CORP 2 - Chapter 13 Flashcards

(42 cards)

1
Q
Risk is usually measured as the
A. potential loss.
B. variability of outcomes around some expected value.
C. probability of expected values.
D. potential expected loss.
A

Risk is usually measured as the

B. variability of outcomes around some expected value.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q
If three investment alternatives all have some degree of risk and different expected returns, which of the following measures could best be used to rank the risk levels of the projects?
A. coefficient of correlation
B. coefficient of variation
C. standard deviation of returns
D. net present value
A

If three investment alternatives all have some degree of risk and different expected returns, which of the following measures could best be used to rank the risk levels of the projects?

B. coefficient of variation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

The term “risk averse” means that
A. an individual refuses to take risks.
B. most investors and businesspersons seek risk.
C. an individual will seek to avoid risk or be compensated with a higher return.
D. only investment proposals with no risk should be accepted.

A

The term “risk averse” means that

C. an individual will seek to avoid risk or be compensated with a higher return.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

In order to reduce risk in a firm, the firm would seek to enter a business that
A. has high positive correlation with its present business.
B. has zero correlation with its present business.
C. has high negative correlation with its present business.
D. has high negative variation with its present business.

A

C. has high negative correlation with its present business.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

The “efficient frontier” indicates
A. alternatives with neutral combinations of risk and return.
B. alternatives with the highest returns.
C. alternatives with the best combination of risk and return.
D. alternatives with no risk.

A

The “efficient frontier” indicates

C. alternatives with the best combination of risk and return.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Risk may be integrated into capital budgeting decisions by
A. adjusting the standard deviation of possible outcomes.
B. determining the expected value.
C. adjusting the discount rate.
D. adjusting the time horizon.

A

Risk may be integrated into capital budgeting decisions by

C. adjusting the discount rate.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Which of the following is a false statement?
A. risky investments may produce large losses
B. risky investments may produce large gains
C. the coefficient of variation is a risk measure
D. risk-averse investors cannot be induced to invest in risky assets

A

Which of the following is a false statement?

D. risk-averse investors cannot be induced to invest in risky assets

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

If one project has a higher standard deviation than another
A. it has a greater risk.
B. it has a higher expected value.
C. it has more possible outcomes.
D. it may be riskier, but this can only be determined by the coefficient of variation.

A

If one project has a higher standard deviation than another

D. it may be riskier, but this can only be determined by the coefficient of variation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q
The firm's highest risk-adjusted discount should be applied to
A. the repair of old machinery.
B. a new product in a related field.
C. a new product in a foreign market.
D. the purchase of new equipment.
A

The firm’s highest risk-adjusted discount should be applied to

C. a new product in a foreign market.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

The portfolio effect in capital budgeting refers to
A. the relationship of stocks to bonds.
B. the degree of correlation between various investments.
C. the coefficient of variation.
D. the risk-adjusted discount rate.

A

The portfolio effect in capital budgeting refers to

B. the degree of correlation between various investments.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

An example of negative correlation may exist between the
A. forest products and housing industries.
B. jewellery and discount furniture industries.
C. steel and aluminum industries.
D. oil and auto industries.

A

An example of negative correlation may exist between the

B. jewellery and discount furniture industries.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

A correlation coefficient of zero indicates
A. the projects have the same expected value.
B. there is no correlation and no risk reduction between combined projects.
C. there is no correlation, but some risk reduction when the projects are combined.
D. the projects have the same standard deviation.

A

A correlation coefficient of zero indicates
A. the projects have the same expected value.

C. there is no correlation, but some risk reduction when the projects are combined.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Which investment has the least amount of risk?
A. standard deviation = $500, expected return = $5,000
B. standard deviation = $700, expected return = $500
C. standard deviation = $900, expected return = $800
D. standard deviation = $400, expected return = $350
Block

A

Which investment has the least amount of risk?

A. standard deviation = $500, expected return = $5,000

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q
In order to evaluate risk, management may also set qualitative risk classes. Rank these four projects from the least to the most risky.
1. completely new market in Canada
2. completely new market in South America
3. addition to normal product line
4. repair to old machinery
A. 4, 3, 1, 2
B. 1, 2, 3, 4
C. 3, 4, 1, 2
D. 2, 3, 4, 1
A

In order to evaluate risk, management may also set qualitative risk classes. Rank these four projects from the least to the most risky.

  1. completely new market in Canada
  2. completely new market in South America
  3. addition to normal product line
  4. repair to old machinery

A. 4, 3, 1, 2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

In a portfolio, risk is evaluated in a different way than with an individual project. In evaluating portfolio risk we
A. need to consider the impact of a given project on the overall risk of the firm.
B. recognize that a risky investment may create a portfolio with less risk.
C. need to consider how the returns of the projects in the portfolio are correlated.
D. all of the other answers are correct.

A

In a portfolio, risk is evaluated in a different way than with an individual project. In evaluating portfolio risk we

D. all of the other answers are correct.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

A “what if” simulation using a computer helps to:
A. reduce the risk associated with a particular investment.
B. determine the effects of changes in certain variables.
C. increase the accuracy of the inputs.
D. more than one of the above are true

A

A “what if” simulation using a computer helps to:

B. determine the effects of changes in certain variables.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q
An analytical tool which helps to organize the decision process by presenting a graphical comparison of investment choices is called a(an)
A. module hierarchy diagram.
B. "what if" simulation.
C. decision tree.
D. none of the other answers are correct
A

An analytical tool which helps to organize the decision process by presenting a graphical comparison of investment choices is called a(an)

C. decision tree.

18
Q

The lower the coefficient of correlation the greater the
A. risk when projects are combined.
B. risk reduction when projects are combined.
C. return when projects are combined.
D. standard deviation when projects are combined.

A

The lower the coefficient of correlation the greater the

B. risk reduction when projects are combined.

19
Q

Simulation models allow the planner to
A. reduce the standard deviations of projects.
B. test possible changes in each variable.
C. deal with the uncertainty in forecasting outcomes.
D. two of the other answers are correct

A

Simulation models allow the planner to

D. two of the other answers are correct

20
Q
Which of the following is a common approach in dealing with uncertainty?
A. Monte Carlo simulation
B. internal rate of return
C. net present value
D. beta analysis
A

Which of the following is a common approach in dealing with uncertainty?

A. Monte Carlo simulation

21
Q

Using progressively higher discount rates
A. tends to penalize late flows more than early flows.
B. tends to penalize early flows more than late flows.
C. tends to lower net present value.
D. two of the other answers are correct

A

Using progressively higher discount rates

D. two of the other answers are correct

22
Q
Using the risk-adjusted discount rate approach, projects with high coefficients of variation will have \_\_\_\_\_\_ net present values than projects with low coefficients of variation.
A. somewhat higher
B. substantially higher
C. lower
D. none of the other answers are correct
A

Using the risk-adjusted discount rate approach, projects with high coefficients of variation will have ______ net present values than projects with low coefficients of variation.

C. lower

23
Q
A coefficient correlation of \_\_\_\_\_ provides no risk reduction.
A. 0
B. - 1
C. + 1
D. +.5
A

A coefficient correlation of _____ provides no risk reduction.

C. + 1

24
Q
A coefficient of \_\_\_\_\_ provides the greatest risk reduction.
A. 0
B. - 1
C. + 1
D. +.5
A

A coefficient of _____ provides the greatest risk reduction.

B. - 1

25
``` Using the risk-adjusted discount rate approach, the cost of capital is applied to projects with A. normal risk. B. high risk. C. no risk. D. low risk. ```
Using the risk-adjusted discount rate approach, the cost of capital is applied to projects with A. normal risk.
26
Beta is a better risk measure than standard deviation when the firm A. is effectively diversified. B. focused on total risk. C. uses the CAPM in its cost of capital calculation. D. has a beta that is close to 1.0.
Beta is a better risk measure than standard deviation when the firm A. is effectively diversified.
27
The certainty equivalent approach A. is only appropriate for analyzing cash flows with risk similar government securities. B. adjusts each cash flow based on a probability distribution. C. adjusts the discount to suit the risk of each cash flow. D. models the sequence of decisions required over time
The certainty equivalent approach B. adjusts each cash flow based on a probability distribution.
28
``` A Monte Carlo simulation model uses A. random variables as inputs. B. a point estimate. C. the cost of capital. D. portfolio risk ```
A Monte Carlo simulation model uses A. random variables as inputs.
29
``` Projects that are totally uncorrelated provide A. no risk reduction. B. some risk reduction. C. extreme risk reduction. D. need more information ```
Projects that are totally uncorrelated provide B. some risk reduction.
30
In order to reduce risk in a firm, the firm would seek to enter a business that A. has high positive correlation with its present business. B. has zero correlation with its present business. C. has high negative correlation with its present business. D. none of the other answers are correct
In order to reduce risk in a firm, the firm would seek to enter a business that C. has high negative correlation with its present business.
31
The "efficient frontier" indicates A. alternatives with neutral combinations of risk and return. B. alternatives with the highest returns. C. alternatives with no risk. D. none of the other answers are correct
The "efficient frontier" indicates D. none of the other answers are correct
32
Which of the following is a true statement? A. risky investments may produce large losses B. risky investments may produce large gains C. the coefficient of variation is a risk measure D. all of the other statements are true
Which of the following is a true statement? D. all of the other statements are true
33
Projects that are negatively correlated A. increase the maximum profit potential for the firm. B. increase the possible losses of the firm. C. are generally in the same industry. D. none of the other answers are correct
Projects that are negatively correlated D. none of the other answers are correct
34
The concept of being risk averse means A. for a given situation investors would prefer relative certainty to uncertainty. B. investors would prefer investments with low standard deviations and greater opportunity for gain. C. that the lower the risk the lower the expected return must be. D. all of the other answers are correct
The concept of being risk averse means D. all of the other answers are correct
35
Which investment has the least amount of risk? A. standard deviation = $800, expected return = $400 B. standard deviation = $700, expected return = $3,000 C. standard deviation = $1,000, expected return = $8,000 D. standard deviation = $1,000, expected return = $7,000
Which investment has the least amount of risk? C. standard deviation = $1,000, expected return = $8,000
36
In a portfolio, risk is evaluated in a different way than with an individual project. In evaluating portfolio risk we A. need to consider the impact of a given project on the overall risk of the firm. B. recognize that a risky investment always creates a portfolio with less risk. C. need to ensure all the projects in the portfolio are positively correlated. D. all of the other answers are correct
In a portfolio, risk is evaluated in a different way than with an individual project. In evaluating portfolio risk we A. need to consider the impact of a given project on the overall risk of the firm.
37
Simulation models allow the planner to A. reduce the standard deviations of projects B. test possible changes in each variable C. deal with all uncertainty in forecasting outcomes D. increase the standard deviation of projects
Simulation models allow the planner to B. test possible changes in each variable
38
``` A project has the following projected outcomes: $100, $500, and $800. The probabilities of their outcomes are 10%, 50%, and 40% respectively. What is the standard deviation of these outcomes? A. $224 B. $580 C. $24 D. $546 ```
A project has the following projected outcomes: $100, $500, and $800. The probabilities of their outcomes are 10%, 50%, and 40% respectively. What is the standard deviation of these outcomes? A. $224
39
``` A project's coefficient of variation is 0.50. The project has a positive coefficient of correlation of 0.20. The expected value is $3,000. What is the standard deviation? A. $600 B. $300 C. $1,200 D. $1,500 ```
A project's coefficient of variation is 0.50. The project has a positive coefficient of correlation of 0.20. The expected value is $3,000. What is the standard deviation? D. $1,500
40
Using progressively higher discount rates A. tends to penalize late flows more than early flows B. tends to penalize early flows more than late flows C. tends to increase net present value D. none of the other answers are correct
Using progressively higher discount rates A. tends to penalize late flows more than early flows
41
``` A project's total risk is measured by _________________________. A. Beta B. Sharpe Ratio C. Chi Square D. coefficient of variation ```
A project's total risk is measured by _________________________. D. coefficient of variation
42
``` The W Equity portfolio has a standard deviation of returns of 8. The R Bond portfolio has a standard deviation of returns of 6. If the Cov of these portfolio is 5 what is this portfolio's coefficient of correlation? A. .1042 B. .889 C. .43 D. -.1042 ```
The W Equity portfolio has a standard deviation of returns of 8. The R Bond portfolio has a standard deviation of returns of 6. If the Cov of these portfolio is 5 what is this portfolio's coefficient of correlation? A. .1042