discharge Flashcards

1
Q

Sumpter v Hudges

A

P builder contracted to build
2 houses & stables for D Hedges for 565, works completed valued at 333, explained he had run out of money & had to stop, D finished the building using materials left behind by P and P sued for the money, held P had abandoned the contract, he could recover the value for the materials but not for the work as he left the D no option

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Sumpter v Hudges; Collins LJ

A

held that where the defendant is given the option to accept incomplete performance, she will be made to pay for it where she has accepted it as the courts
will find the existence of a new contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Nash & Co v Hartland

A

the question of whether a contract is entire is matter of construction, if the contract expressly/implicitly states precise and exact performance is required before an obligation to pay arises, the contract is entire

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Cutter v Powell

A

sailor engaged on voyage to Jamaica, promised 30 guineas on completion but died en route, widow sought payment proportionate to amt of voyage completed, rejected as the contract was intedned to be an all or nothing proposition, the obligation to pay only arose after performance was complete

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Collen v Marum

A

house was to be built for a fixed sum, held part-payment would not be available to the builder on the basis of part-performance as the employer is not bound to pay for half or quarter of a house

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Boone v Eyre

A

where a contract has been performed with minor deviations, payment will be due less the amt required for such deviations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Hoenig v Isaacs

A

builder contracted to renovate flat for 750, neglected to put in agreed bookcase for 55, substantial performance had been achieved, builder owed 750 - 55, Denning LJ substantial compliance will ordinarily take place unless the breach goes to the heart of the contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Bolton v Mahadeva

A

contract to install heating for 560, defects meant system didn’t work, repairs cost 130, held due to the nature of the breach and the high cost of remedy, builder was not entitled to any payment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

McDermott (SP)

A

doctrine of substantial performance is limited as it depends on the interpretation of the contract and parties can simply exclude it by expressly providing nothing but total compliance will suffice

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

McDermott (RB)

A

repudiatory breach is where the defaulting party makes clear their intention not to perform their side of the bargain

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Eminence Property Develpments v Heany

A

held the test for RB is whether a reasonable person would think the defaulting party is abandoning the contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Berber v Dunnes

A

held the ‘cummulative effects’ of the acts complained of must be such as to indicate the party has repudiated the contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Athlone RDC v Campbell (RB)

A

P were contracted to excavate a well, after dispute with council they said theyw oudl no longer complete the work, held to be RB as D indicated no intention of meeting obligations under the contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Decro Wall International

A

consistent late payments not sufficiently serious to amount to RB

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Hochstery De La Tour

A

held a statement of intent not to perform is a breach of contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Carter v McGregor

A

D garage entered contract with P to place ad on local authority bins for 3 yrs, D communicated to cancel the contract on the same day it was made, P ignored & began advertising which D refused to pay for, HOL held the innocent party cannot choose whether he will accept repudiation and sue for damages for AP or elect to continue the contract

17
Q

Universal Cargo v Citati

A

held AP covers all breaches that are bound to happen

18
Q

Leeson v North British Oil

A

if a party genuinely believes he is complying with the contract they will not have the necessary intention to breach the contract

19
Q

Hong Kong Firs

A

Lord Diplock stated the test is wether the breach of the term is such as to deprive the party of substantially the whole benefit of the contract as intended by the parties

20
Q

Dundalk Shopping Centre v Roof Spray

A

D hired P to spray protective surface on roof, negligently done, roof leaked, held since the core of the contract was to waterproof the roof, P was entitled to bring the contract to an end & sue for damages

21
Q

Leopardstown Club v Templeville

A

dispute between parties, D tried to argue fundamental breach to discharge contract, Charleton J held while there was some lack of attention by Leopardstown the issue could be sorted and therefore fundamental breach does not occur where the breaches are trivial

22
Q

Friel

A

contractual obligations can no longer be performed as a result of external factors which so radically alter the basic assumptions on which a contract is founded that its performance is impossible or futile

23
Q

Paradine v Hane

A

original position was that if parties had agreed to obligations they had to carry them out with no excuses

24
Q

Taylor v Caldwell

A

contract to hire music venue was frustrated when venue burned down

25
Krell v Henry
coronation of Edward VII cancelled due to illness, arrangements to view procession from rooms overlooking route, contract for room for 2 days, contract had no express reference to the coronation process, held the contract had been frustrated, the whole purpose of the contract was the position of the rooms for the procession. ‘It was a licence to use the rooms for a particular purpose and none other’, the procession was regarded ‘as the foundation’ of the contract
26
Krell v Henry (Vaughan William LJ)
held court will find performance of a contract impossible where ‘the non-existence of an express condition or state of things…. is essential to the performance of the contract.’
27
McGuilll v Aer Lingus (test)
1. Party must bind himself to something which subsequently becomes impossible 2. The obligation has become impossible to perform without default of either party 3. The circumstances should be strictly scrutinised as this doctrine is not to be lightly applied 4. Where frustration has arisen due to the conduct of one party – that party cannot rely on the doctrine 5. All the circumstances of the contract should be strictly scrutinised 6. The event must be unexpected 7. If one party anticipated / should have anticipated the event and didn’t anticipate a clause in the contract to deal with it – he cannot rely on the doctrine of frustration
28
Zuphen v Kelly
Murphy J, there must be a change in circs that if performed the contract would be a different thing from what was contracted for
29
Herme Bay Steam Boat v Hutton
D hired boat as means of watching naval review during coronation, review was cancelled when king fell ill, D refused to pay balance owed on contract, held contract still enforceable as the purpose of viewing the ships was still possible – unlike in Krell the contract was not directly linked to the physical presence of the king, boats could still be viewed
30
Browne v Mulligan
contract of employment provided that the employment would only continue provided there was sufficient funding available, hospital ran into difficulty, sought to have contract set aside, SC held where the eventuality has been specifically provided for in a contract the doctrine of frustration cannot apply
31
Canary Wharf v European Medicine Agency
EMA took out long lease, as it is a European institute, they argued contract had been frustrated by Brexit, at time of lease UK leaving EU not foreseeable held contract not frustrated as no evidence it was the ‘common purpose’ of the lease
32
Constantine Line v Imperial Smelting
vessel exploded and sank however this didn’t frustrate the contract of charter as it was due to negligence of shipowners
33
Abbleby v Myers
contract was to install machinery, sum agreed, before completion fire destroyed premises, P sought payment for work done held the obligation to pay only fell due after completion, since this was a future obligation at the date of the frustrating event, it was discharged
34
Fibrosa v Myers
where party to contract can show there was no tangible benefit from the contract or there has been a total failure of performance under the contract, P will be entitled to the return of money