Chapter 6: Project Schedule Management Flashcards
The Project Schedule Management processes are:
Plan Schedule Management, Define Activities, Sequence Activities, Estimate Activity Durations, Develop Schedule, Control Schedule
True or false: for smaller projects, the individual processes involved in Project Schedule Management can be combined and viewed as a single process
True. For smaller projects, defining activities, sequencing activities, estimating activity durations, and developing the schedule model are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time
True or false: When possible, the detailed project schedule should remain flexible throughout the project
True. When possible, the detailed project schedule should remain flexible throughout the project to adjust for knowledge gained, increased understanding of the risk, and value-added activities
An activity list, a bar chart, and a network diagram are all possible ________ presentations
Project Schedule
Define “Iterative scheduling with a backlog”
This is a form of rolling wave planning based on adaptive life cycles, such as the agile approach for product development. The requirements are documented in user stories that are then prioritized and refined just prior to construction, and the product features are developed using time-boxed periods of work
Define “On-demand scheduling”
This approach, typically used in a Kanban system, is based on the theory-of- constraints and pull-based scheduling concepts from lean manufacturing to limit a team’s work in progress in order to balance demand against the team’s delivery throughput
The project manager may need to tailor the way Project Schedule Management processes are applied. Considerations for tailoring include but are not limited to:
Life cycle approach, Resource availability, Project dimensions, Technology support
The enterprise environmental factors that can influence the Plan Schedule Management process include but are not limited to:
Organizational culture and structure, Team resource availability and skills and physical resource availability, Scheduling software, Commercial databases, such as standardized estimating data
The schedule management plan can establish the following:
Project schedule model development, Release and iteration length, Level of accuracy, Units of measure, Organizational procedures links, Project schedule model maintenance, Control thresholds, Rules of performance measurement, Reporting formats
Define “Release and iteration length”
When using an adaptive life cycle, the time-boxed periods for releases, waves, and iterations are specified. Time-boxed periods are durations during which the team works steadily toward completion of a goal. Time-boxing helps to minimize scope creep as it forces the teams to process essential features first, then other features when time permits
Define “Earned value management (EVM) rules”
EVM is a technique for measuring project performance and progress in an objective manner. It has the ability to combine measurements of the project management triangle: scope, time, and costs
Define Activities is the process of identifying and documenting the specific actions to be performed to produce the _______
Project Deliverables
Are schedule baseline and cost baseline input or output documents regarding the Define Activities Process?
Output
True or False: The Define Activities process defines the final outputs as activities rather than deliverables
True
Define “Rolling wave planning”
Rolling wave planning is an iterative planning technique in which the work to be accomplished in the near term is planned in detail, while work further in the future is planned at a higher level. It is a form of progressive elaboration applicable to work packages, planning packages, and release planning when using an agile or waterfall approach.
Define “Activity attributes”
Activity attributes extend the description of the activity by identifying multiple components associated with each activity. The components for each activity evolve over time. During the initial stages of the project, they include the unique activity identifier (ID), WBS ID, and activity label or name
What can Activity attributes be used to identify?
Activity attributes can be used to identify the place where the work has to be performed, the project calendar the activity is assigned to, and the type of effort involved
True or false: all milestones outlined on the milestone list are mandatory to hit
False. A milestone list identifies all project milestones and indicates whether the milestone is mandatory, such as those required by contract, or optional, such as those based on historical information
Define the process: “Sequence Activities”
Sequence Activities is the process of identifying and documenting relationships among the project activities. The key benefit of this process is that it defines the logical sequence of work to obtain the greatest efficiency given all project constraints
True or false: The Sequence Activities process is performed throughout the project
True
True or false: The Sequence Activities process concentrates on creating a list to act as a first step to publish the schedule baseline
False. The Sequence Activities process concentrates on converting the project activities from a list to a diagram to act as a first step to publish the schedule baseline
Define “The precedence diagramming method (PDM)”
The precedence diagramming method (PDM) is a technique used for constructing a schedule model in which activities are represented by nodes and are graphically linked by one or more logical relationships to show the sequence in which the activities are to be performed
PDM includes ___ (#) types of dependencies or logical relationships. What are they?
Four. They are: Finish-to-start (FS), Finish-to-finish (FF), Start-to-start (SS), Start-to-finish (SF)
Define “Finish-to-start (FS)”
A logical relationship in which a successor activity cannot start until a predecessor activity has finished. For example, installing the operating system on a PC (successor) cannot start until the PC hardware is assembled (predecessor)