Contract Admin Flashcards
(327 cards)
What is a pay less notice?
- Issued by the employer in the event of over certification
- E.g. CA mistakenly certifies defective work that was only noticed after certificates were issued. CA informed and employer issues a pay less notice
- Also, if liquidated damages are due after non-completion issued.
What if the contractor goes out of business?
- Suspend payments
- Take back possession of the site
- Secure all unfixed materials
What is a variation?
- An item that has not been priced and included within the specification
- A variance to quality or quantity
How do you agree a valuation?
- Prior to works being undertaken.
What was the significance of the 2011 edition of the Local Democracy, Economic Development and Construction Act (Construction Act)?
- Removed requirement for contracts to be in writing for adjudication to apply
- Both employer and contractor can issue payment notices
- Revision of EoT provision
- New definition of insolvency
- Removal of pay when certified clause
What was the aim of the LDEDCA 2011 Construction Act?
- To tighten up payment, certification and payments to protect contractors.
What must you give when certifying a payment?
- Payment certificate
- Basis on which this has been calculated (valuation document)
What is insolvency?
- A company unable to pay its debts
What does a contract administrator do?
- Manage the contract between employer and contractor
- Administered by the employer
What is a designer?
- Someone employed to do design work.
What are the responsibilities of the CA?
- Administer terms of the building contract
- Agent for the employer, but acting impartially
- Makes decisions
- Both contractor and employer challenge decisions
What would you expect of a CA?
- Knowledge to understand the contract
- Knowledge to understand construction
- Impartial and fair
- Keep records
- Be aware of critical path and programming
What does a CA do?
- Meetings
- Valuations
- Inspection of works
- Determine EoT applications
- Interim payments
- Certify PC
- Settle final account
What information should you provide and in what format do you agree to take on an instruction?
- In writing
- Confirm terms and conditions of appointment
- Detail services provided
- Confirm fee basis
- Identify complaints handling procedure in place
- Limitations (what is not included)
- Dispute resolution procedure
- Level of PII
- Set out if CA is allowed to make changes
What do other consultants on a project do?
- Support the CA in administration (design changes, costs)
How do you know how many times you should visit site as a CA?
- Complexity of the project
- Calibre of the contractor
- Progress of work
- Predetermined stages
What do you look for on a site visit to a construction site?
- Activity on site
- Details of instructions given (are they doing it?)
- Progress
- Quality of work
- Check materials are being used
- Refer to preambles
- H&S arrangements
How do you check progress?
- Check against a programme
- Portion of works valued to date
- Experience – you should know
- Consult with suppliers
- The contractor should progress regularly and diligently
Would you value materials?
- If reasonably on site at the correct time
- If way too early, do not value.
In what instance will a variation be issued after PC?
- If defective work in rectification period.
What do you need to issue practical completion?
- H&S file – contractor provides information
- All test certificates
- Works complete (allow de-minimis)
- Beneficial occupation can be taken
When can a contractor make a claim for loss and expense?
- If they can evidence that a relevant matter has occurred, including deferment of possession by the employer, where the regular programme is affected by certain circumstances, but it must be a proven loss.
- Contractor to make a written application for consideration.
What is the risk if a claim for loss and expense is the fault of the surveyor? (Late issue of instruction)
- PII claim
- Must notify insurers
What statutes must you consider when taking on a project services instruction?
- Party Wall Act
- Town and Country Planning Act
- Tree Preservation Orders
- Conservation areas/listed buildings