CVCS (Chemical Volume Control System) Flashcards
(38 cards)
VCT Volume (e.g. % per gal)
41.26 gal/%
VCT level is 45%
RWT to charging pump suction valve (CHN-UV-536) is open
VCT outlet valve (CHN-UV-501) is closed
Which of the following describes the interlock between CHN-UV-536 and CHN-UV-501?
A. UV-501 will automatically open following a manual closure of UV-536.
B. UV-536 auto opens on a loss of power to UV-501.
C. UV-536 will auto open whenever UV-501 is closed.
D. UV-536 will auto open whenever UV-501 is opened.
A. UV-501 will automatically open following a manual closure of UV-536.
Which one of the following describes the sequence of events when a low level of 5% occurs in the volume control tank?
A. Letdown is automatically diverted from the volume control tank to the pre-holdup ion exchanger.
B. Charging pump suction will come from a boric acid makeup pump that will automatically start.
C. Charging pump suction will come from a reactor makeup water pump that will automatically start.
D. Holdup pumps will secure if the holdup pump to the reactor drain filter valve (CHN-V686) is open.
B. Charging pump suction will come from the boric acid makeup pump that will automatically start.
Which one of the following will cause an auto open of the RWT to Charging Pump Suction Valve CHE-UV-536?
A. A low-low (5%) VCT level Only.
B. A loss of power to UV-514 Only.
C. A low-low (5%) VCT level and a loss of power to UV-514.
D. UV-501 is taken to close position with UV-514 closed.
C. Low-Low (5%) VCT level and loss of power to UV-514.
Unit is at rated power.
Seal Injection is isolated to the RCPs due to a leak in the Aux Building.
Which of the following describes the effect (if any), that this has on the RCP Temps?
A. Isolating Seal Injection should have NO impact on the seal temperatures.
B. HP Seal Cooler inlet temperature will rise to between 200F and 220F, all other seal temperatures should increase by about 70F.
C. HP Seal Cooler inlet temperature should remain relatively constant, while all other seal temperatures should increase by about 70F.
D. HP Seal Cooler inlet temperature will rise to between 200F and 220F while all other seal temperatures remain normal.
D. HP Seal Coil inlet temperature will rise to between 200F and 220F while all other seal temperatures remain normal.
Unit is at 100% power.
NC surge tank level is rising.
RU-6 process monitor is in alarm.
What would be indicative of a RCS leak in the letdown heat exchanger?
A. Back pressure control valve closing.
B. Back pressure control valve opening.
C. Indicated letdown flow increasing.
D. NC flow from the heat exchanger decreases.
A. Back pressure control valve closing.
Unit is operating at 100% power.
The chemical and volume control system is in its normal lineup.
Which one of the following would occur if letdown heat exchanger outlet temperature exceeds 135F?
A. Seal injection flow would decrease.
B. Letdown flow would isolate.
C. Volume control tank level would increase.
D. Charging flow would increase for additional cooling.
B. Letdown flow would isolate.
Plant conditions require IMMEDIATE boration.
RCS pressure is 2230 psia.
RWT level is 65%.
Which ONE of the following methods is available for immediate boration?
Align Charging pump…
A. Suction to the RWT through CHE-UV-536.
B. Suction to the RWT through CHN-UV-514, ensuring a BAMP pump is operating.
C. Suction to the RWT through CHN-UV-514, ensuring the Boric Acid Makeup filter is bypassed.
D. Alternate suction through CHB-V327.
D. Alternate suction through CHB-V327.
Valve is in East Mech Pen. Down the ladder
Plant conditions are such that shutdown margin is less than required. Regarding the use of gravity feed from the Safety Injection System through CH-V327 to the charging pumps, which one of the statements is correct?
A. When the RWT Lvl reaches 40%, a CHG pump low suct trip will occur.
B. The RWT Lvl must be above 73% if this flow path is used to ensure CHG pump suction.
C. Manual valve operations must be performed outside the control room.
D. In order to satisfy TS req., the boration flow rate must be 50 gpm.
C. Manual valve operations must be performed outside the control room.
An emergency boration is required and the path through CHN-UV-514 has been chosen. If the BAMPs are not available, which additional valve must be opened to ensure adequate NPSH exists for the charging pumps?
A. CHN-V164
B. CHN-V144
C. CHN-UV536
D. CHN-UV514
A. CHN-V164
Location is 120’ behind block wall
When using the Spent Fuel Pool (SFP) as a source for emergency boration, why must CHN-HV-532 be closed?
A. The SFP boron concentration is higher than RWT.
B. PC Clean-up must be isolated if the valve is left open.
C. A gravity flow path would be established between the SFP and RWT.
D. Three charging pumps cannot run on the SFP with the valve open.
C. A gravity flow path would be established between the SFP and RWT.
CHN-UV-510 will close when CHN-FIC-210Y indicates flow of….
A. 3 GPM
B. 2 GPM
C. 20 GPM
D. 10 GPM
C. 20 gpm.
CHN-UV-510 (re-circ for BAMPs to RWT).
Unit is at 100% power.
Dilution to the RCS is in progress to raise temperature.
CHN-FIC-210X is in auto with an output of 50%.
The unit experiences a loss of NNN-D11.
After NNN-D11 has power restored, CHN-FIC-210X will be in….
A. Manual with 0% output.
B. Auto with 0% output.
C. Auto with 50% output.
D. Manual with 50% output.
A. Manual with 0% output.
The VCT outlet valve (CHN-UV-501) can be operated from the Control Room…
A. ONLY
B. And locally at PHA-M35
C. And the Remote Shutdown Panel
D. And locally at NHN-M72
D. And locally at NHN-M72
Unit is at 100% power in a normal lineup.
The MCC that supplies power to CHN-UV-514 is de-energized.
If a lo-lo level in the VCT now occurs, what is the status of the following valves?
CHN-UV-501, CHE-HV-536, CHN-UV-514
A. Open, Open, Closed
B. Closed, Open, Closed
C. Open, Closed, Closed
D. Closed, Closed, Open
B. Closed, Open, Closed
The Refueling Water Tank is designed to provide full flow of all Engineered Safety Feature pumps for at least ______ (plus 10% margin) prior to reaching a low level switchover to the sump for recirculation.
A. 10 minutes
B. 20 minutes
C. 30 minutes
D. 1 hour
B. 20 min.
Note: RWT is 7500 gal/%
Unit is at 100% power with letdown in service.
A large break loss of cooling accident occurs resulting in a reactor trip.
Pressurizer pressure is 1750 psia and lowering.
What is the status of the following valves?
CHB-UV-515, CHA-UV-516, CHB-UV-523
A. Open, Open, Open
B. Closed, Closed, Open
C. Open, Closed, Closed
D. Closed, Closed, Closed
D. Closed, Closed, Closed
Note: SIAS occurs at <1837 giving a CIAS
What following ESFAS actuations could result in RCP Controlled Bleed Off being directed to the Reactor Drain Tank?
A. Containment Spray Actuation Signal
B. Containment Isolation Actuation Signal
C. Safety Injection Isolation Signal
D. Recirculating Actuation Signal
A. Containment Spray Actuation Signal.
What is the CHG pump requirement for TLCO 3.1.103 and requirement for Modes 1-4?
A. At least one charging pump shall be OPERABLE
B. At least two charging pumps shall be OPERABLE
C. At least one charging pump and one high pressure safety injection pump shall be available
D. At least two charging pumps shall be available
B. At least two charging pumps shall be OPERABLE.
Which of the following will NOT result in a BLUE light on Boric Acid Make-up Pump hand switch CHN-HS-207?
A. RWT level Lo-Lo
B. Loss of control power
C. Low discharge pressure trip
D. Low suction pressure trip
D. Low suction pressure trip
CHN-HS-4 Charging pump mode selector switch is in 1-2-3 position.
A fault occurs on ESF Transformer NBN-X03
After 1 minute what is the status of the charging pumps?
A. All charging pumps are stopped and in an anti pump condition
B. A and B charging pumps are running, E is stopped
C. A charging pump is stopped in an anti pump condition, B charging pump is running
D. All charging pumps are running
C. A charging pump is stopped in an anti pump condition, B charging pump is running.
(Note: LOP means that a loss of power to a PB bus. Since the normal power was not lost the A is in an anti pump condition due to a locked in start signal. The B pump is running because it never lost power)
Which one of the following failures would result in a loss of letdown with no operator action?
A. Thot input to reactor reg fails high, Tavg selected to average.
B. Selected PZR pressure input to PPCS fails high.
C. Tcold input to reactor reg fails high, Tavg selected to average.
D. Selected PZR pressure input to PPCS fails low.
B. Selected PZR pressure input to PPCS fails high.
Note: Spray Valves open causing pressurizer pressure to lower giving a SIAS (1837 psia).
An event has occurred that requires emergency boration.
The crew has established boration through CHN-UV-514 (Boric Acid Makeup to Charging Pumps) with boric acid makeup pump running.
Subsequently
NHN-M1528 (Power to CHN-UV-514) trips open.
CHN-LT-227 (VCT level transmitter) fails LOW.
CHN-LI-226 (VCT Level) reads 48%.
Which ONE of the following describes the impact of these conditions on the emergency boration flow path?
A. The crew must manually open CHE-UV-514 to establish an emergency boration flow path.
B. The crew must manually open CHE-HV-536 to establish an emergency boration flow path.
C. The emergency boration flow path will be maintained through a single suction flow path (via CHN-UV-514) to the charging pumps.
D. The emergency boration flow path will be maintained through two suction flow paths (via CHN-UV-514 and CHN-HV-536) to the charging pumps.
D. The emergency boration flow path will be maintained through two suction flow paths (via CHN-UV-514 and CHN-HV-536) to the charging pumps.
Unit 1 is at 100% power.
Alarm VCT TRBL (3A09A) actuates.
The RO notes the VCT pressure is 5 psig and lowering slowly.
Which ONE of the following identifies (1) the required action (2) the reason for the action?
A. (1) raise Hydrogen pressure (2) to prevent water from flashing inside the VCT
B. (1) raise Hydrogen pressure (2) to maintain charging pump NPSH
C. (1) raise Nitrogen pressure (2) to prevent water from flashing inside the VCT
D. (1) raise Nitrogen pressure (2) to maintain charging pump NPSH
B. (1) raise Hydrogen pressure (2) to maintain charging pump NPSH