Exceptions to the rule that performance must be exact and full
Filler
Performance may have been attempted C1 and law e-resources
Startup V Macdonald (1843)
Claimant had the last 14 days of the month to deliver oil; he did so on the last evening at 8.30 and was refused access because of the lateness of the hour. This enabled him to sue for payment as he had offered performance.
The contract may be severable meaning and case C1
This means that it may be possible to split the contract into several smaller obligations, each of which can be seen as a contract in its own right.
Roberts v Havelock (1832)
A ship was docked for repairs while en route. Half way through the repairs the claimant asked for money for the work done so far. he was successful as the contract was seen as severable, the contract did not require him to complete all the repairs before the payment was due.
The contract may be substantially performed meaning C1
If a small amount needs to be done, there can a claim for the price minus cost of finishing the work.
Dakin V Lee (1916) C1
Builders carried out work to the defendant’s house. They departed from the specification in some minor ways, which could be remedied at minor cost. The builders were able to claim the price of the contract minus an allowance for the repairs still to be done.
Bolton V Mahadever (1972) C1
The claimant installed central heating in the defendant’s house for £560. It did not work and poisoned the inhabitants with toxic fumes. The claimant was unable to claim the price of the work minus the cost of remedy, as there had not been substantial performance.
There may be voluntary acceptance of partial performance C1
Sumpter v Hedges (1898)
Claimant did half a building contract then abandoned it and left the defendant to finish the work.
He claimed a quantum meruit (deserved amount) for the work he had done.
HELD he could not claim any money because the work was not substantially performance and the client had not given their consent to terminate the contract early.
When does a delay allow the other side to terminate the contract?
Filler
A specific date may be included in the contract C1
Union Eagle v Golden Achievement (1997) Privy Council
The purchaser of a flat had paid a 10% deposit of the $4.2million price. The contract stated that if the purchase was not completed by a specified deadline the seller would terminate the contract and the purchaser would lose their deposit. The purchaser was 10 minutes late and the seller refused to complete the sale.
HELD The terms were very clear and in a case like this certainty is most important – the purchaser lost their deposit and had no right to the flat.
The parties may give notice during the period of the contract C1
Rickard v Oppenheim (1950)
Early in 1947 the defendant ordered a Rolls Royce car body, in July the claimants promised to deliver it in 6 or 7 months. After 7 months they had not made it and promised it to him in another 3 months. After this they still did not have it so he said that he would cancel the order if they did not have it in 4 weeks. After another 3 months the chassis was ready but the defendant refused to pay for it. HELD as he gave a time limit and then an extended time beyond that he was not in breach of contract and could refuse to take the chassis.
Unless time is of the essence, delay is a breach of an innominate term C1
Astea Ltd v Time Ltd (2003) Technology and Construction Court
A company ordered some software to run their sales operations. After a long delay the clients cancelled the contract and sued for damages.
HELD the delivery date had not been made into a condition, no final notice had been given and the client had not lost substantially the whole benefit of the contract, therefore they were not entitled to repudiate.
What is anticipatory breach C1
When a party says to the other that in the future they do not intend to perform their contract obligations.
What the parties can do is on the following cards
Sue immediately C1
Hochster v De La Tour (1853)
The claimant was hired to work as a courier, to start in 2 months time. After one month they cancelled the contract and he sued for breach. Their defendant was that he could not sue until the time when the contract should have started.
HELD He could sue immediately as they had made it clear that they intended to breach the contract.
Wait and see C1
If they do this they run the risk of losing their claim if it becomes frustrated.
Avery v Bowden (1856)
B was contracted to carry a cargo for A. When it became clear that A was not going to perform the contract (had no cargo for B to carry) B waited to see if the situation would change and A would in fact perform his obligations. Before the date due for performance a war broke out and the contract was frustrated. This relieved A from any further obligations, although B could have sued him before this time, because the war broke out while B was waiting they lost the right to sue.
Go ahead and perform the contract anyway C1
White & Carter v McGregor (1962)
A contract provided that a company was to provide litter bins for a local council that was to be paid for by advertising on the bins. They contracted with a business to have adverts on the bins however the business backed out of the arrangement before the adverts were prepared. The response of the bin company was to ignore this breach and continue with the contract, placing the adverts on the bins anyway.
HELD they were entitled to claim the price of the contract.
Remedies
Filler
Damages meaning Week 6 remedies
Damages means money. This is a common law remedy, what this means is that if you are entitled to damages it doesn’t matter if this would lead to a harsh or unfair outcome, the court has no discretion.
Damages can be claimed for financial losses that result from non-performance and this can include loss of profits and any physical damage or harm.
If there is no actual loss there can be no claim for damages for breach of contract.
Orders meaning W6R
Orders are things like specific performance and injunctions. These are equitable remedies, this means the court has some discretion and would not award them if it would be unfair in the circumstances.
When damages can not usually be claimed
Filler
Damages can not usually be claimed for mental distress in a commercial contract W6R and law e-resources
Addis v Gramophone Co Ltd (1909)
The claimant was employed as a manager by the defendant. Shortly afterwards they sacked him and replaced him with a new manager.
The manager was entitled to damages for loss of pay but not for disappointment or damage to his reputation.
What was held by law e-resources - Contract law seeks to put the parties in the position they would have been in had the contract been performed. He was therefore limited to claiming wages and loss of commission during the contractually agreed notice period. There was no right to exemplary damages or damage to reputation in contract claims. Such claims would have to be actioned in the law of tort.
When can they claim for mental distress in a commercial contract W6R
Although they can if the main point of the contract is pleasure
Farley v Skinner.
Farley contracted with Skinner for Skinner to survey a potential house for aircraft noise, Skinner concluded that aircraft noise was unlikely.
After moving in Farley discovered that the house was directly under Gatwick airport’s circuit. He could claim damages for inconvenience because that was the point of the contract.