Common Flashcards
(71 cards)
What is spearing? Who has the operating authority to spear?
A spear is a (usually hydraulic) tool used to verify the energized state of a distribution cable by short-circuiting and grounding the conductors. The tool can consist of a fully retractable blade that pierces the cable through to the conductor to provide a short-circuit path to ground. Operating spear pump has to be outside of structure. Only the shift manager can approve the spearing of cable.
What is ABF?
Alive on Backfeed - Energized cable that occurs because there is an unintentional source connected to it. Such as when a NWP failed to open on reverse power flow.
What are the standard forms of TC?
IATC: Ungrounded DC source sent out typically on A & B phase with C phase return to identify cable CATC: Ungrounded DC source sent out over 2 of the 3 phases if one is burnt clear IATC (all 3 phases) CATC (all 3 phases) CATC (+A, -B, C clear) CATC (+B, -C, A clear) CATC (+A, -C, B clear) LVFLTC (A connected to ABC, Ground C?)
What can you do if a TC ground cannot be placed?
Either perform a block & lift or cut secondary to eliminate any source of backfeed.
What is a continuity test? When it is needed?
A test with TC to determine whether there is a continuous electric circuit over conductors between specific points.
Needed when:
- two or more feeders in the same enclosure have been cut while both feeders are of the system for work at the same time.
- When cable terminations at any working points that could be mistaken for the intended ones to be spliced
- when a TX supplying a new isolated network installation is initially connected to a feeder.
- When a new radial HT service or TX is either initially connected to a feeder or transferred from one to another.
- When a new feeder or feeder leg is established
- Prior to perfomring hi-pot from cable ends in the field
- to establish or re-establish a known point
What is the voltage in BQ / SI?
Primary BQ - 27kV, 4KV - 20 networks
Primary SI - 33kV, 13kV, 4KV
Secondary - 120/208, 277/480
What contingency does BQ design to? SI?
BQ - 2nd
SI - 1st
What is second contingency design?
A design with redundancy and logic that allows for up to 2 sources to be out at the same time for a network without losing any customers.
What are the 1st and 2nd Contingency Design Voltages?
Normal: 118-126, 205-218
First: 114-126, 198-218
Second: 108-126, 187-218
How is the system designed?
Design to second contingency
Use spec EO-2073 network feeder contingency design
Ensure proper bus diversity, feeder diversity, no cross banding, no 3 feeder conflicts
Who are our customers?
Our stakeholders, the external customers Rate payers field crews, OH, UG, FOD, I&A, #9 PSC Engineering The public City agencies De - provide ratings, system updates for distribution manual Cust Eng / energy services
What is O&M and Capital?
O&M dollars are used for maintenance and operation of the system. O&M is the cost that affects our profits. Capital dollars are invested into the grid thru reliability and modernization projects, which enable the company to earn an ROE.
What are the rules we live by?
Verify Dead- ensuring equipment is dead before performing dead work
Permits - enter D fault structures only with permit authorized by operator
Atmospheric testing - test before and during work in a confined or enclosed space
Rescue/retrieval - entrant and attendant must wear rescue harnesses
HH PPE - using fall protection, eye protection, FR clothing, rubber gloves, sleeves
What are the steps to processing an OA?
- Fdr Bk opens, DO issues isolation moves,
- verify dead (DBF),
- rack out bkr & apply station grounds
- Station operator establishes condition and applies HV TC to locate fault,
- fault located and info sent to DO
- Reground at station, FOD places target ground,
- Remove station ground and apply tracing current to identify?
- Once verified - FCR submits paperwork to DO,
- remove tc, place station grounds, apply protective grounds
- Feeder goes out to work,
- once completed remove grounds, restoration moves
What is OOE2 and OOE1?
OOE2 - The equipment is in danger of failure or required out of service to ensure environmental compliance but does not pose an immediate hazard to people or other equipment. Work is prioritized BY DO based on load condition, conflicting feeders, or seriousness of condition.
OOE1 - The equipment is in imminent danger of failure and poses direct hazard to people or equipment. Equipment must be removed from service immediate meaning the DO would open the breaker immediately.
What are restoration moves?
- Proof testing - Ammeter clear and hipot
- Prepare for service - rack out G&T, rack in BKR
- Close fdr bkr
- Restore isolated equipment
What is proof testing?
Testing done to ensure all grounding devices have been removed and the feeder insulation is intact.
Ammeter clear - Tests for the removal or primary and secondary grounds.
Hipot - Tests the integrity of the feeder insulation.
Megger on bus
Ammeter clear levels:
Operating kV: Max reading (A)
4 kV 0.5 A
27 kV 0.4 A
Hipot levels:
Op kV Test kV Test duration (min.) Max current (mA) Mod. kV Mod. Dur. Mod. current 4kV 10kV 5min 5mA 5kV 5min 3mA 13kV 30kV 15min 15mA 15kV 5min 8mA 27kV 50kV 15min 15mA 25kV 5min 8mA 33kV 60kV 15min 5mA 30kV 5min 3mA
List 5 D faults
Swollen joint Exposed copper Corroded or missing bond Exposed bell on joint Stressed 3Ms Leaking joint
Name 3 C faults
Collapsed primary lead sleeve splice
Missing arc proofing on 3M splices
No insulator on oil reservoir tubing
What is ICS?
Incident command structure is the approach to command, control and coordination of emergency response, it can be activated by certain weather events or abnormal system conditions. Could be routine, upgraded, serious, or full scale.
What is the ICS personnel structure?
IC, ops chief, planning chief, logistics chief, admin finance chief. CC falls into the planning section, representing as the Control Center Unit Leader with CC Mgmt. FOD, #9 / troubleshooters, and feeder control boss / generator boss.
What can you do to reduce load during ICS?
Closing open mains and nearby TX nps Block open TXs to deload the overloaded feeder Voltage reduction Operate UG switches to drop a portion of the feeder Transfer load for non-network Secondary or Service cuts Connect generation Customer appeals Cooling if it’s a TX overload