Contract practice Flashcards

(38 cards)

1
Q

What is a contract

A

Agreement enforceable by law, which establishes the rights and obligations of 2 parties

Within construction context it is the mechanism allowing the transfer of risk

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is required for a valid contract?

A

Offer
Acceptance
consideration - usually money exchanged for services. This aspect is the benefit which the parties bargaining for and the key for the parties entering into agreement
Intention to form legal agreement
- capacity (18+, mentally sound, not drunk etc.)
- authority - on behalf of the client

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

types of contract?

A

construction contract
consultant contract
s106
lease

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

what are some examples of standard forms of construction contract?

A
  • JCT - SBC, small works, D&B
  • NEC - 6 options (A-F)
  • FIDIC
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Why use standard forms?

A
  • drafted by industry professionals, therefore all parties are represented fairly equally within the drafting
  • well-known throughout the industry, more familiar for contractors therefore more likely to bid for the work & less dispute
  • cheaper, no legal costs for drafting alternative clauses & less legal dispute in general
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

why amendments are made & any issues with this?

A
  • amendments are made to contracts to include bespoke items which alter the risk balance or include a provision for a specific aspect of the project
  • eg. of amendments - changes to the standard payment terms or within JCT contract forcing the programme to be submitted monthly
  • amendments can be problematic as the contract is finely balanced and amending one clause can have a knock on effect
  • for example, Grove vs Balfour Beatty (2016) was due to the fact the payment terms were struck out of the JCT D&B contract ‘to be agreed at a later date’. This never happened and they went to court
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

JCT contracts

A
  • various forms: standard building contract (SBC), Design & Build (D&B), Minor Works Contract
  • use a different form depending on the size of project & procurement route
  • traditional form of contract, client / contractor relationship is traditional and often adverarial
  • 9 main clauses (conditions) followed by the agreement (inc. project specifics) and then the schedules (TPRs etc)
  • document for a D&B contract; Employers requirements (drawings & specs)
  • architect / contract administrator (A/CA) appointed to administer the contract, certify payment & completion, judge EoTs etc
  • D&B contract has an employer’s agent who does the same role
  • a QS will be on board, who assesses valuations
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

NEC ECC contract (Engineering & construction contract)

A
  • 6 forms of contract (options A-F) inc. lump sum, target price, cost plus, management contract
  • focus upon collaboration throughout this contract through use of risk register, early warning system / meetings and punishment for not notifying of compensation events within 8 weeks.
  • partnering option in secondary clauses
  • project manager and supervisor administer the contract
  • programme is a contract document, submitted and accepted by the PM every month
  • documentation: works information (inc. technical drawings, spec, CDP, programme)
  • suited to large infrastructure projects
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

what would you expect to see in a construction contract?

A
  • articles (contract sum, client / contract named, arbitration / adjudication clause)
  • contract particulars (LAD’s, programme, insurance cover)
  • conditions (clauses re: carrying out works, EOTs etc)
  • schedules (TPRs, arbitration)
  • Design information (ERs or similar)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are the key differences between NEC & JCT?

A
  • price
  • administration
  • programme
  • extension of time
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

what are the price differences between NEC and JCT?

A
  • JCT are lump sum contracts, NEC has various payment mechanisms
  • both deal with payments in broadly same way; applications to CA who certifies them
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

what are the administration differences between NEC / JCT?

A

JCT SBC has a contract administrator that issues instructions assesses claims and ensuring obligations are upheld and a QS that values the works
- NEC ECC has a project manager and supervisor. The supervisor issues instructions and makes decisions.
- D&B contracts have an employers agent which act as the contract administrator

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

what are the programme differences between JCT and NEC?

A
  • JCT has no regular updates to the programme, just a programme required
  • NEC the programme is a contract document and is issued to the PM monthly for their acceptables. Programme include float (unlike JCT) and key dates
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are the extension of time differences between JCT and NEC?

A
  • JCT has 2 mechanisms which split time and money:
  • relevant events - change the contract end date
  • eg. variations, delayed VP, adverse weather, force majeure
  • relevant matters - will also give the contractor claim for loss & expense
    eg. work disruptions due to the client, delayed instruction from client, variations
  • NEC has compensation events which grant an extension of time and change in the price
  • eg. NEC contract is only contract whereby bad weather will grant the contractor time and money
  • compensation events need to be known within 8 weeks of occurrence or any claim for loss/expense can be rejected. JCT much less process driven in this respect
  • CE’s must be defined within the contract to be valid
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are typical CEs?

A
  • instructions
  • force majeure
  • weather
  • client delays with information or access
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

what are the time periods for dealing with EOT claims under construction contracts?

A

JCT - Contractor should inform of a relevant event when a delay becomes reasonably apparent. The administrator must provide notice of the decision within 12 weeks of evidence receipt.

NEC - Contractor must give notice within 8 weeks of the event that a delay has been caused, the project manager then has 1 week to make a decision

17
Q

what is a loss and expense claim? what is typically included?

A
  • a claim by the contractor for costs incurred due to a relevant matter under the contract eg. failure to give possession
  • will set out the ‘heads of claim’ with different losses eg. overhead, lost profits
  • typically includes evidence eg. day work sheet
18
Q

why is it important to select the most appropriate form of contract?

A
  • may not be suitable to the procurement route
  • parties not protected by correct obligations
  • disputes will be more common
  • poor risk allocation
  • payment mechanism incorrect causing issues
19
Q

what is a typical change control process?

A
  • log proposed change in a register including:
  • reason for change
  • impact in time / cost / quality terms
  • accept / reject change
  • follow contractual process
  • implement change and update drawings
20
Q

what factors influence the selection of the most appropriate form?

A
  • size and nature of works (complexity, value, type) eg. NEC more appropriate for infrastructure. JCT minor works vs SBC
  • Procurement route - trad, D&B, CM
  • Experience of client - eg. JCT minor works appropriate for inexperienced client
  • familiarity - in the UK, JCT very popular and well known
  • Country of use - FIDIC very popular in Middle East or for international works
  • risk allocation and design responsibility (CDP / Novation)
  • aspiration for working relationship - JCT more adversarial, NEC more collaborate
  • level of tender information - JCT Employer’s requirements vs. NEC Works information
21
Q

What are LADs?

A
  • liquid and ascertained damages - costs payable by the contractor if the project runs past the agreed completion date
  • these calculated prior to the contract being signed and usually a weekly rate
  • note, LADs are a calculation not a penalty
  • can include cost of temporary accommodation etc
22
Q

construction all risks insurance?

A
  • covers the client and contractor, policy jointly taken out by them
  • all encompassing form of insurance which covers 3 aspects:
  • works insurance - building falls down, plant stolen etc.
  • 3rd party (public liability) - 3rd party causes damage
  • employee liability - sometimes**
23
Q

what is professional indemnity insurance (PI) and how it differs to all risks insurance?

A
  • PI covers claims of negligence against professional services providers eg. PM, QS, Architect, Structural Engineer
  • Different to public liability insurance, which covers 3rd parties
24
Q

what types of insurance should a consultant appointment include?

A
  • professional indemnity insurance
  • 3rd party liability insurance
  • employer’s liability insurance
25
what is a parent company guarantee?
protects against insolvency, parent company would step in to pay or complete the works if required
26
what are bonds?
- protection against the contractor not performing their obligations - contractor will pay for the bond, which is held by a bondsman, and paid to the client in the event that the contractor fails
27
what is a performance bond?
- typically 10% of contract value, paid in the event the contractor fails to perform - helps pay for the client to find a new contractor
28
what is an advance payment bond?
- where the client has paid an advance payment for materials etc, a bond is paid by the contractor to secure against their default - if the contractor goes bust the bond is paid to the client to cover the costs - a certificate for materials purchased may be required, so the client can recoup the materials cost in the event of a default
29
what is a relation bond?
- alternative to retention payment (where 5% of the contract value held back until the end of defects) - retention bond is where a bond is held, rather than a retention amount - the value reduces after PC, with full payment on completion of defects period
30
what is a defects liability period?
- alternative to the above, essentially covers post-PC period through the end of defects period (typically 12 months post PC)
31
What is defects liability bond?
- an alternative to the above, essentially covers post-PC period through the end of defects period (typically 12 months post PC)
32
What are conditional vs. on-demand bonds?
conditional bonds require the client to provide evidence that the contractor has not performed their obligations, which on-demand are paid immediately
33
what are third party rights?
- allows a party not named in the contract (eg. purchaser, funder) to enforce the terms of the contract and grants them the benefits of the contract - in a practical sense, this would allow a funder to sue an architect for poor design work etc - TPR Act 1999 changed this, previously no 3rd party could have rights under a contract - 3rd parties are named in the contract or grouped eg. 'funder' if name not known - TPRs can be excluded from the contract
34
what are collateral warranties
- standalone document gives rights written within to a 3rd party - the parties are named in the CW, as in the original contract - liability limits can be different to those written within the contract - Form of CQ will be agreed and appended to the original contract
35
what is the difference between TPR's and CW's?
- TPR's are written within the contract and can just include the group of party eg. funder? - CW's standalone document which names the specific parties - Perception that CW's provide more control, although this is hardly true
36
What is some legislation to contracts?
- local democracy, economic development and construction act 2009 - EU GDPR directive and data protection Act 2018 - CDM regulations 2015
37
What is the local democracy, economic development and construction Act 2009?
- pay when paid clauses made illegal - allows contractor to suspend work if not paid - binding dispute resolution process (adjudication) - rights to interim payments
38
What is a collateral warranty?
- standalone document gives the rights written within to a 3rd party? - the parties are named in the CQ, as in the original contract - liability limits can be different to those written within the contract - form of CW will be agreed and appended to the original contract