Damages Flashcards
(44 cards)
What are damages?
Monetary compensation for loss in a contract
What terms , when breached, can damages be claimed?
- Condition - if this is breached the innocent party can terminate the contract and claim damages
- Warranty - If this is breached there is no repudiation but the innocent party can claim damages
What considerations are necessary if it is an anticipatory breach?
Consider if it is better to :
* affirm the contract and claim payment
or
* accept the breach and sue for damages
What is the purpose of awarding damages?
Either to compensate or deter
What did Lord Reed say about the purpose of damages and in which case?
In Morris-Garner and another v One Step (Support) Ltd (2018)
“Damages… are therefore intended to place the claimant in the same position as he would have been in if the contract had been performed”
What losses are not recoverable?
- If the causation is too remote
- If there is mitigation
- If there are contractual terms that stipulate what amount can be recovered if a breach occurs
When are damages normally assesed? Give a case law example
At the time of breach - Johnson v Agnew (1980)
What is the case that shows this is not an inflexible rule?
**Hooper v Oates (2013) **
What are the two actual measures of damages?
- Expectation Loss
- Reliance Loss
What did Parke B say expectation loss was?
“The rule of the common law is that where a party sustains loss by a breach of contract he is , so far as money can do it, to be placed in the same situation … as if the contract had been performed”
Give a case law example of expectation loss
Radford v De Frobille (1971)
- Plaintiff obtained planning permission to build a house on a plot of land forming part of the grounds of his existing house
- Plaintiff property was subdivided and then the subdivided plot was sold to the Defendant
- Condition of sale: Defendant would build a house, subject to an agreement to erect a wall on the purchased plot, to divide it from Plaintiff’s land
- Defendant built neither house nor wall and sold the plot to a third party, who also failed to build anything
Held:
* Correct measure of damages = cost to Plaintiff of erecting a wall to the contract specification on his own land and NOT amount by which Plaintiff’s land was diminished by the absence of the wall
Give a case law example of expectation loss + basis of calculation
C and P Haulage Co Ltd v Middleton (1983)
- Middleton had a licence to occupy C&P’s premises for 6 months, provided that at the end of the 6 months, any improvements added to the building were not removed
- He improved the property, even though the contract stated fixtures were not to be removed
- C&P ejected him for breach of contract and Middleton argued he should be entitled to damages for the cost of the improvements he had made
(After the breach, Middleton moved back to his house rent free)
Held:
* He would be unjustly enriched if damages were awarded
* At the end of the 6 months, he would have had to leave the “improvements” anyway , as per the licence, and, in any case, he moved back to his house rent free
Give a case law example of “cost of cure”
Watts v Morrow [1991]
- Plaintiff bought house for £177,500 relying on survey report that house was sound and in good condition
- True value of the house at date of purchase was £162,500
- After taking possession, Plaintiff discovered substantial defects
- Plaintiff spent £ 33,961 to put right the defects
- Plaintiffs brought action claiming the cost of repairs
Held:
- Proper measure of damages = diminution in value of the house (ie: £177,500 - £ 162,500), rather than just the cost of the repairs
- Plaintiff bought house for £177,500 relying on survey report that house was sound and in good condition
- True value of the house at date of purchase was £162,500
- After taking possession, Plaintiff discovered substantial defects
- Plaintiff spent £ 33,961 to put right the defects
- Plaintiffs brought action claiming the cost of repairs
Held:
- Proper measure of damages = diminution in value of the house (ie: £177,500 - £ 162,500), rather than just the cost of the repairs
Give a case law example of “cost of cure” and loss of amenity
Amenity = enjoyment of life
Ruxley Electronics and Construction Ltd v Forsyth [1995]
- Forsyth contracted Ruxley to build a swimming pool on his property to a depth of 7 feet 6 inches, which specified pool should have a diving area 7 feet 6 inches deep
- On completion, pool was suitable for diving but diving area was only 6 feet deep BUT there was no adverse effect on the overall value of the property
- Estimated cost of rebuilding the pool to the specified depth was £21,560
Held (House of Lords):
- Cost of cure was wholly disproportionate to the diminution in value and to any loss of pleasure/amenity to the claimant from having the deeper pool
- Court considered Claimant’s intention and was not convinced that if £21, 560 were awarded, the full amount would be spent on rebuilding the pool
What is Reliance loss?
Basis for compensation= the claimant alters their position in reliance on the defendant’s promise
Give a case law example of reliance loss
Anglia Television v Reed [1972]
- Reed, a well known actor, contracted to appear for Anglia to play the lead in a play
which they were producing - Reed wrongfully repudiated the contract and Anglia was forced to abandon the production
- Anglia claimed their total wasted expenditure
- Reed contended that they were entitled only to their expenditure after the contract
was concluded
Held:
Anglia could claim expenditure incurred before the contract as Reed must have known that the expenditure, whether incurred before or after the contract was made, would have been wasted if he broke his contract (i.e. Anglia acted in reliance on Reed starting the contract)
In your own words and in summary what is ‘expectation loss’ and ‘reliance loss’
Expectation loss
* Put the claimant in the position as if the promise had been kept
* Looking forward
* What loss does the claimant have because his expectations are not fulfilled?
Reliance loss
* Put the claimant in the position as if the promise has never been made
* Looking backwards
* What cost did the claimant have because he relied on the promise?
What is Causation?
The link between the contract and the loss
What is remoteness?
The loss being too far from the contract
What happened in the Hadley v Baxendale (1854) and what was the judgement?
**Hadley v Baxendale (1854) **
* A mill had ceased to work because of a broken crankshaft
* Miller did not keep a spare * Broken machinery sent to manufacturer as pattern for new one * Claimant contracted with Defendant carriers * Defendants, in breach of contract, delayed delivery of the crankshaft by 5 days, and there was a lengthy stoppage at the mill , which could not operate without this piece of equipment * Claimants sued for the loss of profit caused by the delay Held: * Claimant not entitled to recover as had not provided Defendants with adequate instructions re: urgency of delivery
In your own words explain what Alderson B said about the awarding of the damges
- Damages should be awarded “fairly and resonably” arising naturally from the usual course of things when a breach has occurred ,as contemplated by both parties, for when a breach occurs
- If there are special circumstances and this was comminicated by the plaintiffs to the defendants then the damages woud be the amount of injury within the context of these expressed special circumstances
This created the two lib test for remoteness
What is the two-limb test for remoteness?
- Damages are reasonably considered as arising naturally from the breach of contract
- Special circumstances were reasonably within the contemplation of the parties when the contract was made
Give a case law example of damages being reasonably considered as arising naturally from the breach of contract
**South Australia Asset Management Corp v York Montague [1996] **
- Case concerned 3 joined appeals - in each case claimant banks instructed defendant valuers to provide valuations of property intended as security for loans to prospective purchasers
- Loans were made based on these valuations
- BUT: the loans would not have been made if the claimants had known true value of properties!
- Borrowers subsequently defaulted and in meantime, property market fell substantially, greatly increasing losses eventually suffered by the claimants
Held:
* Valuation is seldom an exact science BUT once valuer found to have been negligent, loss for which he is
responsible is that which has been caused by the valuation being wrong
* However, damages for negligent valuations are limited to the foreseeable consequences of that advice and do not extend to include losses arising from a general fall in value
Give a case law example of special circumstances being reasonably within the contemplation of the parties when the contract was made
**Victoria Laundry (Windsor) Ltd v Newman Industries Ltd [1949] **
- On April 26, 1946, claimants (Victoria Laundry) concluded a contract with defendants (Newman) to purchase a boiler and delivery was arranged for June 5, 1946
- While the boiler was being dismantled by third parties, it rolled over and sustained damage, so delivery was delayed until November 8, 1946
- Defendants were aware of the nature of the claimants’ business, and had been informed the claimants intended to put the boiler in use in the shortest possible space of time, due to the nature of their business
Held:
Damages for loss of profit were recoverable, as defendants knew they were selling to a laundry company and would have foreseen that a delay of 5 months was likely to result in financial loss