Computational Tools in Risk Management Flashcards

(6 cards)

1
Q

What is temporal risk?

A

Uncertainties potential delays related to time that can impact project completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are some sources of temporal risk?

A
  1. Unrealistic planning
  2. Project complexity
  3. Estimation completed in early stages
  4. Lack of contigency on critical activities
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the critical path method and when is an activity considered critical?

A
  • CPM is used to determine the longest sequence of dependent tasks. Any delays to these tasks will delay the whole project.
  • An activity is critical when float is zero
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

How do you perform CPM?

A
  1. Extract early and late finish times from Microsoft Project
  2. Calculate float
  3. Activities with zero float are considered critical
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the advantages and disadvantages of CPM?

A

Advantages:
1. Identifies tasks to manage closely
2. Enables resource smoothing (if time constraints take priority) or resource levelling (if resource constraints take prority)
3. Helps track project timelines
4. Visual representation

Disadvantages:
1. Assumes fixed durations, may not reflect real world uncertainties
2. Requires robust input data
3. Complex project can have overly complex diagrams

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q
A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly