CM Notes Flashcards
(135 cards)
What are the Seven aspects of a Vertical Cost Breakdown?
IBID-CM-E
- Indirect Costs
- Bonds
- Interest
- Direct Costs
- Contingency
- Markup
- Escalation
List 2 methods of pricing out direct cost estimates
- Crew Method
- Individual Method
Define Swing Shift
the work shift between the day and the night shifts, commonly from 4:00 PM to midnight
3 Types of Estimate for an Owner
- Conceptual Estimate
- Alternative Design Estimate
- Owner’s Engineer Estimate
3 Types of estimate for a contractor
- Contractor’s bid estimate
- alternative methods
- claims / change orders
Two different breakdowns of cost:
Horizontal and Vertical
Horizontal: 7 Categories
PEE-RSLL
- Permanent Materials
- Expendable Materials
- Equipment Operations
- Rentals
- Sub Contractors
- Labour
- Labour Service
Vertical: 7 Categories
IBIDCM-E
- Indirect Costs
- Bonds
- Interest
- Direct Costs
- Contingency
- Markup
- Escalation
List 3 types of mark-up
Home office, Profit, and Risk
List The 4 Types of EOE
Equipment Operating Expense
- FOG: Fuel Oil Grease
- Small Repair Parts
- Tires
- 3rd Party Overhaul
List the 5 Types of Indirect Costs
- Salaries / Payroll
- Time-related O/H expense
- Non-time related expense
- Insurance + taxes
- Construction Plant in + out
Contingency
Safety net accounting for risks
2 Types of Contingency
Identified & Unidentified
3 Categories of Unidentified Contingency
- Soft Subs
- Construction Hedge
- Special Events (i.e. strike)
What is an unidentified contingency?
A little bit of padding thrown into your estimate for small, unanticipated events.
List the 2 categories of risk.
Quantifiable & Unquantifiable risk
2 Types of Network Diagrams
AoA - Activity on Arrow
AoN - Activity on Node
What is a schedule?
A schedule is a logical representation of logical relationships / sequences of tasks or activities.
IPA
Immediately Preceding Activity
Dummy Relationship
Logical relationship with no time associated
(CP) Critical Path
The longest path through the network.
Activities with zero float are considered critical path tasks.
Critical Activity
Any activity on the critical path
- CA’s have zero float
- if a CA is delayed, the entire duration is delayed by the same time
Float
The difference between the available time to complete an activity and the required time.
a. non-critical activities have float
b. critical activities have no float
4 Types of Logical Relationships
Start-Start
Start-Finish
Finish-Finish
Finish-Start
The default is Finish-Start relationship