CAPM Glossary Pt. 2 Flashcards
(112 cards)
The earliest a project activity can finish. Used in the forward pass procedure to discover the critical path and the project float.
Early finish
The earliest a project activity can begin. Used in the forward pass procedure to discover the critical path and the project float.
Early start
The physical work completed to date and the authorized budget for that work. It is the percentage of the budget at completion (BAC) that represents the actual work completed in the project.
Earned value (EV)
The process of measuring the performance of project work against what was planned to identify variances, to note opportunities to improve the project, or to just check the project’s health.
Earned value management (EVM)
A communication tool in which the receiver is involved in the listening experience by paying attention to the visual cues from the speaker and paralingual characteristics, and by asking relevant questions.
Effective listening
A device that encodes the message being sent.
Encoder
A risk response that attempts to adjust the odds or conditions to ensure that a positive risk event will likely happen.
Enhancing
Conditions that affect how the project manager may manage the project. These come from within the project, such as policy, or they may be external to the organization, such as low or regulation.
Enterprise environmental factors (EEF)
A risk response that is appropriate for both positive and negative risk events that may be outside of the project manager’s authority to act upon.
Escalating
A forecasting formula that predicts the likely completed costs of the project based on current scenarios within the project.
Estimate at completion (EAC)
An earned value management formula that predicts how much funding the project will require to be completed. Three variations of this formula are based on conditions the project may be experiencing.
Estimate to complete (ETC)
The monetary value of a risk exposure based on the risk’s probability and impact in the risk matrix. This approach is typically used in quantitive risk analysis because it quantifies the risk exposure.
Expected monetary value (EMV)
The project manager’s authority comes from both their experience with the technology the project focuses on and from their expertise in managing projects
Expert power
Knowledge that can be quickly and easily expressed and communicated through conversations, documentation, figures, or numbers.
Explicit knowledge
A risk response that takes advantage of the positive risks within a project.
Exploit
Dependencies outside of the project’s control. Examples include the delivery of equipment from a vendor, the deliverable of another project, a decision of a committee, a lawsuit, or an unexpected new law.
External dependencies
Quality assurance provided to the external customers of the project.
External QA
Risks that are outside of the project, but directly affect it – for example, legal issues, labor issues, a shift in project priorities, or weather. “Force majeure” risks call for disaster recovery rather than project management. These are risks caused by earthquakes, tornadoes, floods, civil unrest, and other disasters.
External risks
A schedule compression method that changes the relationship of activities. With this method, activities that would normally be done in sequence are allowed to be done in parallel or with some overlap. This can be accomplished by changing the relationship of activities from finish-to-start (FS) to start-to-start (SS) or even finish-to-finish (FF) or by adding lead time to downstream activities. However, utilizing this method does add risk to the project.
Fast tracking
A communication tool in which the sender confirms that the receiver understands the message by directly asking for a response, questions for clarification, or other confirmation.
Feedback
An activity relationship type that requires the current activity to be finished before its successor can finish.
Finish-to-finish (FF)
An activity relationship type that requires the current activity to be finished before its successor can start.
Finish-to-start (FS)
Costs that remain constant throughout the life of the project, such as the cost of a piece of rented equipment for the project, the cost of a consultant brought on to the project, and so on.
Fixed costs
Agreements that define a total price of the product the seller is to provide. Also known as firm and lump-sum./
Fixed-price contracts