D1, C8 - Critical Path Analysis Flashcards

(40 cards)

1
Q

What goes in the two columns of a precedence / dependence table

A

Column 1 - Activity (A, B, …)
Column 2 - Dependence (what the activity depends on)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What type of graph can you display a precedence / dependence table on

A

An activity network

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the node at the start and the node at the end of an activity network called

A

Start - source node
End - sink node

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What does it mean if an activity network is an ‘activity on arc’ network

A

The activities are on the arcs (between nodes) as opposed to ‘activity on node’ networks where the activities take place on the nodes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How do you number nodes on an activity network

A

Number them as they are added to the network (chronological order)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What does a dummy activity show

A

Precedence

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Do dummy activities incur a cost or time

A

NO

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

When do you get dummy activities

A

When an activity (C) is dependent on just one other activity (A), but another activity (D) is dependent on the same activity as C (A) but also another activity (B)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How do you draw dummy activity lines

A

Dotted lines

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the time it takes to complete an activity called

A

Its duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is an early event time

A

The earliest time an activity can start / finish

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is a late event time

A

The latest time an activity can start / finish

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How do you show early and late times on an activity network

A

Replace nodes with two boxes, top box is the early event time, bottom box is the late event time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What numbers go in the early and late time box for the source node

A

0, 0

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What numbers go in the early and late time box for the sink node

A

The SAME number

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

How do you find the early event time

A

Perform a forward pass/scan
Longest time to finish

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

How do you find the late event time

A

Perform a backward pass/scan
Shortest time to start

18
Q

For a forward pass do you pick the highest or lowest option

19
Q

For a backward pass do you pick the highest or lowest option

20
Q

What is a critical activity

A

An activity which will delay the finish time of the project if it is delayed

21
Q

What is a critical path

A

A path which goes from the source node to the sink node only through critical activities

22
Q

What is true of the early event time and late event times for a critical activity

A

They are equal
Early event time = late event time

23
Q

Where do critical activities often (not always) happen between

A

Between critical events

24
Q

Can you have multiple critical paths

25
What is the float of an activity
The amount of time that the start of the activity may be delayed by, without delaying the finish time of a project
26
How do you calculate the total float for an activity
Total float = latest finish time - duration - earliest start time
27
What do Gantt (or Cascade) charts show
The activities on a network
28
What do solid rectangles represent on Gantt charts
Activities
29
What do dotted lines represent on Gantt charts
Delays to activities (floats)
30
Where do you put critical activities on a Gantt chart
On the top row
31
What do resource histograms display
The number of workers needed for an activity
32
How many activities can one worker be assigned to on a resource histogram at a time
1 activity at a time
32
When can workers stop their activity on a resource histogram
When they have finished it
33
How long after finishing an activity does it take for a worker to start a new activity on a resource histogram
Immediately available
34
What is levelling with resource histograms
The process of adjusting the start / finish of activities to take into account any constraints on resources
35
What goes in the x and y axis for a resource histogram
y = number of resources needed per activity (workers) x = time needed per activity (days / hours / etc)
36
For scheduling diagrams how many workers are assumed to be required per activity
One worker assumed to be required per activity
37
For scheduling diagrams which worker do you use
The first available worker
38
For scheduling diagrams, if we can choose more than one activity to assign a worker to, which activity do you choose
Choose the activity with the lowest last time
39
What is the formula to calculate the lower bound for the number of workers needed to complete a project by its critical late time
Lower bound = (sum of all activity times) / (critical time of the project) (take the smallest integer >= the answer)