Critical path analysis 3.3.4 Flashcards

1
Q

What is critical path analysis?

A

A project management tool that identifies the most efficient and cost-effective way of completing a complex project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What does it involve?

A
  • list of all activities required to complete the project
  • the time that each activity will take
  • the order the activities must be completed
  • the earliest and latest each project can start and finish without delaying completion
    activities that can be completed simultaneously
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Calculating EST

A

Working forward from node 1 it is possible to calculate the EST for each activity by adding the duration of each task

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Calculating LFT

A

Working backwards from the last node it is possible to calculate the LFT for each activity by subtracting the duration of each task

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Calculating float time

A

Float time exists where there is a difference between EST and LFT. Managers may transfer resources as there is extra time to complete these tasks.
Float = LFT- duration - EST

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Identifying the critical path

A

If any critical activities are delayed the project as a whole will be delayed. The critical path follows nodes where the EST and LFT are equal.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Limitations of Critical Path Analysis

A
  • very complex projects involve a very large number of activities
  • network analysis often relies on estimates and forecasts
  • does not guarantee success
  • resources may not prove to be as flexible when float periods are identified
How well did you know this?
1
Not at all
2
3
4
5
Perfectly