Case Study Flashcards
(110 cards)
Why did you select the JCT Minor Works Contract for this project?
- The works were simple in nature.
- Low value works (beneath £250k recommended limit for MW).
- No requirement for contractor design.
- No requirement for sectional completion.
- No requirement for third party rights (collateral warranties etc.).
How were Liquidated Damages calculated?
The LD’s were calculated by the client based on the likely loss to be suffered should the contractor fail to meet the completion date.
Was 5% retention applied for all payment certificates?
- 5% retention was applied to all payment certificates up to practical completion.
- 2.5% retention was applied to payment certificates after practical completion.
Did you or the Principal Designer prepare the PCIP?
The Principal Designer prepared the PCIP, however I assisted in gathering the relevant information from the client to be included in the PCIP.
Can you describe the contents of the Pre-Construction Information Pack?
- Nature of the project.
- Client considerations and management requirements.
- Environmental restrictions and existing on site risks (hazardous materials, contaminated land etc).
- Design and construction hazards.
- Health and safety information (construction phase plan).
- Designer risk assessment.
- F10 notification.
Who is responsible for producing the Pre-Construction Information Pack?
The client, however the PD will assist the client in gathering the relevant information.
Was an asbestos survey undertaken before the works were carried out?
Yes, an asbestos refurbishment and demolition survey was undertaken of the roof and internal ceilings.
Where is the requirement for undertaking of an asbestos refurbishment and demolition survey stipulated?
Regulation 5 of CAR 2012 – identification of the presence of asbestos.
Would Regulation 4 (duty to manage) apply to the property?
Regulation 4 only applies to common parts of residential properties (circulation areas).
Where might you find asbestos within roofs?
- Asbestos roof tiles.
- Asbestos bitumen sarking felt.
- Asbestos to cold water storage tanks.
- Asbestos insulation.
Were the external walls loadbearing? Was there a loadbearing internal brickwork skin?
Yes, there was an internal skin of brickwork to the external walls.
What was the construction of the flat roofs?
- Timber, finished with a combination of mineral felt and lead sheeting.
- Cold roof construction.
What does Part L of the Building Regulations refer to and what are the different parts Approved Document L?
- Conservation of Fuel and Power.
- Volume 1: Dwellings.
- Volume 2: Buildings other than dwellings.
You have mentioned the need for obtaining planning permission for increasing the roof height, can you please explain the process involved in obtaining planning permission?
- Submit a planning application to the LA planning department with correct fee and relevant documentation.
- The LA will validate the application and request any missing documents.
- The LA will acknowledge a valid application.
- The LA will publicise and consult on the application.
- Application considered by planning officer or planning committee.
The application will then either be:
- Not decided within the 8-week period.
- Permission granted.
- Permission granted with conditions.
- Permission refused.
What information/documentation should be included within a planning application submission?
- Plans and drawings (location plan scale to be 1:1250 or 1:2500).
- Existing and proposed drawings.
- Ownership Certificate and Agricultural Land Declaration.
- Design and Access Statement (for some planning applications).
- Fire Statement (for some planning applications made on or after 1 August 2021).
- Correct fee.
What is a design and access statement?
- A concise report accompanying certain applications for planning permission and applications for listed building consent.
- They provide a framework for applicants to explain how the proposed development is a suitable response to the site and its setting, and demonstrate that it can be adequately accessed by prospective users.
- Design and Access Statements can aid decision-making by enabling local planning authorities and third parties to better understand the analysis that has underpinned the design of a development proposal.
What is the typical duration for a decision to be made on a planning application?
8 (straight forward applications) – 13 weeks (large or complex applications).
What type of planning application was submitted?
Full plans.
How did you establish that the increase in roof height would require planning permission?
I submitted a Householder Planning Check form to North Yorkshire County Council, who undertook a “Permitted Development Check”, outlining the need for planning permission for the works.
What other method can be used to confirm works can be carried out under PD rights?
- Application to local authority for a certificate of lawfulness.
- Will confirm whether or not the works fall under PD and will likely be requested when selling the property.
Did the schedule of works that the contractor priced prior to your involvement need to be changed to ensure compliance with the Building Regulations?
Yes, this involved increasing the level of insulation to achieve a U-value of 0.22 (payback of 13 years).
What was your involvement regarding the schedule of works and how did this fall under your role as CA?
- I reviewed the quotation provided by the roofing contractor and transferred this onto a SoW excel document.
- Additional works were included within the final schedule of works and items were split to assist with undertaking interim valuations.
- Part of our appointment included pre-contract consultancy services around advising the client and assisting them with the contract documents etc.
Can you provide an example of an items included within the SoW and what was included for this in the SoW?
- Removal and reinstatement of existing slates.
- Allow for reinstatement of the slates. Slates are to be laid in diminishing courses and random widths, with a minimum head lap of 75mm, secured with two copper nails.
Can you please explain the construction and build-up of the existing pitched roof sections?
- Westmoreland slate covering.
- Timber battens.
- Timber rafters (75mm).
- Timber purlins.
- Combination of plasterboard and lath and plaster ceilings.
- “Crown” construction (hipped with tabletop).