CPA Flashcards

(10 cards)

1
Q

wha is cpa

A

a project management technique which completes the project in the shortest possible time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

what is float time

A

amount of time that a task can get delayed without causing a delay to the completion date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

what is EST

A

earliest start time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

what is LFT

A

Latest finishing time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

how to calculate Total float

A

LFT(this activity)-Duration-EST(this activity)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

how to calculate Free float

A

EST(next activity)-Duration-EST(this activity)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

what is free float

A

amount of time an activity can be delayed without causing a delay to the next activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Advantages of CPA

A

-Identifies activities that have a float time
-Identifies critical path analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Disadvantages of CPA

A

-Just a prediction, reliability is based on estimates
-Lots of activities can make a CPA complictaed to manage

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q
A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly