How did you calculate the £8000 contingency sum for the patch repairs?
I worked with the design team to understand the full scope of works that might be required and build up a cost for the areas including the removal of the top layer, drying out, and the reinstatement of the vapour control layer and the roof tiles including making good to the flashings because the areas were at the corner of the flat roof.
Risk allowances and contingency are often used interchangeably but please can you tell me the difference between the two?
Contingency typically for unknown risks, risk allowance typically comes from a risk register of known risks.
You had a budget of £8000 to deal with the leakage but the contractor’s cost came to £400k for all the repairs. How did you communicate this to the client?
- I advised the client that the £8k was for patch repairs only and the works would definitely cost more, although at the time I was unsure of the full extent of the scope of works
- Because of the timescales I spoke to the client about the budget we had received as part of the options. Advising them that I do not believe it was a true representation of the costs that would be required.
What are the different types of waterproofing?
- Structural / Integrated wtaerproofing
- Barriers, which is what we used on Silbury House
- Cavity drain systems
What is a typical build up of a flat roof?
On Silbury House it was:
- Metal roof deck £120 m2
- Vapour control layer
- Insulation
- Waterproofing
You mentioned there were 38 EAIs. Can you talk me through why there were so many and the change control process on the project?
At what RIBA design stage was the design responsibility shifted to the Contractor?
Any allowance for design development risk that would have protected the client from additional costs
How did you arrive at the contingency sum of £8000. Did the contractor’s price include for fixing the leak?
What was the contractor’s proposal for fixing the leak identified after the first survey.
By consulting a specialist roofing consultant, are you acting ethically?
What was the scope of works covered under the enabling works? – Why separate?
Does the project value reflect the initial works, or the enhanced requirements? How did they differ cost wise?
How did you get to your number of £8k for the patch repairs?
Do you know why the survey did not pick up the other areas of defects?
Was there an option to act on any existing warranties? Late
How did the 400k differ from the £180k you advised?
Was the 400k a budget or a fixed cost proposals?
Was there any differences in the revised value for £60k
Was the roofing advisor party to the contract? What would happen if their advise was wrong?
How important was cost to the client, given you were paying for all these enhancements to the scope? Were these included within your contingency
Did the contractor know about the surveys before they started?
In the contract, is there a timeframe for which they have to provide the cost for rectifying the leaks?
Is 2 weeks to issue an EAI a reasonable timeframe?