Chapter 4 Time Management Flashcards

(32 cards)

0
Q

Input to plan schedule management process?

A

OPA
eEF
PMP
Project Charter

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
1
Q

Processes of time management?

A
  1. Plan schedule management
  2. Define activities: activities list
  3. Sequence activities: id & document in project schedule network diagram relationship among activities
  4. Estimate activity resources
  5. Estimate activity duration
  6. Develop schedule
  7. Control schedule
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Tools of plan schedule management?

A

Analytical techniques
Expert judgement
Meetings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Output of plan schedule management process?

A

Schedule management plan:

-How to management plan
-Define criteria and process to develop, monitor & control e.g:
Level of accuracy
Performance measurement rules. EV, spi, sv
Reporting formats

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Inputs to define activities process?

A

Schedule management plan
Scope baseline: project scope statement, wbs & wbs dictionary
OPA
EEF

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Tools of define activities process?

A

Expert judgement

Rolling wave planning - iterative planning based on progressive elaboration / plan as you go

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Outputs of define activities process?

A
  1. Activities list - lower lvl than wbs
  2. Activities attributes - description, relationship between activities and resourcing required
  3. Milestone list - important checkpoints of the project
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Inputs to sequence activities process?

A
Activity list
Activity attributes
Milestone list
Schedule management plan
OPA
EEF
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Tools of sequence activities process?

A
  1. Precedence diagramming method (PDM) or network diagram
  2. Dependency determination
  3. Leads and lags
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Outputs of sequence activities process?

A

Project schedule network diagram

Project document updates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Dependency determination - four major dependencies?

A
  1. Mandatory - often legally required.
  2. Discretionary - preferred logic.
  3. External - beyond the team’s control.
  4. Internal - within the team’s control.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Lead and lags?

A

Lead = start an activity before it’s predecessor is finished
E.g.
FS-5 days

Lags = delay before successor can start

E.g.
FS+3 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Inputs to estimate activity resources process?

A
  1. Schedule management plan
  2. Activity list
  3. Activity attributes
  4. Resource calendars
  5. Risk register
  6. Activity cost estimate
  7. EEF
  8. OPA
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Tools of estimate activity resources process?

A
  1. Expert judgement
  2. Alternatives analysis
  3. Bottom up estimating
  4. Published estimating data
  5. PM software
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Outputs of estimate activity resources process?

A
  1. Activity resource requirements
  2. Resource breakdown structure - hierarchical structure of resources, organised by resource category and resource type
  3. Project document updates
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Inputs to estimate activity duration process?

A
Schedule management plan
Activity list
Activity attributes
Activity resource requirements
Resource calendar
Project scope statement
Risk register
Resource breakdown structure
OPA
EEF
16
Q

Tools of estimate activity duration?

A
Expert judgement
Analogue estimating
Parametric estimating
Three point estimating
Group decision making
Reserve analysis
17
Q

Outputs to estimate activity duration process?

A

Activity duration estimates

Project document updates

18
Q

Analogous (top down estimate)?

A

Estimating based on previous project activities

Least accurate

Least time consuming

19
Q

Parametric estimating?

A

Simple maths relationship estimating

20
Q

Three point estimating?

A

By default = beta distribution

(O+4ML+P)/6

Triangular distribution

(O+ML+P)/3

Standard deviation of beta distr.

(P - O)/6

21
Q

Reserve analysis?

A

Contingency reserve - known unknown

Management reserve - unknown unknown

22
Q

Inputs to develop schedule process?

A
Schedule management plan
Activity list 
Activity attributes
Milestone list
RBS
Project scope statement
Risk register
Resource calendar
Activity resource requirements
Project schedule network diagrams
Project staff assignment
23
Q

Tools to develop schedule process?

A
Schedule network analysis
Critical path method
Critical chain method
Resource optimisation technique
Modelling technique
Leads and lags 
scheduling tool
24
CPM definition?
Longest sequence activities in the project Minimum duration of the project Delay in cp activities will delay project completion
25
CCM definition?
Used to account for limited resources and project uncertainties. CCM focuses on resource allocation, optimization and levelling and activity duration uncertainty on critical path, CCM add duration buffers to any schedule path.
26
Outputs to develop schedule process?
``` Schedule baseline Project schedule Project calendar PMP updates Schedule data ```
27
Inputs to control schedule process?
``` PMP Project schedule Work performance data Project calendars Schedule data OPA ```
28
Tools to control schedule process?
``` Performance reviews Project management software Resource optimization technique Modelling technique Leads and lags Schedule compression Scheduling tool ```
29
Outputs to control schedule process?
``` Work performance info Schedule forecast Change request PMP updates OPA updates Project document updates ```
30
CPM free float facts?
Free float = ES(s) - FS(p) - 1 All float is total float = time an activity maybe delayed or extended without affecting total project duration. Some total float is free float = time an activity maybe delayed without affecting the start of any successor activity.
31
Fast tracking vs crashing?
Fast tracking speed up schedule by completing activities in parallel Crashing speed up schedule by adding resources