Construction Test 1 - Lecture 3 Flashcards

(33 cards)

1
Q

How is the need for a construction project established?

A

It is recognized by the owner or users based on personal preference, profit, quality improvement, or market demand.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What analysis helps determine if the project need is justified?

A

Feasibility analysis, which includes cost evaluation, financial feasibility, market analysis, and local conditions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are conceptual drawings used for?

A

They are early-stage sketches and cost estimates presented to potential funding sources.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are common cost estimation methods?

A

Cost per unit, cost per square foot, cost per cubic foot, and using industry/historical data.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the two stages of the design process?

A

Preliminary design (40% complete) and Detailed design (fully developed drawings and specifications).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the purpose of the preliminary design phase?

A

To allow the owner to review financial feasibility and refine project requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What accuracy should the detailed estimate achieve?

A

±3% accuracy.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is construction bidding?

A

The process of submitting a proposal to undertake a construction project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Why is bidding important?

A

It introduces competition, reducing costs and selecting the most qualified contractor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are the two main types of bidding?

A

Competitive bid and negotiated bid.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Is cost the only factor in selecting a bid?

A

No, experience, capability, and realistic pricing are also considered.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What types of projects typically use the lowest bid as the basis for award?

A

Public infrastructure projects like bridges.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are the main steps in the bidding process?

A

Bid Request (Notice to Bidders)
Prequalification
Bid Package Preparation
Bid Submission
Bid Opening & Evaluation
Award of Contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is the purpose of a bid request?

A

To announce project opportunities and provide necessary details for prospective bidders.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

How is a bid request advertised?

A

Through newspapers, trade journals, mailing lists, trade association bulletins, and online databases.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Why is prequalification required?

A

To ensure the bidder has the technical competence, financial resources, and safety record to complete the project.

17
Q

What is the typical bonding capacity required?

A

10 times the liquid assets or net worth.

18
Q

What documents are included in a bid package?

A

Proposal form
General conditions
Special conditions
Drawings
Specifications
Addenda

19
Q

What is a proposal form?

A

A document submitted by the contractor showing intent to perform the work according to specifications and budget.

20
Q

What are the two types of bid proposals?

A

Lump-sum and unit-price proposals.

21
Q

What are general conditions in a contract?

A

Standard procedures applicable to all construction contracts, including contract administration and responsibilities.

22
Q

What are supplementary (special) conditions?

A

Project-specific conditions, such as duration, payment terms, and liquidated damages.

23
Q

What are technical specifications?

A

Verbal descriptions of project requirements, including materials, quality, and methods.

24
Q

What is an addendum?

A

A document detailing changes, additions, or corrections made before the bid submission deadline.

25
What is the estimated bid preparation cost for a $10 million project?
Approximately 0.25% of the total bid value.
26
What are important steps in preparing a bid proposal?
Analyzing bid documents Conducting site visits Estimating costs Ensuring all requirements are met
27
What happens during bid opening?
Bids are reviewed for compliance, and the lowest responsible bid is considered.
28
What is the "Notice of Intent to Award"?
A document inviting the winning bidder to discuss and sign the contract.
29
What is the "Notice to Proceed"?
A document authorizing the contractor to start work.
30
Under what conditions can a bid be withdrawn?
If a mistake is proven before bid acceptance.
31
What are common reasons for rejecting a bid?
too few bids, over-budget proposals, irregularities, or qualifications in the bid.
32
What is a bid substitution?
A voluntary change suggested by the contractor to improve cost, quality, or safety.
33
What is a bid alternate?
An option requested by the owner to compare different products or methods.