CDS - Contracts Flashcards
A101-2007
Standard Form of Agreement BetweenOwner and Contractor where the basis ofpayment is a Stipulated Sum
A201-2007
General Conditions of the Contractfor Construction
A701-1997
Instructions to Bidders
B101-2007
Standard Form of Agreement BetweenOwner and Architect
C401-2007
Standard Form of Agreement BetweenArchitect and Consultant; ex. C141; Architect-Consultant agreement; consultant is responsible for code compliance regarding their area of work; consultant responsible for checking their own document for consistency, but architect is liable to the owner for consultant’s work
BOILERPLATE
a standard portion (generally a paragraph or more) of a written document, such as a contract or architectural specification, that appears in all similar documents
DESCRIBED IN THE BASE FEE (contracts)
major project milestone dates, scope of services, reimbursable expenses with respective unit billing rate, number of meetings with third parties included (authorities having jurisdiction, landlords, etc.)
CM AS ADVISOR
Owner-Construction Manager Agreement; B801/CMa
CM AS CONSTRUCTOR
Owner-Construction Manager Agreement; A121/CMc or A131/CMc
PRIVITY
this concept theoretically protects the architect from claims by parties with whom he or she has no direct contractual relationships
INDEMNIFICATION CLAUSE
attempts to hold harmless both the owner and architect for any damages, claims, or losses resulting from the performance of any work on the project whether by thecontractor or others with whom the architect has no contractual relationship.
B141 used on projects where
services are based on traditional five phases
- SD
- DD
- CD
- BIDDING/NEGOTIATION
- CA
B161
standard form of agreement between o-a for designated services
- for more extensive services performed by the architect
- B161 & B162 must be used together
B141
- outlines scope of basic services
2. at tend of each of the first three phases, architect to submit cost estimates for construction
owner responsible for
- program
- desired schedule
- budget
- surveys
- soil tests
- furnish the services of other consultans
additional services
services not included in basic standard services
- project representation beyond basic services
- contingent additional services - if drawings/specs are required due to change order, architect to receive add’l compensation
- optional additional services - services the owner would like but that are beyond basic services, ex. programming, tenant planning, verification of work by others
- if included in the agreement, they are written into the agreement along with the basis for compensation
hazardous materials
architect has no responsibility for the
- discovery
- handling
- removal
- disposal
- exposure of persons to hazardous materials
ex. asbestos, PCBs, toxic substances
9 categories of services (B161)
- predesign
- site analysis
- schematic design
- design development
- CDs
- bidding / negotiation
- construction contract administration
- post construction
- supplemental services
basic provisions common to all contracts
- description of work (exclusions can be spelled out here)
- times of commencement (specific date, or when contractor/architect is given notice to proceed)
- time of substantial completion (specific date or num. of calendar days from notice to proceed)
- contract sum
if a specific date is important to the owner
- provisions for liquidated damages may be included
- liquidated damages - monies paid by the contractor to the owner for every day the project is late
- can write in contract anticipated losses the owner will incur if the project is not complete in time
- usually a bonus provision for early completion based on saving the owner will incur for early occupancy
- if a penalty clause is included, a bonus provision must be included
A201 - General Conditions (owner responsibilities)
- article 2- duties, responsibilities, and rights of the owner
- furnish evidence that financial arrangements have been made to fulfill owner’s obligations and pay the contractor
- must provide free of charge necessary copies of the contract documents
- owner may order contractor to stop work if contractor fails in their duties (7 days from written notice)
A201 - General Conditions (contractor responsibilities)
- contractor solely responsible for means, methods, techniques of construction and coordination/scheduling
- contractor not liable to the owner or architect for damage resulting from errors/omissions in the contract documents
- contractor not responsible to ascertain that contract documents are in accordance with building codes, ordinances, other regulations
- if contractor notices variance, must notify architect and owner in writing; if not, contractor assumes responsibility
- contractor to provide a schedule for review by O/A
- contractor to indemnify and hold harmless O/A and architect’s consultants and agents against claims/damages/expense arising out of performance of the work
indemnify
to secure against loss or damage
architect’s documents
- contract documents are instruments of a service and belong to the architect (copyright)