Contract Practice - NEC full Flashcards
(36 cards)
What are the key updates from NEC3 to NEC4?
NEC4 has introduced two new contracts: 1. Design Build and Operate (DBO) Contract, and 2. Alliance Contract (ALC). The Risk Register is now the ‘Early Warning Register’. ‘Employer’ is now ‘Client’ and ‘Works Information’ is now ‘Scope’. A 4-week period for dispute escalation and negotiation has been introduced. ‘Partnering’ is now ‘Collaboration’. There is only one fee percentage, and contractors must submit applications for payments. All contracts are now written gender neutrally.
What does NEC stand for?
New Engineering Contract.
What does ECC stand for?
Engineering and Construction Contract.
Please can you give me an overview of the NEC4 ECC contract?
The NEC4 ECC contract is suitable for any sector, promotes cooperation and fair risk allocation, and includes six main options (A - F). It emphasizes clarity, flexibility, and requires early warnings from parties.
What are some advantages of using the NEC4 ECC contract?
Advantages include clarity and simplicity, flexibility and adaptability, collaboration and communication, strong risk allocation and management, and mechanisms for dispute avoidance and resolution.
What are the 6 main options under the NEC4 ECC contract?
Option A: Priced contract with activity schedule. Option B: Priced contract with bill of quantities. Option C: Target contract with activity schedule. Option D: Target contract with bill of quantities. Option E: Cost-reimbursable contract. Option F: Management contract.
Can you provide an overview of Option A?
Option A involves a priced activity schedule suitable for well-defined scopes. Payments are based on completed activities, and the contractor assumes risk for delivering at agreed prices.
Can you provide an overview of Option B?
Option B is a priced contract with a bill of quantities. It quantifies work items with specified quantities and prices, suitable for accurately quantified projects.
Can you provide an overview of Option C?
Option C is a target contract with an activity schedule, allowing shared financial risk between client and contractor, motivating cost-efficient delivery.
Can you provide an overview of Option D?
Option D is a target cost contract with a bill of quantities, similar to Option C but uses a BoQ instead of an activity schedule.
Can you provide an overview of Option E?
Option E is a cost-reimbursable contract ideal for projects with undefined scopes, where the contractor is paid actual costs plus an agreed fee.
Can you provide an overview of Option F?
Option F is a cost-reimbursable management contract where the contractor acts as a management contractor, and the client pays actual amounts to suppliers plus a fee.
Which NEC4 ECC main option carries the least financial risk for the employer?
Option A, as it is a fixed price contract.
Which NEC4 ECC main option carries the most financial risk for the employer?
Option E, as the contractor is reimbursed for actual costs incurred plus a fee.
What are secondary options under NEC4 ECC?
Secondary options (X, Y, Z) are optional clauses that can be applied to the contract, with X and Y being pre-written and Z being bespoke amendments.
What are the X Clauses under the NEC4 ECC contract?
X Clauses include: X1 (Price adjustment for inflation), X2 (Changes in law), X3 (Multiple currencies), X4 (Ultimate holding company guarantee), X5 (Sectional completion), X6 (Bonus for early completion), X7 (Delay damages), X8 (Undertakings), X9 (Transfer of rights), X10 (Information Modelling), X11 (Termination by the client), X12 (Multiparty collaboration), X13 (Performance bond), X14 (Advanced payment), X15 (Contractor’s design), X16 (Retention), X17 (Low performance damages), X18 (Limitation of liability), X20 (Key performance indicators), X21 (Whole life cost), and X22 (Early contractor involvement).
What are the options for dispute resolution under NEC4 ECC?
Options W1, W2, and W3 provide formal dispute resolution, with W1 requiring initial referral to senior representatives and W3 allowing for a Dispute Avoidance Board.
What are Z clauses?
Z clauses are bespoke amendments that allow parties to agree on additional terms specific to a project.
What problems can potentially arise when drafting Z clauses into the contract?
Poorly drafted Z clauses can conflict with core clauses, impacting the contract’s effectiveness. They should be drafted by knowledgeable individuals.
What is ‘scope’ under NEC4 ECC contracts?
Scope refers to the extent and boundaries of the required works, including specific activities and deliverables the contractor is responsible for.
Which of the NEC ECC contracts are design & build contracts?
The NEC ECC contract can be suitable for contractors with no design responsibility or full design responsibility, as defined in the scope.
What is ‘site information’ under NEC4 ECC contracts?
Site information describes past and present site conditions, including subsoil investigations, survey information, and details about underground and above-ground services.
What are compensation events?
Compensation events are events not caused by the contractor that change the cost or time needed to complete the work, potentially entitling the contractor to more time or money.
Does the NEC contract have relevant events and relevant matters like JCT?
No, NEC contracts address these issues under the single heading of compensation events.