Planned Value

A

PV = percent complete of where the project should be

2
Q

Earned Value

A

EV = percent complete * BAC

3
Q

Cost Variance

A

CV = EV - AC

4
Q

Schedule Variance

A

SV = EV - PV

5
Q

Cost Performance Index

A

CPI = EV / AC

6
Q

Schedule Performance Index

A

SPI = EV / PV

7
Q

Estimate at Completion (typical variance)

A

EAC = BAC / CPI

8
Q

Estimate at Completion (atypical variance)

A

EAC = BAC + AC - EV

9
Q

Estimate at Completion

A

EAC = AC + ETC

10
Q

Estimate to Complete

A

ETC = EAC - AC

11
Q

To-Complete Performance Index (BAC)

A

TCPI = (BAC - EV) / (BAC - AC)

12
Q

To-Complete Performance Index (EAC)

A

TCPI = (BAC - EV) / (EAC - AC)

13
Q

Variance at Completion

A

VAC = BAC - EAC