Constrains and Estimations Flashcards

1
Q

What is EV? And what formula is used to calculate it?

A

Earned Value. It is the value of the work performed so far in a project. It is a method to track the dollar amount of the work performed by staff or consultants.
EV is determined by (percent of the project that is complete * the budget at completion).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is CV and how do you calculate it?

A

Cost variance is found by subtracting the EV from the AC.
The cost variance is the difference of the earned value and the actual costs of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is AC and how do you calculate it?

A

.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the cost of nonconformance?

A

Wasted materials are almost always a loss of resulting from a breakdown in quality. For example, network cables that are not punched down properly, purchasing wrong hardware for a system, or purchasing applications for the wrong operating system are all examples of the cost of nonconformance.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly