Contract Dates Flashcards

(28 cards)

1
Q

Contractor to give Owner notice of cancellation or expiration of required insurance.

A

3 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Owner to give Contractor notice of cancellation or expiration of required insurance.

A

3 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Successful Bidder to deliver required bonds to Owner, after execution of Contract.

A

3 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Architect to issue addenda, before bid date.

A

4 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Contractor/Architect’s notice to Owner before disclosing confidential information.

A

7 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Architect to respond to Application for Payment.

A

7 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Contractor to pay subcontractor, after receiving payment from Owner.

A

7 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Contractor to provide proof of payment of subcontractors, at Owner’s request.

A

7 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Owner to pay Contractor, after date established in Contract Documents, if any.

A

7 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Contractor’s notice to Owner and Architect of stopping Work, after failure to receive payment.

A

7 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Contractor/Architect’s notice to Owner before terminating Contract for cause.

A

7 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Owner’s notice to Contractor before terminating for cause.

A

7 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Bidder’s deadline to submit RFIs, before bid date.

A

7 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Owner to furnish reasonable evidence of financial arrangements to Bidders, upon request.

A

7 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Architect to request lien rights from Owner, at Consultant’s request.

A

7 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Contractor to send Application for Payment to Architect, prior to scheduled progress payment date

17
Q

Bidder’s deadline to return Bid Documents to issuing office for refund of deposit, after bid date.

18
Q

Bidder’s deadline to propose substitutions, before bid date.

19
Q

Owner to furnish reasonable evidence of financial arrangements to Contractor, at Contractor’s request.

20
Q

Contractor to report concealed or unknown conditions, after discovery.

21
Q

Architect to report objections, whether by Architect or Owner, to proposed superintendent or subcontractors, or request additional time to consider.

22
Q

Owner to evaluate, give notice of, or enforce mechanic’s lien rights.

23
Q

Owner to furnish information necessary for Architect to evaluate, give notice of, or enforce lien rights, upon request.

24
Q

Injured party to give notice of injury or damage to other party, after discovery.

25
Of stopped Work, at no fault of the Contractor, before Contractor may terminate the Contract.
30 days
26
Days of stopped Work, due to Owner non conformance, before Contractor may terminate the Contract.
60 days
27
Days after Substantial Completion, Construction Phase services to be compensated as Additional Services.
60 days
28
Cumulative days of suspended Work before Architect can terminate.
90 days