discharge Flashcards
Sumpter v Hudges
P builder contracted to build
2 houses & stables for D Hedges for 565, works completed valued at 333, explained he had run out of money & had to stop, D finished the building using materials left behind by P and P sued for the money, held P had abandoned the contract, he could recover the value for the materials but not for the work as he left the D no option
Sumpter v Hudges; Collins LJ
held that where the defendant is given the option to accept incomplete performance, she will be made to pay for it where she has accepted it as the courts
will find the existence of a new contract.
Nash & Co v Hartland
the question of whether a contract is entire is matter of construction, if the contract expressly/implicitly states precise and exact performance is required before an obligation to pay arises, the contract is entire
Cutter v Powell
sailor engaged on voyage to Jamaica, promised 30 guineas on completion but died en route, widow sought payment proportionate to amt of voyage completed, rejected as the contract was intedned to be an all or nothing proposition, the obligation to pay only arose after performance was complete
Collen v Marum
house was to be built for a fixed sum, held part-payment would not be available to the builder on the basis of part-performance as the employer is not bound to pay for half or quarter of a house
Boone v Eyre
where a contract has been performed with minor deviations, payment will be due less the amt required for such deviations
Hoenig v Isaacs
builder contracted to renovate flat for 750, neglected to put in agreed bookcase for 55, substantial performance had been achieved, builder owed 750 - 55, Denning LJ substantial compliance will ordinarily take place unless the breach goes to the heart of the contract
Bolton v Mahadeva
contract to install heating for 560, defects meant system didn’t work, repairs cost 130, held due to the nature of the breach and the high cost of remedy, builder was not entitled to any payment
McDermott (SP)
doctrine of substantial performance is limited as it depends on the interpretation of the contract and parties can simply exclude it by expressly providing nothing but total compliance will suffice
McDermott (RB)
repudiatory breach is where the defaulting party makes clear their intention not to perform their side of the bargain
Eminence Property Develpments v Heany
held the test for RB is whether a reasonable person would think the defaulting party is abandoning the contract
Berber v Dunnes
held the ‘cummulative effects’ of the acts complained of must be such as to indicate the party has repudiated the contract
Athlone RDC v Campbell (RB)
P were contracted to excavate a well, after dispute with council they said theyw oudl no longer complete the work, held to be RB as D indicated no intention of meeting obligations under the contract
Decro Wall International
consistent late payments not sufficiently serious to amount to RB
Hochstery De La Tour
held a statement of intent not to perform is a breach of contract
Carter v McGregor
D garage entered contract with P to place ad on local authority bins for 3 yrs, D communicated to cancel the contract on the same day it was made, P ignored & began advertising which D refused to pay for, HOL held the innocent party cannot choose whether he will accept repudiation and sue for damages for AP or elect to continue the contract
Universal Cargo v Citati
held AP covers all breaches that are bound to happen
Leeson v North British Oil
if a party genuinely believes he is complying with the contract they will not have the necessary intention to breach the contract
Hong Kong Firs
Lord Diplock stated the test is wether the breach of the term is such as to deprive the party of substantially the whole benefit of the contract as intended by the parties
Dundalk Shopping Centre v Roof Spray
D hired P to spray protective surface on roof, negligently done, roof leaked, held since the core of the contract was to waterproof the roof, P was entitled to bring the contract to an end & sue for damages
Leopardstown Club v Templeville
dispute between parties, D tried to argue fundamental breach to discharge contract, Charleton J held while there was some lack of attention by Leopardstown the issue could be sorted and therefore fundamental breach does not occur where the breaches are trivial
Friel
contractual obligations can no longer be performed as a result of external factors which so radically alter the basic assumptions on which a contract is founded that its performance is impossible or futile
Paradine v Hane
original position was that if parties had agreed to obligations they had to carry them out with no excuses
Taylor v Caldwell
contract to hire music venue was frustrated when venue burned down