Cost Flashcards

(43 cards)

0
Q

What is NPV?

A

NPV compares the value of a dollar today vs the value of the same dollar in the future after taking inflation and discount rate into account.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
1
Q

What are 4 types of cost?

A

Direct cost: Cost directly attributable to the work of the project (salaries of coders)
Indirect cost: Cost indirectly attributable to work of the project (project building security cost)
Fixed cost: Consistent cost throughout the life of the project regardless of activity of project.
Variable cost: Cost that fluctuates with activity on project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is ROI?

A

Return on Investment - Chose the biggest

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is IRR?

A

Internal rate of return: NPV of all cash flow equal to zero.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is BCR?

A

Benefit to cost ratio: Compares benefit of project to cost. Usually want 1:1.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is Opportunity cost?

A

Cost associated with taking another oppty.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is payback period?

A

Payback period is the amount of time need to earn back the investment.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is future value?

A

The value of something (cash) at a point in the future - for ex. FV of 1000 invested at 8% for three years 1259.
FV=PV x (1.r) to the n power

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is present value? PV

A

Present value of something today that you need to create a certain amount of investment in the future.

PV= FV/(1+r) to the n power

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is sunk cost?

A

Cost that has been already spent on a project. Do not consider sunk cost when making project decisions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is depreciation?

A

The process of devaluing a capital asset in the tax system. (Wear and tear on an asset)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

How is standard depreciation calculated?

A

Starting value - Scrape value / timeframe

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is accelerated depreciation?

A

This allows a company / project to realize more depreciation sooner. Two types:
Sum of year digit
Double declining balance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is lifecyle costing (total cost of ownership)?

A

Process of examining all costs associated with a project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is fixed formula progress reporting?

A

aka earned value rules. Technique that creates a consistent status report for project activities. Used for shorter duration not exceeding to reporting periods.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is weighted milestone?

A

Usu used for activities that are longer than two reporting periods. Work is divided into multiple milestones with a measurable output for each section.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is plan cost management?

A

Process used to create the cost mgmt plan.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What are inputs to Plan Cost Mgmt?

A

Project mgmt plan
Project charter
EEFs
OPAs

18
Q

What are tools and techs to Plan Cost Mgmt?

A

Expert judgement

Analytical techs

19
Q

What are inputs to Estimate Cost?

A
Cost mgmt plan
HR plan
Scope baseline
Proj schedule
Risk register
20
Q

What are tools and techs to Estimate Cost?

A
Expert judgement
Analogous estimating
Parametric estimating
Bottom up estimating
Three point estimating
Reserve analysis
Cost of quality
Vendor bid analysis
Proj mgmt software
21
Q

What is cost range?

A

Key principle in any environment is that the less is known earlier in proj the wider tolerance needed for project costs. (could be -25% to +75%)

22
Q

What are inputs to Determine Budget?

A
Cost mgmt plan
Scope baseline
Activity cost est
Basis of est
Proj schedule
Resource calendars
Risk register
Agreements
23
Q

What are tool and techs to Estimate Cost?

A
Cost aggregation
Reserve analysis
Expert judgement
Historical relationships
Funding limit reconciliation
24
What are outputs to Estimate Cost?
Cost baseline | Report funding requirements
25
What is chart of accounts?
List of accounts used by accounting to track budgets associated with project
26
What is code of accounts?
Numbering system applied to project mgmt to identify individual pieces of work in the WBS.
27
What are inputs to Control Costs?
Project mgmt plan Proj funding reqs Work performance data OPAs
28
What are tools and techs to Control Costs?
``` Earned Value mgmt Forecasting TCPI (To complete performance index) Performance review PM software Reserve analysis ```
29
What is earned value management?
Technique for measuring the progress of a project by looking at its scope, schedule, and cost in an integrated manner.
30
Types of earned value: | Budget at Completion?
Amount you expect the project to cost.
31
Types of earned value: | What is planned value?
What is budgeted cost of the work scheduled?
32
Types of earned value: What is actual cost? AC
Cost of work completed.
33
Types of earned value: | What is earned value?
Measurement of progress of project including any work started ahead of schedule.
34
Types of earned value: | What is schedule performance index?
EV/PV | An effeciency indicator that denote the amount of work done at a single point in time. If result is 1, work is on track.
35
Types of earned value: What is schedule variance? SV
EV-PV Denotes the difference between the value of the work completed and value of the work that should have been completed.
36
Types of earned value: | Cost performance index (CPI)
EV/AC Denotes the return on each dollar spent at a point in time. Result of 1 means project is on track.
37
Types of earned value: | What is cost variance?
EV-AC Denotes difference btw cost of work completed vs value of work completed. Result of 0 means project is on track.
38
Forecasting: What is Estimate at Completion?
Current projected final cost based on the current spending efficiency. EAC = BAC / CPI
39
Forecasting: What is Estimate to Complete?
Amount needed to finish the project based on the current spending efficiency of the project. ETC = EAC-AC
40
Forecasting: What is Variance at Completion?
Difference between the budget at completion and estimate at completion. VAC = BAC - EAC
41
Forecasting: What is to complete performance index?
Effeciency needed from the remaining resources to meet the cost goals and finish on time. TCPI = (BAC - EV) / (BAC - AC)
42
What is S-Curve?
Graphic representation of interaction between cost, scope, and time over life of project.