Control Costs Flashcards
Monitoring & Controlling (24 cards)
What is the purpose of the Control Costs process?
To monitor the status of the project, to update project budget and manage changes to the cost baseline.
What are the outputs of Control Costs Process?
1) Work Performance Information, 2) Change Requests, 3) Costs Forecasts, 4) Project Mgmt Plan Updates, 5) Project Document Updates, 6) OPA Updates
What are the tools and techniques to Control Costs?
1) Earned Value Mgmt, 2) Costs Forecasts, 3) To-complete Performance Index (TCPI), 4) Performance Reviews, 5) Project Mgmt Software, 6) Reserve Analysis
What is Earned Value Management (EVM)?
Methodology that combines scope, schedule, and resource measurements to assess project and progress. The difference between Planned Value and Earned Value.
What is Planned Value (PV)?
The authorized budget assigned to scheduled work which does not include Management Reserve.
What is Budget at Completion (BAC)?
The total Plan Value for the project.
What is Earned Value (EV)?
Measure of work performed expressed in terms of the budget authorized for that work which is used to calculate the percentage complete of a project.
What is Actual Costs (AC)?
Costs incurred for the work performed on an activity during a specific time period.
What is Estimate of Completion (EAC)?
Expected total cost (forecast) at the end.
What is Estimate to Complete (ETC)?
Expected remaining costs (now until end).
What is Variance of Completion (VAC)?
Expected variance over/under budget.
What is Cost Management Plan?
Plan that describes how costs will be planned, structured and controlled.
How do you calculate Cost Variance (CV)?
EV - AC = CV (Negative bad, Positive good)
How do you calculate Schedule Variance (SV)?
EV - PV = SV (Negative bad, Positive good)
How do you calculate Cost Performance Index (CPI)?
EV / AC = CPI (Under 1 is bad, Over 1 is good)
How do you calculate Schedule Performance Index (SPI)?
EV / PV = SPI (Under 1 is bad, Over 1 is good)
How do you calculate Estimate to Complete (ETC)?
EAC - AC = ETC (Value of work remaining)
How do you calculate Variance at Completion (VAC)?
BAC - EAC = VAC (Negative is bad, Positive is good)
How do you calculate to Complete Performance Index (TCPI) within budget?
(BAC - EV) / (BAC - AC) = TCPI (Use 80% of time)
How do you calculate to Complete Performance Index (TCPI) outside of budget?
(BAC - EV) / (EAC - AC) = TCPI (Use if original budget is not possible)
How do you calculate Estimate at Completion (EAC) with atypical variance (not continue or budget rate)?
AC + (BAC - EV) = EAC (Actual cost plus work remaining, is not based on past performance)
How do you calculate Estimate at Completion (EAC) with typical variance?
BAC / CPI = EAC (Use this calculation if project is on track, is based on past performance)
How do you calculate Estimate at Completion (EAC) with assume poor performance but need to hit firm completion date?
AC + [(BAC - EV) / (CPI * SPI)] = EAC
What is To Complete Performance Index (TCPI)?
A measure of cost performance that is acquired to be achieved with the remaining resources in order to meet a specified management goal.