Develop and Manage a Project Schedule Flashcards
1
Q
Contingency Reserves
A
Money allocated in the cost baseline
2
Q
Management Reserves
A
Amount of the project budget held outside of the baseline
3
Q
A
Contingency Reserves
Money allocated in the cost baseline
Management Reserves
Amount of the project budget held outside of the baseline