C - Procurement and Tendering Flashcards
(90 cards)
What is Procurement?
Relates to how the services of a contractor are purchased
What is Tendering?
Relates to how the successful contractor is ultimately selected
What Australian Standard provides guidance to tendering practices?
AS 4120 - 1994 Code of Tendering
What is the purpose of the Code of Tendering?
To encourage high ethical standards in tendering in the construction industry.
It imposes an obligation on all parties to refuse to condone unethical behaviour by others in the industry.
What is a procurement strategy?
Entails weighing up the benefits, risks and financial constraints of a project which will be reflected in the choice of contractual arrangements
What is required to determine the most appropriate procurement strategy?
QS must identify the client’s attitude to risk in the following areas:
1) Time
2) Cost
3) Quality
The following should be addressed:
- What are the risks?
- What will their impact be?
- What is the likelihood of the risks occurring?
- Who will be responsible for the management of the risk?
What considerations should be addressed when selecting a procurement route?
Clients attitude to the following:
1) Exposure to financial uncertainty
2) Requirement of control over the design & construction
3) Extent of design information at tender
4) Required extent of involvement of contractor / supply chain
5) Distribution of risk, responsibility and accountability
6) Client resources and knowledge
7) Complexity of the project
8) Timing of the project
What are the most common procurement routes?
1) Traditional
2) Design and Construct
3) Management Contracting
4) Construction Management
What is Traditional procurement?
1) Design is completed before going to competitive tender
2) Main contractor is employed to build what the designers have specified
When may Traditional procurement be appropriate?
1) If the Client has had the design prepared
2) If the design is substantially completed at the time of contractor selection
3) The client wishes to retain control over the design and specification
4) Cost certainty at start on site is important
5) The shortest overall programme is not the Client’s main priority
BENEFITS IN COST & QUALITY AT THE EXPENSE OF TIME
What is the risk profile of Traditional procurement?
Contractor
- Responsible for the financial risk of the construction of the Client’s design, for a fixed fee within an agreed contract period
Client
- Responsible for the performance of the design team
What are the advantages and disadvantages of Traditional procurement
ADVANTAGES
- Simple, well defined and understood process
- Obtains the most competitive price
- Client retains design control
- High level of cost certainty before commencement
- Changes are reasonably easy to arrange and value
DISADVANTAGES
- Longer overall project duration
- No Contractor input into design and planning
- Dual point of responsibility
- Quality dependent on the appointed design team
What is Design and Construct procurement?
Where the Contractor is responsible for the design, planning, organisation, control and construction of the works to the Employer’s requirements
When may Design and Construct procurement be appropriate?
1) Where there is a need to make an early start on site - design and construction phases can overlap
2) Where the Client wishes to minimise their risk - not responsible for design
3) For technically complex projects - benefits of Contractor expertise
4) Where the employer does not want to retain control over the design development
BENEFITS IN COST & TIME AT THE EXPENSE OF QUALITY
What are the advantages and disadvantages of Design & Construct procurement?
ADVANTAGES
1) Single point of responsibility for design and construction
2) Reduced project duration
3) Benefit of Contractor’s experience harnessed during design
4) Early price certainty
DISADVANTAGES
1) Client may have difficulty preparing a sufficiently comprehensive brief (Employer’s Requirements)
2) Client has to commit to a concept design early
3) Variations from the original brief are difficult to arrange and often expensive
4) Harder to compare tenders
5) Ease of fabrication may be prioritised over quality
What is Management Contracting?
A management contractor is employed to contribute their expertise to the design and manage construction and is paid a fee for doing so.
Project is split into works packages which are individually let through the Management Contractor
How does Management Contracting work in practice?
1) The management contractor has direct contractual link with all ‘works contractors’ - Client’s contractual link is to the management contractor, not the works contractors.
2) Management contractor has the responsibility for the construction works, without actually carrying out the works
3) Client employs the design team
4) Not all of the design needs to be completed before the first works contractors start work
5) MC selects the works contractors through competitive open book tendering
6) The client reimburses the cost of these packages to the MC plus their fee
7) The MC’s risk is low - they get prime cost plus a fee
When may Management Contracting be appropriate?
1) Where the Client is not prioritising cost certainty before commencement
2) When an early start on site is the priority
BENEFITS IN TIME & QUALITY AT THE EXPENSE OF COST
What are the advantages and disadvantages of Management Contracting?
ADVANTAGES
1) Overall project duration is shorter
2) Contractor contributes to the design and planning process
3) Changes can be relatively easily accommodated into packages not yet let
4) The works are let competitively at current market prices on a firm price basis
5) Client retains design control
DISADVANTAGES
1) Increase financial risk to the Client:
a) Management Contractor is paid a fee and does not take project cost risk - Client is exposed
b) Cost certainty is not achieved until the final package is let
2) Changes in the design of later packages may affect packages already let
3) Although procurement is fast, time certainty is poor until the final package is let
What is Construction Management
The Client places a direct contract with each of the trade contractors and utilises the expertise of a construction manager, who acts as a consultant to co-ordinate the contracts.
How does Construction Management work in practice?
1) Trade contractors directly contracted to the Client to carry out the work
2) Construction Managers supervise the construction process and co-ordinate the design
3) CM has no contractual link with the trade contractors, or members of the design team
4) The CM role includes preparation of the programme, determining requirements for site facilities, breaking down the project into suitable works packages, obtaining and evaluating tenders, co-ordinating and supervising the works
When may Construction Management be appropriate?
1) Large, complex projects where the advantages of the Construction Manager can be put to use
2) Where early start on site is key
3) Flexibility in design, procurement and construction strategy
4) Where price certainty before commencement is not key
5) Where the Client is experienced in construction
BENEFITS IN TIME & QUALITY AT THE EXPENSE OF COST
What are the advantages and disadvantages of Construction Management?
ADVANTAGES
1) Overall project duration is shorter
2) Construction Manager can contribute into the design and project planning process
3) Roles, risks and relationships for all parties are clear
4) Changes in the design can be accommodated without paying a premium
5) Prices may be lower due to direct contracts with trade contractors
6) Client has means of redress to trade contractors through direct contractual links
7) Client maintains design control
DISADVANTAGES
1) Increased financial risk to the client
a) Construction Manager does not take project cost risk - Client is exposed
b) Cost certainty is not achieved until the final package is let
2) Changes to the design of later packages may affect packages already let which would make the change expensive
3) Need an informed, pro-active client - all parties report to them
4) Client has a lot of Consultants and Contractors to deal with - not just one - more fees and more time
5) Although procurement is fast, time certainty is poor until the final package is let
What is the difference between Management Contracting and Construction Management?
MANAGEMENT CONTRACTING
- Client has contract with Management Contractor only
- Management Contractor is in direct contractual relationship with the trades contractors
CONSTRUCTION MANAGEMENT
- Client has direct contractual relationship with all trades contractors
- Construction Manager does not have a contractual relationship with the trades contractors