Critical path Analysis Flashcards

(28 cards)

1
Q

What is the precedence table

How to make the precedence tables

A

This a table to show each activity and what they depend on (what must be com0leted first) for that activity ti continue )

Make a chart with activities on left and dependence on right

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

How to SIMPLIFY precedence tables

A

Basically if it says something like G depends on all, think of activities that if you included means you don’t have to include another, because one DEPENDS on another

Basically if it says all, add all activities that ARENT present in the precedence’s before

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How to convert the precedence table into an ACTIVITY NETWORK

A

Label each new node , starting from 0 of the sink
1) MUST have a source and sink node.
2) things that don’t depend on anything come out of sink
3) try make as straight and not overlap as possible, but if can’t it’s okay

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What does a dummy activity hold value waive and what does it do

A

It holds 0

It just connects nodes together which would otherwise be impossible to connect

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

When making an activity network, what should you aim to do FIRST to avoid mistakes?

A

Always try do the activities that depend on ONE THING ONLY first, otherwise it might be impossible to do

Then try do those depend on 2 ONLY

You’ll find this way you won’t make mistake with dummy variables

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What does an activity network allow you to model

A

Basically tasks, and their durations , what depends on each other

You can see which tasks must be done on time to avoid the overall project form running late etc, snd which tasks have more freedom when to be completed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How to do FORWARD PASS to find Early times

A

whatever the number is, add the arc weight to it

2; next compare all options, and when a decision must be made PICK THE BIGGEST SIZE CHOICE

(This because for that event to pass, all other activities must at least pass, so you know to pick the biggest earliest time to accommodate for everyone Else)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How to do BACKWARD PASS to find all the late START times

A

First the LAST BOX IS DUPLICATED

  • subtract this time when going back in weights
  • only make a choice if you have all backward pass OPTIONS AVAILABLE TO YOU
  • when making a choice, pick the EARLIEST TIME

(This because if you pick a bigger time, then an activity will be missed as you went past it’s deadline)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

When done the forward and backward pass, what should look like and how to find CRITICAL ACTIVITIES AND PATHS

What is a critical path even show

A

First should be 00 and last same same

  • critical activities are those with the same early and late start
  • critical path is where two critical activities are connected EXACTLY by the weight in between

This means this activity must start at this and end at that time, else whole project overload

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How ti find overall critical path

critical vs non critical?

A

Just connect all other critical paths up

2) Remember critical paths are activities that must start and finish at certain times else project is late

Whereas non critical paths have some room to FLOAT

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

3 types of float

A

Total
Independent
Interfering

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

How to work out total float

A

Late finish - early start - duration

Or OUTER - outer - duration

(This bevause the total length is subtraction of outer, but actual wriggle room in thr slider is given by subtracting from the weight too)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is the INDEPENDENT FLOAT
How to work out

What happens if answer is less than 0?

A

1) independent float is the amount of float activity can do without causing any other activities to start late or finish earlier
(For example if I finish late, then the next activity can’t start earlier )

2) INNER - INNER - DURATION

if less than 0, then = to 0

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is the interfering float and how to calculate

A

This is the float that WILL cause neighbouring activities to be forced to start and finish differently

Would = total float - independent float

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is the total independent and interfering float for critical activities

A

00 and 0

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

How to make cascade / gannt chart
Critical paths
- non critical path activities + how to show the float

A

1) time on x axis till max time
2) ANYTHING THAT IS CRITICAL PATH, CONNECT IT
- start with early start time, then make box length of duration
- connect each critical path together as next will start after lentgh of duration

3) Anything that ISNT critical takes a row each by itself and goes above
- again start early start, make width duration and MAKE DASHED BOX UNTIL LATE FINISH TIME= this represents the total, float

17
Q

How to show MULTIPLE CRITICAL PATHS

A

First critical path = first row

Second one goes on top, and here include all activities that weren’t INJTALLT IN FIRST ROW CRITICAL PATH

18
Q

How to make resource histogram from giant chart / without

A

Gang chart = act like gravity has dropped each thing down

ITS SUPPOSED TO SHOW AMLUNT IF WORKERS REQUIRES EACH DAY basicallt , so yh might need to adjust if certain activities take more workers

19
Q

What does resolute historysm show you and what can you do by fiddling around

A

It shows that if you delay an activity to another day maybe, then maybe overal you’ll only need less workers to complete whole project which is goooood

20
Q

For finding floats of non critical activities, how to identify what to pick
First what to do

A

Circle the whoel activity and then do it on thr two arcs connecting this (even if THEY HAVE CRITICAL THINGS IN THEM)

Identify critical activities first , then get rid of them

21
Q

What is often an assumption when modelling days etc for duration?

A

Thst all the activities take a WHOLE NUMBER amount of days

22
Q

Remember what are the definitions of early and late start time

A

Earliest and latest time whole activity can start without affecting the overall PROJECT LENGTH

23
Q

What can an activity interfering with other activities do

A

Can ALLOW them to start later if it itself starts later, or force something to finish earlier

24
Q

What is critical activity and path significance to whole project again

Thus how can you change the overall length time if you could change an acitivityn

IMPORTWNT WHAT TO LOOK OUT FOR

A

These are activities that must start and finish at set times or thr whole activity will overrun, so they are decisive ones

If you could change an activity , then pick the one in the critical path as these affect the whole length of project.
- IN PARTICULAR IF THERE ARE MORE THAN ONE CRITICAL PATH, PICK THR ACTIVITY THAT HOPEFULLY FALLS UNDER BOTH PATHS, so that changing this will change both paths which thus change the length of project

25
How to draw cascade properly after experience
Do the critical Then everything else goes in ALPHABETICAL ORDER downwards from top And make it easier for yourself, instead of calculating floats just check Kate time and mark it using the x axis be really quick
26
How to show or check if whole project can be completed by 2 workers three workers etc
Calculate time of whole tasks combined Then the whole project length (because this is the max that if you fit each activity perfectly the duration a worker will spend ) Now multiply project length by workers and see if that first the total amount of time the task is
27
If they increase length time of the project how to find routes to finish the project with less workers?
The start times should add up to the project time exactly, that’s how you can manipulate So if project time now 56, need two routes with workers starting directly after each other that will add clean to make 56
28
HOW TO FIND THE LONGEST AND SHORTEST ROUTE FROM A TO B OF A NETOWRK IMPORTANT
Longest = forward backward pass method, will give the length time which equal to LONGEST LENGTH, and the paths are the critical pathways Shortest = USE DIJKSTRA method to get length and path. The path to B will clearly be visible !!!!