Chapter 1 Making Buildings Flashcards

(25 cards)

1
Q

design/bid/build project

A

the owner first hires a team of architects and engineers to perform design services, leading to the creation of construction documents that comprehensively describe the facility to be built. next, construction firms are invited to bid on the project. each bidding firm reviews the construction firms are invited to bid on the project. each bidding firm reviews the construction documents and proposes a cost to construct the facility. the owner evaluates the submitted proposals and awards the construction contract to the bidder deemed most suitable. this selection may be based on bid price alone or other factors related to bidders’ qualifications may also be considered. construction documents then become part of the construction contract and the selected firm proceeds with the work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

general contractor

A

coordinates and oversees the construction process but frequently relying on smaller, more specialized subcontractors to perform significant portions or even all of the work itself

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

design/build

A

delivery, the owner contracts with two entities, and design and construction responsibility for both design and construction. this project begins with the owner developing a conceptual design or program that describes the functional or performance requirements of the proposed facility but does not detail its form or how it is to be constructed. next using this conceptual information, a design/build organization is selected to complete the design and construction of the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

construction manager

A

participates in the project prior to the onset of construction, introducing construction expertise during the design stage

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

turnkey construction

A

owner contracts with a single entity that provides not only design and construction services but financing for the project as well

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

single purpose entity

A

owner, architect, contractor are all joint members

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

fixed-fee/lump-sum compensation

A

general contractor or other construction entity is paid a fixed dollar amount to complete the construction of a project regardless of that entity’s actual costs to perform the work… the owner begins construction with a known, fixed cost and assumes minimal risk for unanticipated cost increases… construction contractor assumes most of the risk of unforeseen costs but also stands to gain from potential savings… fixed-fee is most suitable to projects where the scope of the construction work is well defined when the construction fee is set, as is the case, for example, with design/bid/build construction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

guaranteed maximum price

A

max fee that the owner may be required to pay … once compensation reaches guaranteed max, the owner is no longer required to make additional payments and the contractor assumes responsibility for all additional costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

incentive provisions

A

can be used to more closely align owner and contractor interests.. Ex: in simple cost plus a fee construction, there may be an incentive for a contractor to add costs to a project, as these added costs will generate added fees. to eliminate such a counter-productive incentive, a bonus fee or profit-sharing provision can provide for some portion of construction cost savings to be returned to the contractor - contractor and owner jointly share in the benefits of reduced construction cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

surety bonds

A

another form of legal instruments used to manage financial risks of construction, most frequently with publicly financed or very large projects. the purpose of a surety bond is to protect an owner from the risks of default, such as bankruptcy, by the construction contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

performance bond

A

to assure completion of the construction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

payment bond

A

to assure full payment to suppliers and subcontractors

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

sequential construction

A

each major phase in the design and construction of a building is completed before the next phase begins and construction does not start until all design work has been completed .. often associated with design/bid/build

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

phased construction (fast track)

A

aims to reduce the time required to complete a project by overlapping the design and construction of various project parts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Gantt (or bar) chart

A

series of horizontal bars represents the duration of various tasks or groups of tasks that make up the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

critical path

A

sequence of activities that determines the least amount of time in which a project can be completed

17
Q

float

A

more flexibility in scheduling

18
Q

critical path method

A

technique for analyzing collections of activities and optimizing the project schedule to minimize the duration and cost of a project - requires detailed breakdown of the work involved in a project and the identification of dependencies among the parts

19
Q

five schedule classes

A

degree of project definition in schedule is described by - class 1 - provides highest degree of project definition such as that needed for project bidding and costing, class 3 - relies on a medium degree - project budgeting, class 5 - least project definition - early conceptual work

20
Q

schedule levels

A

define amount of detail provided within the construction schedule

21
Q

rolling (look-ahead) schedules

A

day to day processes extending a limited number of weeks or months into the future are described, are examples of level 4 schedules

22
Q

integrated project delivery

A

major parties - including at least the design team, construction team and owner group - share mutually the responsibilities, decision making and financial risks and rewards of the project

23
Q

lean construction

A

such methods attempt to reduce complexity, eliminate wasteful activities, structure the supply of materials and methods of production to achieve the quickest and most reliable workflow, decentralize info and decision making to put control of processes into the hands of those most familiar with the work and most capable of improving it

24
Q

building info modeling

A

three dimensional and intelligent, components represented geometrically, spatially and are linked to data describing their intrinsic properties and relationships to other components - object based and parametric

25
BIM execution plan
defines the role of the building model and its level of development at various project stages, identifies sources of data that will contribute to the model, assigns responsibilities for authoring and managing the model, establishes protocols for info exchange among parties and defines the technical and project infrastructure required to support these activities