Contract Administration Flashcards
What is phased completion?
Construction works can be planned as a series of stages or phases, rather than as one continuous process.
This can be useful for clients where a complex sequence of events needs to be followed (such as on densely occupied or complex site), or where there are a number of distinct components to the works, particularly for clients who are seeking to maintain some level of business operation during construction and so wish to minimise disruption.
In such cases, the project works can be divided into a series of smaller projects, spaced out over a period of months or even years.
What is sectional completion ?
Sectional completion refers to a provision within construction contracts allowing different completion dates for different sections of the works. This is common on large projects that are completed in sections, allowing the client to take possession of the completed parts whilst construction continues on others.
What are the risk associated with a client paying for items direct and outside of the contract ?
They would not be included within the contract, contract administrators inspection and have limited protection.
Can you please expand on what the role of a Contract Administrator is ?
A contract administrator manages contracts made between building contractors, employers, and clients. Their responsibility is to administer construction contracts, whereby they may act as project managers, engineers, consultants and client representatives
Can you expand on your knowledge of the JCT Intermediate contract ?
A JCT contract that allows for a number of addition in comparison to JCT MW including, clerk of works, sectional completion, partial possession, sectional completion and use of bonds
Can you expand on your knowledge of the JCT Standard Building Contract
The JCT SBC allows for, in addition to the intermediate contract such as:
Employers representative, listed sub contractors (for specialist works), retention bonds, variation and acceleration quotations, third party rights.
What JCT contracts allow for a clerk of works ?
- JCT standard Building contract
- JCT Intermediate Contract
- Not JCT MW
What contract allows for sectional completion and named sub contractors?
Intermediate and standard building contract
Can you talk me through the EOT timeline JCT ?
12
Contractor to notify the employer of the delay event (when it becomes reasonably apparent that it will affect the works, but this can be amended) - response to contractor (reasonably practicable/ within 12 weeks)
Can you talk me through the EOT timeline NEC ?
8-1-2
NEC = Delay that could affect completion date - early warning must be given by either PM or contractor- Risk reduction meeting - 8 weeks from becoming aware of the event the contractor must submit a CE (after 8 weeks EOT is waived) - PM has one week to notify the contractor of their decision - No response contractor can confirm the failure - PM then has 2 weeks to respond - if no response the CE is accepted -Contractor instructed to submit quotation - 3 weeks submits quotation - 2 weeks PM responds
Who produces the AS in NEC?
PM but the contractor responds with their own broken down into how they would like to get paid
Can you explain the interim payment procedure under JCT MW ?
7 - 5 - 14- 5
- Pre- contract stage state the interim valuation Date (IVD) (in the contract) - shouldn’t be more then a Month after commencement
- following valuations dates no more then one month after that
- interim payment due date is 7 day after the relevant IVD
Interim certificate is 5 days after due date - Final date for Payment must be made 14 days from the due date
- Pay less notice issued 5 days before final date for payment
7 - 5 - 14- 5
When can a employer claim for liquidated damages (JCT MW) ?
What are liquidated damages?
Liquidated damages are a well established method to collect compensation for a specific breach of a contractual obligation. If the breach is considered a relevant
What is the ‘Guide to select the appropriate JCT Main Contract ‘?
Its a diagram that helps enable you select the correct contract through a series of yes and no questions in a spider diagram.
Does JCT MW allow for clerk of works ? What contracts do allow for this ?
No it does not however, both intermediate and standard building contracts do allow for this.
What are the main types of tendering ?
- Open
- Selective
- negotiated
-Serial
-Framework
What are the main updates from JCT MW contract ?
JCT MW 2016 updates include:
- Amendments to reflect CDM 2015
- Increased Flexibility regarding insurance and ‘insured by other means’
- Simplified payment provision including the interim payment provision under the Housing Grant, Construction and Regeneration Act 1996
What is a traditional lump sum contract ?
A lump sum contract is the traditional means of procuring construction and involves a single ‘lump sum’ price for all the works being agreed before the works begin. This means that the contractor is able to accurately price the works they are being asked to carry out.
What is the role of the contract administrator ?
To administer the conditions/works under the terms of the contract. Acting impartially.
What is a contract variation ?
A change made to the terms or conditions of an existing contract. This could be altering the scope, price or deadlines ect. They can occur for a variety of reasons; unforeseen circumstances, changes in project requirement, or mutual agreement between parties.
What is traditional Procurement?
The traditional procurement route involves separating design from construction. The client first appoints consultants to design the project in detail and to ensure cost control and inspect the construction works as they proceed. Contractors are then invited to submit tenders for the construction of the project on a single-stage competitive basis.
Included in the contractor’s responsibilities are workmanship, materials and work undertaken by suppliers and subcontractors. The contractor is not responsible for the design (other than temporary works), although some traditional contracts may provide for the contractor to design specific parts of the works (see key criteria below).
Traditional procurement is typically undertaken under a lump sum contract. A single ‘lump sum’ price for all the works is agreed before the works begin, then stage payments are made as the works proceed. This is appropriate where the project is well defined when tenders are sought, and significant changes to requirements are unlikely. This allows the contractor to accurately price the works they are being asked to carry out.
What is single stage tender?
The most common type of tendering strategy is the
single-stage competitive tender for obtaining a price for
the whole of the construction works. Invitation to
tender documents are issued to a number of
competing contractors who are all given the chance to
bid for the project based on identical tender
documentation
What is procurement?
The overall act of obtaining goods and services from external sources and, includes deciding the strategy on how those goods are to be acquired by reviewing the clients requirements