chp 9 Flashcards

(11 cards)

1
Q

describe precast concrete construction

A
  • cast in manufacturing yard and fixed in position in site
  • normally cast in steel moulds
  • more stringent dimensional precision is required
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

describe cast-in-situ

A
  • casting and fixing at the exact same position on the construction site
  • usually cast in timber moulds
  • less critical in dimensional precision
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

criteria that need particular consideration

A
  • handling stress
  • anchorage at support
  • joints in movement
  • overall stability
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

type of connections

A
  • tension joint
  • compression joint
  • shear joint
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

type of joints in movement

A
  • contraction joint
  • expansion joint
  • sliding joint
  • settlement joint
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

advantages of precast

A
  • faster construction speed
  • better quality control
  • dimensional deviation is small
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

limitations of precast

A
  • tolerances must be allowed for
  • distance between precast yard and site will affect costing of project
  • accessibility, storage area and the capacity if crane will affect erection process on site
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

stages of fabrication process

A
  • manufacturing stage
  • erection stage
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

procedure of manufacturing stage

A
  • mould fabrication
  • casting and curing of concrete
  • storage of precast components
  • delivery of components
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

equipment used in manufacturing precast components

A
  • cranes
  • racks
  • tucks and trailers
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

process in erection stages

A
  • temporary storage on site
  • putting up the components
  • temporary support
  • fixing of joints
How well did you know this?
1
Not at all
2
3
4
5
Perfectly