CDS Flashcards

(98 cards)

1
Q

International Building Code

A
  • Created in 2000
  • From 3 main previous building codes
  • Primary Model Code
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Occupancy

A

Type of use of a building or interior space

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Occupancy Groups

A

10 major ones:

Assembly, Business, Educational, Factory and industrial, Hazardous, Institutional, Mercantile, Residential, Storage, Utility

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Fiduciary

A

a party to whom another party entrusts property for safekeeping. Failure to fulfill fiduciary responsibilities is determined not so much by the fiduciary’s actions as it is by the RESULTS (damages). Negligence does not necessarily have to be proved in order for the fiduciary to be liable.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Indemnification

A

‘Hold Harmless Clause’ - Contractual obligation where one party is unable to file claims against another from specific liabilities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Schedule of Values

A

A statement from the C to the A reflecting the $$ owed for each division of work. Serves as a guide for payment.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Record Drawing

A

NOT as-builts. Last approved DOB drawing issued to what SHOULD have been the final result.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Substantial Completion

A

Stage in the work where the O is able to occupy the space. C decides that its time, prepares Punch List, A & O inspects, if approved, A prepares Certificate of Substantial Completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Certificate of Substantial Completion

A

(G704) Document prepared by A, stating work is substantially complete. Signed by O, A & C

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Retainage

A

(A101) O withholds $$ from C, as protection against C potential failure to complete work from CDs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Quality Control

A

Careful checking of the work (drawings, const) before distributed to user (drafter, owner)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Statute of Limitations

A

Legislation which specifies period of time within which legal action must be brought in order to obtain legal relief for damage or injury.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Liquidated Damages

A

In O/C Agreement. $$ in contract charagable against C, for damages suffered by O, b/c C’s failure to contract. Usually results in delayed const, which is actual loss to O (Rent due, etc)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Mechanic’s Lien/ Lien

A

Claim against PROPERTY. Provides security that labor & materials will be paid in the event of non-payment by O. Forces sale of O’s PROPERTY. To protect owner: Retainage, Labor & Materials Bond, Affidavit and release of liens

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Changes in the Work

A

Change WITH additional or red. cost/time = Change Order (AIA form G701)
Change WITHOUT additional or red. cost/time = ASI (AIA G710 form)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Alternates

A

Changes in specific parts of CD’s that allow O to tailor bid proposals. May be additive or deductive.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Unit Cost

A

Cost of work determined by unit prices of materials. Used when quantity of materials are unknown for estimating purposes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Agent

A

Someone authorized to act on behalf of another party. (A is agent of O, typ.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Negligence

A

Failure to meet standard of care expects of an A

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Area/ Volume Estimate

A

Type of cost estimating, used in SD phase due to lack of details available. Used in conjunction with unit cost.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Subsystems Estimate

A

Type of cost estimating, used during DD and CD phase. Used to compare costs of assemblies once specifics become available.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Detailed Estimate

A

Quantity and Cost Method/ Labor and Material Method. Type of Cost estimating that requires more research on the A, which requires change order. Materials, quantity, and labor = total direct cost. C overhead, gen conditions cost, contingency, and profit = indirect cost. total direct + indirect cost = detailed estimate (extensive research and usually done by C estimator)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Bar Graph Schedule

A

Start and finish dates of phases of work, no indication of relationship b/w sequences of activities. Superior to CPM for visualization, inferior to CPM for management.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

CPM

A

Critical Path Method of Scheduling. Planning and management tool for C. CPM = network diagram.. continuous schedule. Most effective way to cut time, is to reduce CRITICAL PATH time, by reducing CRITICAL activities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Critical Activities (CPM)
Tasks along a critical path. If the activity is delayed, the completion of the project will delay (Critical Path Method of Scheduling)
26
Float Paths (CPM)
All paths in the network, other than critical. Measures extra time available, allows for delays to occur. (Critical Path Method of Scheduling)
27
Fast-Track Scheduling
Technique to save time in overall completion by combining A/E schedules with C schedule. Requires close coordination, usually need to hire CM to supervise. Additional service for A
28
Barrier-Free Provisions (ADA)
Regulations which provide accessibility to buildings and sites for persons with disabilities.
29
Accessible Route (ADA)
Continuous unobstructed path connecting all accessible elements.
30
Area of Refuge (ADA)
Area where disabled people are unable to use stairways and can remain while waiting for assistance. Area must be fire-rated and smoke-proof.
31
Clear Floor Space (ADA)
Minimum unobstructed floor space required to accommodate a single wheelchair (30" x 48")
32
Detectable Warning (ADA)
Surface feature built in to warn of hazards on a circulation path (i.e. subway yellow, domed lines)
33
Min. Clear Width for ADA route
36"
34
Accessible Route Slope (ADA)
Max 1:12
35
Door Min. Clear Opening Width (ADA)
32"
36
Accessible Door Hardware Height (ADA)
48" max. A.F.F.
37
Grab Bar Height (ADA)
33" to 36" A.F.F.
38
ADA Stall Dimensions
60" x 56"
39
Max Ramp Slope (ADA)
1:12
40
Top of Ramp Handrails (ADA)
34" - 36", extend handrail 12" past ramp
41
Ramp Length w/o Landing (ADA)
No more than 30 feet
42
Max Stair Riser Height and Tread (ADA)
Riser: 4" min, 7" max / Tread: 11" min. (no open risers)
43
Protruding Objects Rule (ADA)
below 27" = UL above 27" = 4" max
44
Min. Headroom in Circulation Spaces (ADA)
Vertical clearance of 80" (6'-8")
45
ADA Seating in Public Areas
5% fixed ADA seating of total amount of seating
46
Occupancy Group
A - Assembly (1-Theaters, 2-Restaurants, 3-Libraries, 4-Arenas, 5-Stadiums), B - Business (office, college), E - Education (HS), F - Factory and Industrial (1-High hazard, 2-low hazard), H - Hazardous, I - Institutional (1-group home, 2-hospitals, 3-jails, 4-daycare), M - Mercantile (retail, mall), R - Residential (1-hotels, 2-apartment, 3-b&b, 4-small assisted living), S - Storage, U - Utilities
47
Public Way (Egress)
Land unobstructed from the ground to the sky, appropriated to the public & clear width of 10 feet.
48
Occupant Load Factor
Amount of floor area presumed to be occupied for one person
49
Net SF
Space actually used
50
Gross SF
Space actually used + stairs, corridor, toilet rooms, mechanical rooms, closets, interior partition thickness.
51
Accessory Occupancy
space that is an accessory to main occupancy (less than 10% SF), that does not need to be separated from occupancy with fire barrier. (i.e. gift shop in hospital)
52
Incidental Accessory Occupancy
Space (less than 10% SF of main occupancy STORY) that is incidental to main occupancy (and in same group), but MUST be separated by a fire barrier (i.e. linen collection room on same floor as hotel rooms)
53
Occupant Load
of ppl that will occupy a space. Use largest number determined by one of 3 methods: 1) Actual # of ppl (count seats) 2) Use a LOAD FACTOR 3) Cumulative occupants EXITING through spaces = add load factors in diff. occupancies (auditorium LF + classrooms LF)
54
Means of Egress
Continious and unobstructed path of vertical and horizontal egress travel to public way. 3 parts: 1) The Exit Access = measured travel distance to exit 2) The Exit = portion of egress that is rated from exit access to exit discharge 3) The Exit Discharge = portion of egress b/w building exit and public way
55
Common Path of Egress Travel
Portion of exit access for travel BEFORE other egress paths meet to two means of egress. Not to exceed 75' (100' in sprinklered)
56
Exit Access Travel Distance
Distance ppl must travel from to most remote point in space to nearest exit. Code limits length, based on occupancy and sprinkler system.
57
Width of Exits (Egress)
Occupancy Load x .03 (Stairs) Occupancy Load x .02 (Others, i.e. Doors) Factor >/= Code
58
Exit Corridor Min. Width (Egress)
44" (3'-8") | no projection of doors or handrails more than 7"
59
Egress Doors
1) 36" Wide (min) 2) 32" clear width 3) Must swing in the director of travel 4) Cannot swing into require travel PATH more than 7"
60
Approved Standards and Testing (BC)
All approved materials and assemblies required to be made with accepted testing methods or approved by agencies such as: ASTM, NFPA, ANSI, ASHRAE, NRTL, UL
61
Construction Types (BC)
Types I, II, III, IV, V. Type I is MOST fire resistant, Type V is LEAST fire resistant.
62
Allowable Floor Area and Height (BC)
Based on Const Type. More hazardous the building, the smaller it should be.
63
ASTM 119 (BC)
Construction Assembly Test for building construction and material. Evaluates assemblies to prevent passage of fire, heat, and hot gasses, for time. given rating according to time - 1-4hr for doors, 20/30/45 for other
64
NFPA 252 (BC)
Construction Assembly Test for door assemblies. given rating according to time - 1-4hr for doors
65
NFPA 257 (BC)
Construction Assembly Test for window and glass block assembly. Fire and hose stream test in units of time.
66
ASTM E84 (BC)
Finish Materials Test. Steiner Tunnel Test, measures surface burning characteristics of building materials. result has flame spread rating. Class A (I), B (II), C (III). A is most fire resistant.
67
NFPA 265 (BC)
Finish Materials Test. Room Corner Test. determines contribution of interior textiles to fire growth using a 3 wall room. sometimes used with test ASTM E84
68
NFPA 286 (BC)
Finish Materials Test. Evaluates contribution of wall and ceiling finish to room fire growth.
69
Fire Partition (BC)
Wall assembly with 1-hour fire rating. ex: corridor walls
70
Fire Barrier (BC)
More protection than fire partition. Vertical or horizontal assembly. Designed to CONFINE SPREAD of fire. ex: stairwell
71
Fire Wall (BC)
Fire rated wall, separating one structure from another OR one construction type from another. Must be 2 - 4 hour rating, extend from foundation through the roof.
72
Smoke Barrier (BC)
Continuous vertical or horizontal membrane with min. rating of 1-hour, designed to resist movement of smoke. Passive form of smoke control.
73
Privity
egal protection for the A from claims by parties with whom he/she has no DIRECT relationship
74
Tort
CIVIL wrong resulting from negligence as opposed to a criminal act
75
Arbitration v. Mediation
Arbitration - Non-litigation of resolving disputes, neutral 3rd party hears both sides and makes binding decision Mediation - both sides meet with neutral 3rd party and resolves disputes through compromise, rather than going through litigation
76
Application for Payment
notarized statement of value of work done to date of application and value of materials purchased. should be submitted at least 10 days before pay date
77
Proprietary Specification
AKA Closed/ Prescriptive Product is specifically listed by name and #, NO SUBS allowed. Why? A/O wants to see specific product
78
Descriptive Specification
All REQUIREMENTS of product are described (details, arrangement of parts, chemical props) Why? Most detailed, A assumes all responsibility
79
Performance Specification
Like open, but instead of manufacturers, lists required EXPECTATIONS and RESULTS for the product. Why? Allows contractor to competitively bid. (means to an end)
80
Open Specification
Lists 3-5 materials/products/systems, contractor can use any oft them or suggest his own (needs to prove performance is equal) Why? PUBLIC JOB, and allows for COMPETITIVE BIDDING
81
Reference Specification
Like open, but product has to meet specific testing requirements (UL, ASTM, ANSI) Why? You need things to conform to requirements.
82
Cash Allowance Specification
$$ decided upon per product, that hasnt been designed yet. | Why? You dont know WHATto use yet, but you know how MUCH $$ to spend
83
What are the Parts of the Spec Section?
1. GENERAL - Scope, related sections, quality control, required submittals, guarantees, warranties. 2. MATERIALS - materials, products, and equipment to be used 3. EXECUTION - instruction on how to install the product
84
What are the contents of the Project Manual?
1. Bid Form 2. Instruction to Bidders 3. Contract Forms (O/C Agreement (A101, Performance Bond, Payment Bond, Certificate of Insurance) 4. General/Supp Conditions 5. Specification Index
85
Completion Bond
Surety bond obtained by O, which guarantees project will be completed free of liens
86
Performance Bond
A312 Surety bond obtained by C, guarantees to O that C will PERFORM work in accordance with contract docs. Required for bidders within Bid Bond
87
Bid Bond
A310 Furnished by Bidder to guarantee (1) they will enter into a contract with O (2) they will provide performance AND labor and material payment BOND to guarantee work will be properly carried out.
88
Labor and Material Payment Bond
A312 Surety bond obtained by C guaranteeing to O that the contractor will pay for all labor (subs, supplies) and materials. Protects O from mechanic's lien and claims arising from unpaid C bills. Usually requested by O in conjunction with Performance Bond. Required as part of Bid Bond
89
Certificate of Insurance
G715 | Outline of types and limits of insurance coverage the C must carry.
90
Subrogation (Insurance)
Procedure in which the insurance company, after paying loss, can recover $$ from party responsible. a waiver in A201 can preclude these parties from subrogation
91
Property Insurance
Purchased for O, A201 requires it. Insurance value = Project value 2 types: ALL RISK & named peril
92
Loss of Use Insurance
Purchased by O, protects against financial losses from DELAYS or events PREVENTING the owner from using the project WHEN and AS expected.
93
General Liability Insurance
Purchased by all. A201 requires O/C to purchase. Protects against claims for damages for injury, sickness, etc. Professional Liability/Errors and Omissions Insurance - liability insurance against negligence to meet standard of care expected from a professional
94
Fixed Fee
(Stipulated Sum Agreement) A lump sum for a scope of work. Contingencies are included (5-10%) to cover risk that cost > budget. Reimbursable are extra. - If const. cost > Fixed Price = C eats $, O not responsible - If const. cost
95
Cost Plus Fee
Reimbursement for actual expense to perform work. Includes salaries, benefits, overhead, plus fee for profit. Usually includes guarantee maximum price (GMP). Why? When O wants specific contractor.
96
Percentage of Construction Cost Fee
Based on % of total cost of construction
97
Guaranteed Maximum Price (GMP)
Highest cost of construction guaranteed by C. | - If const. cost GMP, $ is owed to O by C.
98
Construction Change Directive
G714 Document prepared by A, signed by O/A. Instructs C to change work, REGARDLESS of C agreement. If C agrees to change in FEE, C signs CCD, and it becomes CHANGE ORDER. If C does NOT agree on fee, A determines fee based on actual cost (time, materials, overhead), if still NOT in agreement, CCD goes to ARBITRATION.