Chapter 1 TPM Fundamentals Flashcards
(50 cards)
What does an RTPM PM demonstrates?
demonstrates proficiency in a vast collection of telecommunications project management principles, concepts, tools and technology.
What is SDO?
Standard Development Organization
What are some types of infrastructure types in an ICT project?
Premise distribution, OSP, Wireless technology,
TPM typically consist of monitoring and controlling the implementation and execution of two primary and distinct processes:
ICT project design activities
ICT project construction/installation commissioning activities.
ICT projects may involve?
Single or multi-building premise types
One or more occupancy/facility types
Multiple ICT applications to be implemented
Installation of active equipment
Depending on the size and complexity of an ICT project, a telecommunications PM may fill one or more of the following roles:
Design PM
Client PM
Define Design PM
Responsible for determining client’s needs and desires including existing conditions.
Define Client PM
Act as the client’s representative in overseeing project design and installation activities.
What is a project?
A temporary endeavor with a definite beginning and end, whose result is to produce a product or service.
What’s premise distribution
(horizontal backbone), cabling and associated pathways, spaces, and connectivity hardware.
What’s OSP?
(aeria, direct-burial and underground), cabling and assocaited pathways, spaces, and connectivity hardware.
What’s wireless technlogies?
(DAS, Wi-Fi Systems), and associated pathways, spaces, and connectivity hardware.
Multiple ICT applications to be implemented include:
enterprise voice/data systems
A/V systems
ESS systems
BMS systems
Installation of active equipment include:
switches, routers, media converters, amplifiers, displays, CCTV cameras, power equipment (UPS, PDU), applicable to the ICT infrastructure, networks and applications.
The construction/installation PM is responsible for:
the execution and completion of the agreed SoW within a project.
TPM Design Flowchart
- Review expression of interest for client
- Perform a user needs analysis
- Perform site surveys and meet with client
- Generate preliminary desing submittals
- Respond to/incorporate client comments
- Prepare final bid documents RFP and engineers cost estimate.
- Issue final RFP package to client.
- Client makes RFP available to potential bidders.
- Review bid submissions from bidders and answer bidders technical questions.
- Assist client in evaluating bids for technical compliance and/or determination of low bid/best value.
Construction Installation PM Flowchart
- Review client RFP and associated documents
- Perform site surveys
- Organize and submit bidder’s questions to client.
- Organize and submit final proposal/bid documents to client.
- Client award contract and gives contractor notice to proceed.
- Contractor mobilizes.
- Project installation begins/monitor installation.
Projects are governed by limits called?
constraints
Project constraints may include:
Project assumptions.
Overall SoW to be performed.
Cost.
Time.
Reputation.
Project site environment.
Project location (e.g., rural, urban)
True or False do not assume the basic building structure is complete and can support ICT installation
True
True or False for retrofits and upgrades, assume all existing premise ICT infrastructure is fully documented and accounted for.
False
True or False you must document the removal or demolition of existing ICT infrastructure no longer required after the retrofit or upgrade is complete.
True
True or False
Do not assume the absence of environmental hazards at the work site
(e.g., asbestos-containing materials, chemically contaminated areas)
True
True or False
The SoW for a project can range from limited to full.
True
The telecommunications PM should understand the overall SoW for the project and the requirements and constraints associated with it.