CAPM Flashcards
(213 cards)
What document formally authorizes a project and grants authority to the project manager?
The Project Charter is the official document that authorizes the project’s existence and assigns the project manager.
Who is responsible for reviewing and approving change requests?
Change requests are reviewed and approved by the Change Control Board (CCB) in the Perform Integrated Change Control process. The Project Sponsor may approve major changes but usually defers to the CCB.
What is the main output of the Develop Project Management Plan process?
The Project Management Plan is the comprehensive document that guides project execution, monitoring, and closure.
During project execution, a stakeholder requests a change. What should the project manager do first?
Document it and analyze its impact.
What is the final step in the Close Project or Phase process?
Obtaining formal acceptance of deliverables
A project manager is about to start planning a new sales software development project and will work with the project team to create the project management plan. What will the project manager and the team not use during planning a project?
A) Work Performance Information
B) Scope Statement
C) Scope Baseline
D) Risk Register
Answer: A) Work Performance Information
The work performance information is an output of monitoring and controlling and is not used during planning the project. Scope statement, scope baseline, and risk register are all created during the planning processes.
The project manager has received a change request from the project sponsor to reduce the budget by 20%. After the project manager has reviewed the change, he decides that the only way this can be done is by removing a part of the project that was not completed yet. Who needs to approve this change?
A) Project Team
B) Change Approval Board
C) Change Management Board
D) Change Control Board
Answer: D) Change Control Board
The change control board (CCB) is a group that helps the project manager to assess, and deny or approve changes. The project team may help assess the change, but do not approve it. Change approval and management boards are made up terms.
The CEO of a small business has requested that the company’s accounting software be upgraded to better support the financial records. He has requested that the software include a report that can forecast the following month’s expenses. Where should the CEO outline why this project needs to get done?The CEO of a small business has requested that the company’s accounting software be upgraded to better support the financial records. He has requested that the software include a report that can forecast the following month’s expenses. Where should the CEO outline why this project needs to get done?
A) Business Documents
B) Scope Outline
C) Scope Statement
D) Work Breakdown Structure (WBS)
Answer: A) Business Documents
The business documents contain two parts, the business case and the benefits management plan. In this question, the business case would be use to explain why the project needs to get done. Scope outline is a made up term. Scope statement and the WBS only have the work needed to finish the project.
Project manager Mike worked with the sponsor Chris to get the project charter approved for the new office reorganization project. While reviewing the requirements, both Mike and Chris are sure that there is no need to upgrade the current wireless network in the office. Where is the best place Mike and Chris can store this information?
A) Project Charter
B) Business Case
C) Assumption Documentation
D) Assumption Log
Answer: D) Assumption Log
Mike and Chris are making an assumption since they are confident, but have not verified. The assumption log is used to track all assumptions made throughout the project. A project charter and business case will not have assumptions. Assumption documentation is a made up term.
While working on creating a project management plan, the project manager has brought a group of expert programmers and planners to ensure it is created correctly. What tool best describes this approach?
A) Meeting
B) Interpersonal and Team Skills
C) Data Analysis
D) Data Gathering
Answer: D) Data Gathering
The tool that is being used is a focus group, which is part of data gathering. Meeting and interpersonal and team skills do not contain a focus group. Data analysis is used to analyze data that that was already gathered.
When a project has been executed, what input would best help the project manager determine how to manage changes to the project?
A) Change Control Plan
B) Project Management Plan
C) Change Control Board
D) Change Control Charts
Answer: B) Project Management Plan
The project management plan contains the change management plan. The change control board is a tool, not an input. Change control plan and change control charts are made up terms.
Company XYZ has been executing a new business development project for the last 4 months. Stakeholders have requested several changes to the scope and have gotten them approved. After a change is approved, what is the best next step to conduct on a project?
Execute the approved change request in the process of Monitor and Control Project Work
Once a change request has been approved in the perform integrated change control process, the project manager will then execute the change in the direct and manage project work process.
A change control board has informed the project manager that a change request made by stakeholder Mark to reduce the schedule of the project by 2 weeks was rejected. What is the first step the project manager should take?
Once a change has been approved or rejected, the project manager should update the change log to reflect the status of the change. Asking Mark to reduce his change request by 1 week would need a new change request.
The deliverable for the product improvement project has been accepted by the sponsor. What should the project manager do next?
Once a deliverable has been accepted, the project manager should then conduct the close project or phase process. In that process, the project manager will conduct the lessons learned and release or reassign the project team. A project manager should never leave a project without formally closing it.
While getting ready to manage the project schedule, the project manager would like to document how accurate the schedule must be and what model the team would use to create the schedule. What document would this information be in?
The schedule management plan will describe how the schedule would be planned, developed, managed, executed, and controlled throughout the project. It would also have the level of accuracy, reporting formats, and the schedule model.
In developing the schedule management plan which of the following tools will the project manager use?
Data analysis is a tool that is used in plan schedule management which is used to create the schedule management plan.
The project manager has met with the project team to define the activities on the project. Which of the following components of the project management plan will the team NOT use to define the activities?
A) Work Breakdown Structure (WBS)
B) WBS Dictionary
C) Scope Statement
D) Activity Lists
D: Activity Lists
The WBS, WBS dictionary and scope statement are part of the scope baseline which is an input to the process of define activities. The activity list is the output of the process, not an input.
While conducting the process of define activities, a few of the team members has decided to use the lesson learned repository from previous projects. Which of the following input describes this lesson learned repository?
The organizational process assets include but not limited to the lesson Learned repository from previous projects and templates.
The project team has embarked on a very complex software development project and is currently having a difficult time decomposing work packages that will be done farther in the future. They have decided to decompose these work packages as they get closer to the work. What technique best represents the scenario?
Rolling wave planning is a planning technique in which the work to be accomplish in the future is decomposed as the work gets closer.
The Activity List and Work Breakdown Structure (WBS) are used to help create the Scope Baseline and the Schedule Baseline. Which of the following statements is true regarding these two documents?
A) The WBS is not part of the Project Management Plan, while the Activity List is
B) The Activity List is part of the Schedule Baseline, and the WBS is part of the Scope Baseline
C) The Activity List and WBS are both part of the Schedule Baseline
D) The Activity List and the WBS can be developed either sequentially or concurrently
D: The activity list, WBS, and the WBS dictionary can be developed either sequentially or concurrently.
While decomposing project activities, which of the following statements is true regarding the usage of this technique?
A) It is only done once per project
B) Involving the team members can lead to better and more accurate results
C) It is a tool used in Sequence Activities
D) It is used to create the Project Scope Statement
B: Decomposition is best done when the team members are involved since they are considered to subject matter experts and will generally lead to more accurate result. It should be done throughout the project as more work is done and understood. It is not a tool used in sequence activity or defined scope processes.
The project sponsor is examining the project schedule and has noticed a few activities with a duration of zero. What best describes these activities?
Milestones have a zero duration because they represent a significant point or event on the project
While working on a large building development project the team has identified a particular warehouse they would use to fabricate the steel beams. Where would the team store this information?
The activity attributes can be used to identify the place where the work is to be performed.
Which method is used to construct a schedule in which activities are represented by nodes and are graphically linked?
The precedence diagramming method is used to construct a schedule in which the activities are represented graphically using nodes and are linked based on their relationship.