Chapter 4 Discharge of Contract, Remedies, Limitation of Actions Flashcards
Discharge of Contract
In what ways can a contract be discharged?
Discharge by performance
Discharge by agreement
Discharge by frustration
Discharge in consequence of repudiatory breach
Discharge of Contract
Discharge by performance
When both parties have performed their contractual obligations. This means contract has come to an end and neither parties have obligations.
Discharge of Contract
Part Performance
Case: Re Moore and Co v Landauer and Co (1921)
Case: Cutter v Powell (1795)
Generally there is a requirement that parties fully perform what they are contracted to do. Part performance will not usually be enough.
Case: Re Moore and Co v Landauer and Co (1921)
Buyer bought a consignment of fruit to be packed in cases of 30 tins. They delivered correct amount, but it was packed in cases of 24 tins.
Held: buyer was allowed to reject the entire consignment.
Case: Cutter v Powell (1795)
Sailor agreed to sail ship from Jamaica to Liverpool. He was to be paid 30 Guineas on arrival, but he died at sea.
Held: widow was not entitled to payment for work done. He was obliged to have completed the whole voyage.
(Nowadays his widow would be entitled to a proportion of that payment)
Discharge by Performance
Minute Deviations
Case: Reardon Smith v Hansen - Tangen (1976)
Case: Peter Darlington and Partners v Gosho Ltd (1964)
Where there only has been a minor deviation.
Case: Reardon Smith v Hansen - Tangen (1976)
Contract related to the building of a ship and mentioned that it had to be built in ‘yard 354’. All specifications were met, but it was built elsewhere. Defendants rejected delivery.
Held: defendants couldn’t reject ship, as ‘yard 354’ was not a term in the contract.
Case: Peter Darlington and Partners v Gosho Ltd (1964)
Seller was to supply a quantity of canary seed on a ‘pure basis’. 98% was pure and considered to be the highest standard in the marker.
Held: seller completed their obligation.
SOGA 1979 also states that if the implied term results in damage that is so slight it is unreasonable for buyer to reject goods. It will be seen only as a breach of a warranty, so court will only allow damages.
What if the failure to fully perform the contract is not the fault of the defaulting party?
This is not enough to discharge the contract, unless it has become physically or legally impossible to complete the contract, making it become radically different.
What if the failure to fully perform the contract is not the fault of the defaulting party?
Exceptions
Divisible Contracts
Prevention to complete performance by another party
Agreement to accept partial performance
Doctrine of substantial performance
What if the failure to fully perform the contract is not the fault of the defaulting party?
Exceptions
Divisible Contracts
Payment in stages, where each stage will be seen as a separate contract, which will raise an obligation to pay. Example, someone who is paid weekly. They can refuse to work the following weeks, even if they have been paid for the first week.
What if the failure to fully perform the contract is not the fault of the defaulting party?
Exceptions
Prevention of complete performance by another party
Quantum Meruit
If one party prevents the other from performing, the other party will be entitled to claim for work done: Quantum Meruit.
Case: Planche v Colburn (1831)
Publisher commissioned a writer to write a book for £100. He wrote part of it, but then publisher cancelled the contract.
Held: The writer recovered £50 for the work done on a Quantum Meruit basis.
What if the failure to fully perform the contract is not the fault of the defaulting party?
Exceptions
Agreement to accept partial peformance
If a purchaser agrees to accept a lesser amount, he is obliged to pay them.
What if the failure to fully perform the contract is not the fault of the defaulting party?
Exceptions
Doctrine of substantial performance
Case: Hoening v Isaacs (1952)
Case: Bolton v Mahadeva (1972)
If substantial work was performed, party will be entitled to payment of the work that was done, minus the minor outstanding part.
Case: Hoening v Isaacs (1952)
Claimant agreed to decorate defendants flat, fir a bookcase and a wardrobe for £750. On completion defendant paid £400, but complained about faulty work and refused to pay the rest.
Held: work was substantially completed, so claimant was entitled to the remaining £350, less the cost of the remedy for the defects, which was about £50.
Case: Bolton v Mahadeva (1972)
Contractor agreed to install central heating for £560, but it didn’t heat house adequately and emitted fumes. It would cost £174 to remedy the defects. He claimed the price, minus the £174.
Held: Court of Appeal rejected substantial performance had been done, as the price to remedy it was proportionally much larger than above.
Time in relation to performance
Case: Charles Rickards v Oppenheim (1950)
Failure to complete the contract on time allows the party to terminate the contract, unless it can be shown that time is of fundamental importance.
Time is of essence:
- if expressly stated in the contract that time is of essence;
- if the subject matter or circumstances of the contract mean that time is presumed to be of essence, and parties haven’t stated otherwise.
It is generally presumed that in commercial contracts time is of essence.
In contracts relating to the sale of land, time is not considered to be of essence.
Case: Charles Rickards v Oppenheim (1950)
Contract to build Rolls Royce chassis within 7 months. Period expired, and purchaser agreed to wait another 3 months. They remained undelivered then, and purchaser told them they expected delivery within 4 weeks. They delivered 3 months later.
Held: purchaser was not obliged to accept delivery.
Application (or appropriation) of debts
Under statute, if a debt is not paid within 6 years, creditor no longer has the right to claim the debt.
Discharge by agreement
3 ways it can occur
Three ways this may occur:
- specific provision in contract
- bilateral discharge
- unilateral discharge
Discharge by agreement
Specific provision in contract
Parties can mutually agree that a contract terminates at the expiration of a fixed time.
Contracts for the hire of goods, leasing of premises, or fixed terms employment contracts.
Discharge by agreement
Bilateral discharge
If neither part has performed obligations under the contract, discharge by agreement creates no difficulties. Each side cancels the other side’s obligations.
If there was consideration for any part performed it needs to be paid.
Discharge by agreement
Unilateral discharge
By novation
Case: Re Charge Card Services (1986)
If only one party performed their obligations, the other party may agree to substitute original contract with a new one.
New contract is called novation.
Discharge will only be binding if the party being released provides some additional consideration in return for the release.
Case: Re Charge Card Services (1986)
Garage agreed to accept payment for petrol by charge card. This discharged the customer’s obligation to pay by cash, when charge card firm became insolvent, the customer didn’t have to pay again.
Discharge by agreement
Unilateral discharge
By deed
If a deed is used to unilaterally discharge a contract, no consideration is required.
Condition subsequent
Case: Bland v Sparkes (1999)
Parties agree that if a specific event occurs, the contract will come to an end.
An example, a manufacturer offering a refund, if a goods have a fault within a specific given time.
Case: Bland v Sparkes (1999)
Bland has been a swimmer and was hired by the Amateur Swimming Association to promote its award scheme. ASA could terminate the contract of Bland was convicted of any serious offence.
They later discovered that Bland had accepted bribes and secret commissions.
Held: Court of Appeal held that Bland’s conduct entitled ASA to terminate the contract.
Discharge by frustration
Case: Paradine v Jane (1647)
Case: Taylor v Caldwell (1863)
Until the development of the frustration doctrine, the contract needed to be fulfilled even if it became impossible.
Case: Paradine v Jane (1647)
Lessee was evicted during civil war.
Held: was still liable to pay rent, even after being evicted.
This was too harsh, so the doctrine of frustration emerged with case Taylor v Caldwell (1863)
Case: Taylor v Caldwell (1863)
Music Hall hired a series of concerts, but burned down before the first performance.
This frustrated the contract and hirer had no obligation to pay charges.
Circumstances in which a contract can be frustrated
Subsequent impossibility
Subsequent illegality
Non-occurrence of future event
Intervening enforced delay subsequently changes the commercial nature of the contract
Contracts of a personal nature
Performance rendered radically different
Self-induced frustration
Discharge by frustration
Subsequent impossibility
Case: Taylor v Caldwell (1863)
The subject matter of the contract was destroyed.
Case: Taylor v Caldwell (1863)
Music Hall hired a series of concerts, but burned down before the first performance.
This frustrated the contract and hirer had no obligation to pay charges.
Discharge by frustration
Non-occurrence of future event
Case: Krell v Henry (1903)
If it depends on a future event that doesn’t occur.
Case: Krell v Henry (1903)
Contract for a room hire overlooking the coronation route of Edward VII. The King became ill and the coronation was postponed.
Contract was held as frustrated.
Discharge by frustration
Intervening enforced delay subsequently changes the commercial nature of the contract
Case: Metropolitan Water Board v Dick Kerr and Co (1918)
There have been a number of cases where the powers by the government in time of war or emergency have lead to frustrated contracts.
Case: Metropolitan Water Board v Dick Kerr and Co (1918)
Contractors agreed to build a reservoir in 1914. In 1916, under emergency, wartime powers, the government ordered them to stop work and sell the plant.
It could have been restarted after the war, but it was held to be sufficiently serious to frustrate the contract.
Discharge by frustration
Contracts of a personal nature
If contract for personal services by an individual is imprisoned, dies or becomes so ill they cannot perform, the contract will be frustrated.