Days Flashcards
(48 cards)
3 days (insurance)
Bonds to be delivered to owner after execution of contract
A701 7.2
3 days (insurance)
Owner - contractor both ways; inform of findings that require insurances will be cancelled or expired (3 business days)
A202-11.1.4 / 11.2.3
4 days (bidding)
Addendums no later than 4 days prior to bidder
A701-3.4.3
7 days (bidding)
RFIs submitted to architect prior to the bid due date
A701-3.2.2
7 days (bidding)
Owner to furnish reasonable evidence that financial arrangements have been made prior the the time of the withdrawal of bids
A701-6.2
7 days (legal)
Liens
Arch to request info from owner for consultants to evaluate, give notice or enforce lien rights within 7 days of written request.
Also arch furnishes info obtained to consultants
C401-5.9
7 days (suspension)
If arch elects to suspend services, arch should notify the owner within 7 days written notice.
B101-9.1
7 days (termination)
Owner - architect can terminate agreement with not less than 7 days written notice if other party fails to perform in accordance with contracts
B101-9.4
7 days (termination)
Owner can terminate agreement for convenience with not less than 7 days written notice
B101-9.5
7 days (info)
Receiving party may disclose confidential information to the other party.
A201-2.2.4
B101-10.8.1
7 days (payment)
Arch issues certificate of payment to owner, 7 days after receiving contractor’s application for payment.
A201-9.4.1
7 days (payment)
Contractor to pay subs within 7 days of receiving payment from owner.
A201-9.6.2
And provides evidence of this payment to the owner upon his request
A201-9.6.4
7 days (payment)
Owner to pay contractor within 7 days of date established within the contract docs.
A201-9.7
7 days (stop)
Contractor may stop work within 7 days notice if arch fails to issue cert. of payment or owner fails to pay contractor within time limits
A201-9.7
7 days (termination)
Contractor must provide additional 7 days written notice if they want to terminate contract due to owner’s failure to fulfill obligations.
A201-14.1.4
7 days (termination)
Owner may terminate for cause with 7 days written notice
A201-14.2.2
10 days (bidding)
Bidding docs deposit refunded to bidders who return the papers of bidding docs in good condition
A701-5.1.2
10 days (bidding)
Submit substitutions prior to bidding date
A701-6.2
10 days (notice)
Owner and contractor can change rep. After 10 days written notice
A101-8.4
Same for owner and design builder
A141-1.2.5
10 days (billing)
Arch to review issues with consultants invoices within 10 days of receiving the invoice
C401-11.6
10 days (correction of work)
If contractor fails to correct the work after 10 days notice from the owner, the owner can carry out the correction of the work.
A201-2.5
10 days (payment)
10 days for contractor to submit application for payment prior to established progress payment date
A201-9.3.1
10 days (claims)
IDM to review claims within 10 days of claim reviewed.
If IDM needs info, party to respond within 10 days
A201-15.2.2 & 15.2.4
14 days (bidding)
Bidder can request the owner to provide evidence that financial arrangements have been made to fulfill owner’s obligations to bidders, prior to withdrawal of bids.
A701-6.2