Contract practice Flashcards
(38 cards)
What is a contract
Agreement enforceable by law, which establishes the rights and obligations of 2 parties
Within construction context it is the mechanism allowing the transfer of risk
What is required for a valid contract?
Offer
Acceptance
consideration - usually money exchanged for services. This aspect is the benefit which the parties bargaining for and the key for the parties entering into agreement
Intention to form legal agreement
- capacity (18+, mentally sound, not drunk etc.)
- authority - on behalf of the client
types of contract?
construction contract
consultant contract
s106
lease
what are some examples of standard forms of construction contract?
- JCT - SBC, small works, D&B
- NEC - 6 options (A-F)
- FIDIC
Why use standard forms?
- drafted by industry professionals, therefore all parties are represented fairly equally within the drafting
- well-known throughout the industry, more familiar for contractors therefore more likely to bid for the work & less dispute
- cheaper, no legal costs for drafting alternative clauses & less legal dispute in general
why amendments are made & any issues with this?
- amendments are made to contracts to include bespoke items which alter the risk balance or include a provision for a specific aspect of the project
- eg. of amendments - changes to the standard payment terms or within JCT contract forcing the programme to be submitted monthly
- amendments can be problematic as the contract is finely balanced and amending one clause can have a knock on effect
- for example, Grove vs Balfour Beatty (2016) was due to the fact the payment terms were struck out of the JCT D&B contract ‘to be agreed at a later date’. This never happened and they went to court
JCT contracts
- various forms: standard building contract (SBC), Design & Build (D&B), Minor Works Contract
- use a different form depending on the size of project & procurement route
- traditional form of contract, client / contractor relationship is traditional and often adverarial
- 9 main clauses (conditions) followed by the agreement (inc. project specifics) and then the schedules (TPRs etc)
- document for a D&B contract; Employers requirements (drawings & specs)
- architect / contract administrator (A/CA) appointed to administer the contract, certify payment & completion, judge EoTs etc
- D&B contract has an employer’s agent who does the same role
- a QS will be on board, who assesses valuations
NEC ECC contract (Engineering & construction contract)
- 6 forms of contract (options A-F) inc. lump sum, target price, cost plus, management contract
- focus upon collaboration throughout this contract through use of risk register, early warning system / meetings and punishment for not notifying of compensation events within 8 weeks.
- partnering option in secondary clauses
- project manager and supervisor administer the contract
- programme is a contract document, submitted and accepted by the PM every month
- documentation: works information (inc. technical drawings, spec, CDP, programme)
- suited to large infrastructure projects
what would you expect to see in a construction contract?
- articles (contract sum, client / contract named, arbitration / adjudication clause)
- contract particulars (LAD’s, programme, insurance cover)
- conditions (clauses re: carrying out works, EOTs etc)
- schedules (TPRs, arbitration)
- Design information (ERs or similar)
What are the key differences between NEC & JCT?
- price
- administration
- programme
- extension of time
what are the price differences between NEC and JCT?
- JCT are lump sum contracts, NEC has various payment mechanisms
- both deal with payments in broadly same way; applications to CA who certifies them
what are the administration differences between NEC / JCT?
JCT SBC has a contract administrator that issues instructions assesses claims and ensuring obligations are upheld and a QS that values the works
- NEC ECC has a project manager and supervisor. The supervisor issues instructions and makes decisions.
- D&B contracts have an employers agent which act as the contract administrator
what are the programme differences between JCT and NEC?
- JCT has no regular updates to the programme, just a programme required
- NEC the programme is a contract document and is issued to the PM monthly for their acceptables. Programme include float (unlike JCT) and key dates
What are the extension of time differences between JCT and NEC?
- JCT has 2 mechanisms which split time and money:
- relevant events - change the contract end date
- eg. variations, delayed VP, adverse weather, force majeure
- relevant matters - will also give the contractor claim for loss & expense
eg. work disruptions due to the client, delayed instruction from client, variations - NEC has compensation events which grant an extension of time and change in the price
- eg. NEC contract is only contract whereby bad weather will grant the contractor time and money
- compensation events need to be known within 8 weeks of occurrence or any claim for loss/expense can be rejected. JCT much less process driven in this respect
- CE’s must be defined within the contract to be valid
What are typical CEs?
- instructions
- force majeure
- weather
- client delays with information or access
what are the time periods for dealing with EOT claims under construction contracts?
JCT - Contractor should inform of a relevant event when a delay becomes reasonably apparent. The administrator must provide notice of the decision within 12 weeks of evidence receipt.
NEC - Contractor must give notice within 8 weeks of the event that a delay has been caused, the project manager then has 1 week to make a decision
what is a loss and expense claim? what is typically included?
- a claim by the contractor for costs incurred due to a relevant matter under the contract eg. failure to give possession
- will set out the ‘heads of claim’ with different losses eg. overhead, lost profits
- typically includes evidence eg. day work sheet
why is it important to select the most appropriate form of contract?
- may not be suitable to the procurement route
- parties not protected by correct obligations
- disputes will be more common
- poor risk allocation
- payment mechanism incorrect causing issues
what is a typical change control process?
- log proposed change in a register including:
- reason for change
- impact in time / cost / quality terms
- accept / reject change
- follow contractual process
- implement change and update drawings
what factors influence the selection of the most appropriate form?
- size and nature of works (complexity, value, type) eg. NEC more appropriate for infrastructure. JCT minor works vs SBC
- Procurement route - trad, D&B, CM
- Experience of client - eg. JCT minor works appropriate for inexperienced client
- familiarity - in the UK, JCT very popular and well known
- Country of use - FIDIC very popular in Middle East or for international works
- risk allocation and design responsibility (CDP / Novation)
- aspiration for working relationship - JCT more adversarial, NEC more collaborate
- level of tender information - JCT Employer’s requirements vs. NEC Works information
What are LADs?
- liquid and ascertained damages - costs payable by the contractor if the project runs past the agreed completion date
- these calculated prior to the contract being signed and usually a weekly rate
- note, LADs are a calculation not a penalty
- can include cost of temporary accommodation etc
construction all risks insurance?
- covers the client and contractor, policy jointly taken out by them
- all encompassing form of insurance which covers 3 aspects:
- works insurance - building falls down, plant stolen etc.
- 3rd party (public liability) - 3rd party causes damage
- employee liability - sometimes**
what is professional indemnity insurance (PI) and how it differs to all risks insurance?
- PI covers claims of negligence against professional services providers eg. PM, QS, Architect, Structural Engineer
- Different to public liability insurance, which covers 3rd parties
what types of insurance should a consultant appointment include?
- professional indemnity insurance
- 3rd party liability insurance
- employer’s liability insurance