Ch 7- Project Management Flashcards

(31 cards)

1
Q

project

A

an interrelated set of activities with a definite starting and ending point which results in a unique outcome for a specific allocation of resources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

3 main goals of any project

A
  1. Complete the project on time
  2. Don’t exceed the budget
  3. Meet the specifications to the satisfaction of the customer
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

project management

A

systemized, phased approach to defining, organizing, planning, monitoring, and controlling projects

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

program

A

interdependent set of projects that have a common strategic purpose

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

scope creep

A

Changes to scope that inevitably increase costs and delay completion. too many are primary causes of failed projects

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

2 steps of constructing a project network

A
  1. defining the work breakdown structure

2. diagramming the network

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

work breakdown structure

A

statement of all work that has to be completed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

activity

A

the smallest unit of work effort consuming both time and resources that the project manager can schedule and control

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

network diagram

A

a network planning method - designed to depict the relationships between activities - that consists of nodes (circles) and arcs (arrows)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Program evaluation and review technique (PERT)

A

network planning method created for the US Navy’s Polaris missile project in the 1950s, which involved 3,000 separate contractors and suppliers

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Critical path method (CPM)

A

network planning method developed in 1950s as means of scheduling maintenance shutdowns at chemical-processing plants

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

precedence relationship

A

relationship that determines a sequence for undertaking activities; it specifies that one activity cannot start until a preceding activity has been completed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

path

A

sequence of activities between a project’s start and finish

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

critical path

A

the sequence between a project’s start and finish that takes the longest to complete
- determines the completion time of the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

activity slack

A

max length of time an activity can be delayed without delaying the whole project
- activities on the critical path have no slack

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Gantt Chart

A

a project schedule - usually created by the project manager using computer software - that superimposes project activities with their precedence relationships and estimated duration times on a time line.

    • don’t use with complex projects
    • doesn’t clearly show inter-relationships among tasks (like PERT)
17
Q

Total project costs

A

Sum of direct costs, indirect costs, and penalty costs

18
Q

Normal time (NT)

A

Time necessary to complete an activity under normal conditions

19
Q

Normal cost (NC)

A

the activity cost associated with the normal time

20
Q

crash time (CT)

A

the shortest possible time to complete an activity

21
Q

crash cost (CC)

A

the activity cost associated with the crash time

22
Q

minimum-cost schedule

A

a schedule determined by starting with the normal time schedule and crashing activities along the critical path in such a way that the costs of crashing do not exceed the savings in indirect and penalty costs

23
Q

risk-management plan

A

a plan that identifies the key risks to a project’s success and prescribes ways to circumvent them

24
Q

Parkinson’s Law

A

If you give “x” amount of time, all o that time will be used

The solution: give less time to finish, leaving a cushion (basically don’t tell the employees the full time they have)

25
failure
failing to meet all goals
26
success
meeting all goals
27
Formula for time estimate of a task
``` (a+4m+b)/6 where a= optimistic forecast m= realistic forecast b= pessimistic forecast ```
28
optimistic time
``` represented as (a) = shortest time in which an activity can be completed, if all goes exceptionally well ```
29
most likely time
``` represented as (m) = the probable time required to perform an activity ```
30
pessimistic time
``` represented as (b) = the longest estimated time required to perform an activity ```
31
4 categories for assessing project risk
1. Strategic fit - how well does it fit with goals of the firm? 2. Service/product attributes - market, tech, or legal risks 3. Project team capability - does team have capability to complete the project successfully? 4. Operations - risks from poor info accuracy, communication errors, missing precedence relationships, or bad time estimates