Design Economics Flashcards
(133 cards)
What is BIM?
a. Building information modelling
b. Shared management approach to the use of shared, structured data to design, deliver & use buildings
What are the benefits of BIM?
a. De-risks construction phase for the contractor / client
b. Built in £D before real = coordination improvements = SAVINGS
c. Incorporate construction materials & models to confirm buildability
d. Visualisation facilitates effective collaboration
e. Modelling efficiencies
f. Automated updates on drawings which impact measures, rates etc. with no further input from user
What is a cost plan?
a. A critical breakdown of the cost limit for the building into cost targets which would typically be organised elementally and issued at the key RIBA stages.
b. Guides the design team to distribute the available budget among the elements of the building
What are the challenges with BIM?
a. Cost of software & training
b. New way of working for all
c. Availability & quality of information
d. Change control & quality control
e. Design liability issues
f. Working protocols required
g. Supply chain integration & collaboration
How is BIM going to influence you as a QS?
a. Efficiencies in working
What are capital allowances?
a. Form of tax relief that can be claimed against capital expenditure on certain types of fixed asset
What are the levels of BIM?
a. Level 0 - unmanaged CAD
b. Level 1 - managed CAD in 2D & 3D
c. Level 2 - managed 3D environment with data attached, but created in separate models
d. Level 3 - single, online, project model with construction sequencing (4D), cost information (5D) and life cycle management (6D)
Can you describe some non-physical aspects of a cost plan?
a. Main contractor prelims
b. Main contractor OH&P
c. Project / design team fees
d. Development costs e.g. insurance, planning fees, section 106
e. Risk allowances
f. Inflation
g. Capital allowances / land remediation
What is a cost estimate?
a. Can be carried out any time to provide the client or design team with a high level budget (e.g. variation)
What is a formal cost plan stage?
What is a formal cost plan stage?
What are the MC OH&P?
a. MC costs associated with head office administration & return on capital investment which is apportioned to the building contract
What are preliminaries?
a. Expenses the contractor will incur during construction, which are directly related to the running of the project and have not been included in the materials,
labour or overheads
What are estimating methods for building works in a cost estimate?
a. Floor area
b. Functional Unit method
c. Elemental Method
What is the purpose of a cost plan?
a. Ensure that employers are provided with value for money
b. Ensure all parties are aware of cost consequences of their desires
c. Provide advice to designers to enable them to make informed decisions
d. Keep to cost limit
e. Provide robust cost information for client to make informed decisions
What are the formal cost planning stages?
a. Stage 2 - Concept Design
b. Stage 3 - Spatial Coordination
c. Stage 4 - Technical Design
d. Employer is required to sign off each cost plan before authorising commencement of next stage
What occurs at stage 2?
a. Scope of works fully defined
b. Condensed list of elements & sub elements
c. Where inefficient information GIFA method used
d. Alternative concept design considered
e. Specification purely indicative
What occurs at stage 3?
a. Progression of design
b. Developed by checking cost of significant cost targets for elements as more information received
c. Schematics / spec
What occurs at stage 4?
a. Based on technical designs, spec & detailed information for construction
b. Provide reference for appraising tenders
What information do you need to form a cost plan?
a. Building tenure
b. Location
c. When is it being built / indicative timeline
d. Area schedule
e. Storey height / number of stories
f. Level of fit-out
How did you produce a cost plan?
a. Measurement of elemental areas using NRM
b. Costing - unit rates, inflation / benchmarking, if design limited used floor area
c. Apply on costs & risk allowance (MC prelims 11-16%, DD contingency 3-5%, Client other 3-5%
d. Present costs in elemental breakdown
How did you deal with risk in your cost plan?
a. Evaluating the project with risk management
b. Mechanisms to deal with risk (e.g. risk register, monte carlo techniques, central limit theorem)
What are the different types of cost data for a cost plan?
a. BCIS data
b. Previous estimate
c. Budget cost plans
d. Research papers
e. Price books
What are typical inclusions for a cost plan?
a. Exec summary / client brief
b. Area schedule
c. Elemental cost breakdown
d. Prelims
e. Basis of estimate & base date
f. Assumptions, inclusions, exclusions
What are typical cost plan exclusions?
a. VAT
b. Fees
c. Statutory authorities
d. FFE
e. Land costs
f. Capital allowances
g. Client contingency
h. Building regulations