Construction Documents Flashcards

(64 cards)

1
Q

What drawing shows how the design was actually built.

A

As-Built (Record Drawings)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

All trees, shrubs, rock outcrops, slabs, structures, and utility lines within the project area are to be abandoned or moved

A

Clearing, Grubbing, Demolition

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

(1) Preliminary Surveying (2) Tree Protection, Temporary Conditions (3) Clearing, grubbing, and Demolition (4) Topsoil stripping and stockpiling (5)Rough Grading (6) Finish Grading (7) Installation of Site Improvements (8) Planting and Seeding

A

Construction Activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the purpose of Construction Documents?

A

Graphic and verbal instructions to a contractor for the purpose of bidding and constructing a proposed design. Provide the contractor with information concerning linear and aerial dimensions, volumes, and location of proposed elements. (1) Scale (2) Date (3) and North Arrow are required on all plans

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Contractors use Construction Drawings and Specifications to put together bids

A

Cost Estimate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Project Title, Sponsor, Consultants Names, Index to Drawings by Title and Sheet Number, a Project Location Map, a graphic key to the drawing symbols

A

Cover or Index Sheet

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

The plan that displays Information often overlaid the existing condition plan. Shows the items to be demolished, removed, relocated, or transplanted

A

Demolition Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

A reproduction of a registered survey plan for the site, drawn to or spliced into the standard sheet size of the working drawing set.

A

Existing Conditions Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What elements are required on the Existing Conditions Plan?

A

Scale, date, and North Arrow(True Magnetic North)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What should be included in the existing conditions plan?

A

Shows (1) Property Boundary line lengths and bearings (2) the total acres (3) the Topographic configuration illustrated with the contours and (4)significant spot elevations (5) existing structures (6)vegetation type and size (7) utilities (8) easements (9) adjacent roads (10) geodetic or DPW survey grid at 500 or 100 ft stations (11) a Location Map (12) and Boring Data.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Erosion Control

A

Prevent Silting of Streams and drains as regulated by the EPA specifications

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Establish finished elevations

A

Finish Grading

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Grading and Drainage Plan

A

Enables the contractor to establish vertical controls for the location of all site and building elements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What elements are included in a Grading and Drainage Plan?

A

Spot elevations, Contour Lines, locations and rim elevations of structures receiving runoff, Limit of grading (no-cut/no-fill line)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What plan(s) needs to be coordinated with building elevations, finished floor elevations, and all utility drawings?

A

Grading and Drainage Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Grubbing

A

Grubbing or clearing denotes the removal of trees, shrubs, stumps, and rubbish from a site, often from the site on which a transportation or utility corridor, e. g. a road or power line; an edifice, e. g. a home or office; or a garden is to be constructed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Layout and Materials Plan

A

Shows the Proposed development superimposed on existing conditions plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Drawing from which quantities and materials are calculated by the contractor

A

Layout and Materials Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Show detailed layouts in courtyards or entrances

A

Plan Enlargements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Show locations of all proposed plant materials, their names, sizes, and any other characteristics that will assist the designer

A

Planting Plan and Details

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What should be included in the plant list?

A

quantity, botanical name(genus, species, variety), common name, size (height, spread, caliper, etc), spacing, and special requirements(Multistem, first branch height, etc)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

A note or clause in the Planting Specifications should state that which of the following shall take precedence; plan or the list?

A

The Plan takes precedence over the Planting List

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

What constitutes the Primary Drawings?

A

(1) Cover or Index Sheet (2) Existing Conditions (3) Demolition Plan (4) Site Preparation Plan (5) Site Preparation (6) Grading and Drainage Plan (7) Planting Plan and Details (8) Utility Plan (9) Site Details and Sections

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Show a profile section along a roadway centerline and designate finish and existing grades at 50 to 100’ stations along that line

A

Road Profiles and Sections

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
What is Stationing?
A station is a Horizontal measurement along the Survey Center Line of a project.
26
How is Station Number 1 at a 100-foot interval written?
1+100
27
What is the difference in distance between Station 650(650+00) and Station 920(920+00)?
(920-650) x 100 = 27,000'
28
What is two feet ahead of station 500+00
500+02
29
Find the distance from the Station 20+60 to Station 12+80?
2060-1280=780'
30
The distance from Station 80+10 to 85+20?
8520-8010 = 8010
31
How many feet are in a half station?
50 feet
32
Invert elevations, pipe sizes, types, and locations
Surface drainage
33
Topsoil Stripping and Stockpiling
Contractor removes all topsoil within the grading limits and stockpiles the soil in an area that is convenient for future respreading
34
Moving trees to avoid construction damage
Tree Transplanting
35
Wrapped or enclosed. As described in the Specifications
Tree Protection
36
(1) Stormwater Drainage (2) Subdrainage (3) Sewerage (4) Water Distribution (5) Electrical layout (6) Buried cables (8) Steam and heat lines (9) Fuel Lines are included in what plan?
Utility Plan
37
What plans are laid over a half-toned grading plan?
Utility Plan
38
Preparation of all subgrade surfaces for footings and subbase materials for below or on-grade structures
Rough Grading
39
Detailed descriptions of (1) General Conditions (2)Special Provisions (3) Materials (4) Quantities (5) Information on Installation
Specifications
40
Procedure and performance standards
Specifications
41
Provided by a contractor when required by Designer
Shop Drawings
42
Convey specific methods of construction to the contractor
Site Details and Sections
43
Illustrates the proposed development and indicates the location of stockpiling areas, trees to be removed and thinned, limit of the work line, employee parking and construction road access, erosion control methods, concrete truck washout areas, staging areas, storage areas, stockpile areas, trees to be protected, and location of dewatering trenches or construction siltation ponds
Site Preparation Plan
44
Contractor verifies major dimensions, roadway geometry, property boundaries, construction limit line, stockpiling areas, and horizontal measurements
Preliminary Surveying
45
Major Source of General Construction Specifications
CSI Construction Specifications Institute
46
Legal Responsibilities of Costruction Documentss
Formal Legal Documents
47
Construction Activities
``` Each Drawing represents a class of operations Organized by Activity ```
48
Installation of Site Improvements
Contractor installs fixtures, benches, pavements, steps, trash, receptacles, planters, equipement, and finished amenities
49
Planting and Seeding
Contractor plants trees, shrubs, and other plant materials; mulches and edges beds; harrows, rakes, conditions, fertilizer, and seeds or sods
50
What part of every sheet contains (1)Sheet Title, (2)Client's Name, (3)Name of Consulting Firm(s) info (4)Date, (5)Drawn by, (6)Checked by, (7)Revision Block, (8)Job Number, (9)Sheet Number
Title Block
51
What information is included on each sheet?
(1)Title block, (2)Border, (3)North Arrow, (4)Written and Graphic Scale, (5)Registration Seal, (6)Appropriate legend, notes, and labels, (7) References to copyright
52
What are some Additional Drawings that may be included in a package?
Plan Enlargements, Road Profiles, and Sections, Shop Drawings, Record (as-built)drawings
53
What sheet displays the Project Title, Sponsor, Consultants Names, Index to Drawings by Title and Sheet Number, a Project Location Map, a graphic key to the drawing symbols?
Cover or Index Sheet
54
Forms the basis for Horizontal Controls formed presented in the layout plan and the vertical controls shown in the Grading Plan
Existing Conditions Plan
55
``` What drawing shows: Property Boundary line lengths and bearings Total acres The topographic configuration illustrated with the contours and significant spot elevations Existing structures Vegetation type and size Utilities Easements Adjacent roads Geodetic or DPW survey grid at 500 or 100 ft stations A Location Map Boring Data ```
Existing Conditions Plan
56
Shows the Proposed development superimposed on existing conditions plan
Layout and Materials Plan
57
The plan that shows the proposed design is located horizontally on the ground by using bearings and distances, station offsets, and coordinate points
Layout and Materials Plan
58
What plan(s) show the limit of grading is usually indicated by the no-cut/no-fill line?
Grading and Drainage Plan
59
What plan requires coordination with building elevations, finish floor elevations and Utilities?
Grading and Drainage Plan
60
True or False; A note or clause in the specifications should state that the plan shall take precedence over the list in the event of a discrepancy
True
61
The following is included in what document? ``` Property Lines Match lines Limit of contract Buildings and overhangs Paved areas, terraces, and walls Surface and sub-surface utilities Location and size of existing plant material Location, type, and size of proposed plant material Areas to receive seed or sod Planting list or schedule Existing and proposed topography Location of decorative lighting fixtures Irrigation ```
Planting Plan and Details
62
The plan that must be coordinated with other plans, specifically for major plantings or hard-surfaced areas?
Utility Plans
63
In some cases the Contractor is given latitude to design special features that require craftsmanship
Shop Drawings
64
What drawing must be drawn after the contractor notifies the landscape Architect so that changes can be added?
As-Built (Record Drawings)