Case Study Q&A Flashcards
(56 cards)
What constitutes value for money?
In construction, value for money (VfM) means achieving the best possible balance between project benefits, quality, and overall cost, ensuring the project meets the client’s needs and objectives efficiently.
How did you ascertain the clients objectives?
I chaired a number of meetings with the client where we discussed his objectives and desired for the project.
I was also involved in a number of early design team meeting where we the initial design developed, which helped me understand the type of finish the client wanted to achieve.
Could you start on site earlier with a singe stage competitive tender and how?
Going out to tender with a less developed design including CDP and PSums
What is Management Contracting
management contracting involves a client appointing a management contractor to oversee the project, who then engages subcontractors directly
What is Construction management
the client directly employ’s trade contractors, with a construction manager acting as a consultant and advisor
Why do Management Contracting and Construction Management carry a higher financial risk?
The management contractor is paid a fee for their services, and they are also reimbursed for the costs incurred in managing the subcontractors.
The construction manager is paid a fee for their services
What can be done to eliminate/reduce design compromise under a D&B contract?
One option is formal novation, where the contractor assumes full responsibility for the design team, managing the remaining design process with the existing team. Alternatively, clients can retain a designer as a ‘technical advisor’ to scrutinize the work of the contractor’s chosen designer
Did you explain to the client that all four objectives (Time, Risk, Quality & Cost), may not be achieved?
Yes, typically 2 or 3 of these priorities take precedence and are achieved at the sacrifice of the other(s)
What design stage was the project tendered at?
RIBA stage 4.
On a single stage competitive tender, is there a way you could allow part of the design to be less developed?
Yes, through the use of CDP and PSums.
Traditional two-stage tender - How did you ensure competitiveness throughout the second stage?
You could ask for 3 quotes for certain / large package.
In two stage how did you assess the risk apportionment on this approach?
Contractor would be appointed under a PCSA clearly defining their responsibilities for pre construction.
They can help reduce the level of risk associated with construction and design, through input of buildability and expertise.
Would require PII.
how can you still get value for money in a negotiated tender in construction
Open book approach - requesting 3 sub-contractor quotations.
Post tender KPI’s; performance, compliance and risk management.
- Cost tracking - are costs inline with the contract
What is a PCSA
The Pre-Construction Services Agreement enables the contractor to collaborate with the employer or their team of consultants to develop detailed designs.
What kind of information would you expect to be included in a PCSA.
including scope of work, payment terms, design liability, intellectual property, termination conditions, and often includes provisions for the services to be subsumed into the main works contract.
It should make clear whether the contractor is undertaking design work, whether they will have any design liability, and what will happen to this liability if they are not appointed for the second stage (the construction works). It should also set out the method of payment, and any provisions for deferred payment.
Can works be undertaken under a PCSA?
Yes, but it is not advised.
As no insurances or contractual clauses are included, I would recommend using a letter of intent to be more appropriate.
Is a Pre-Construction Agreement always necessary?
No, it’s a contractual agreement used in specific circumstances, particularly in design and build projects, to enable a contractor to commence design work before the main contract is finalized.
What is an alternative to a PCSA Agreement
Letter of Intent (LOI) - is a non-binding document outlining the preliminary agreement or intentions of parties before entering into a formal contract.
A letter of intent (LOI) is a possible alternative to a pre-construction service agreement (PCSA):
PCSA: A comprehensive, stand-alone agreement for a specific scope of work.
LOI: A temporary placeholder for a building contract that’s used when a preferred contractor has been identified but some details are still being worked out. LOIs are often used to give parties time to finish negotiations and start work while the final details are agreed. However, not all LOIs are legally binding.
Why is a traditional Single stage Tender time consuming Pre-Contract?
It involves a sequential process where design and tender preparation, evaluation, and potentially negotiation, all occur before construction can begin
What is Value Engineering
reduce costs while maintaining or enhancing functionality and quality.
Did you come up with the value engineering options yourself?
No, I discussed these with the wider design team, to try and establish, given the programme constraints, what we could VE
What is the difference between scope reduction and VE?
Scope reduction is the process of cutting activities associated with a project, while value engineering (VE) is a process that involves finding ways to reduce costs while maintaining the value of a project
Is VE purely about reducing cost?
No, value engineering is about a creative problem-solving process that aims to optimize value while minimizing costs.
Could you tell me the difference between Value Management and Value Engineering?
Value management (VM) and value engineering (VE) are both used to improve the value of a project, but they differ in their scope, approach, and when they are best applied:
Approach
VM is a positive process that seeks to balance time, cost, and quality, while VE can be seen as a negative process that focuses on eliminating costs.
Audience
VM reports are often strategic documents for a broad range of stakeholders, while VE reports are more technical and written for engineers or project managers.
Timing
VM should be carried out early in a project, while VE is more systematic and can be used to address specific functions.